PARTIES Brotherhood of Maintenance of Way Employes
TO and

DISPUTE Chicago and North Western Transportation Company

STATEMENT OF CLAIM: "Claim of the System Committee of the Brotherhood that:





FINDINGS: This Board, upon the whole record and all of the evidence, finds that the Employees and Carrier involved in this dispute are respectively Employees and Carrier within the meaning of the Railway Labor Act as amended and that the Board has jurisdiction over the dispute involved herein.

OPINION OF THE BOARD: In its initial claim, the Organization made the following assertions:





                                        Page 2


    "The Carrier failed to provide any notification to the Brotherhood regarding the intent to contract out the work described in this claim. Furthermore, the work involved did not require special skills, equipment or material."


The Carrier responded, asserting that "the dismantled track at Morrison, Illinois was purchased by an outside contractor, and all material was retained by the outside contractor. None of the material was returned to the Transportation Company, in that the material was not owned by the Transportation Company." Accordingly, there was no violation, in their opinion. Subsequently, the Union asked for a copy of the contract with the outside concern. It was not provided until roughly a year later, coincidentally on the same day the Parties advanced the case to the Board.

Before the Board, the organization maintained that the dismantling of track is work specifically reserved to them by virtue of Rule 1 (b). The Carrier continued to argue that because the track was sold "as is, where is," the ownership left the Carrier and, therefore, left the scope of the Agreement.

The first problem with the Carrier's argument is that at the time the work in question was done, the track was owned by the Carrier. The work was performed May 18 and 19. The contract to sell this particular section of track was not consummated until June 1, 1989. There was an earlier basic contract between the Carrier and the contractor, but this merely set the general terms for future agreements over specific sections of track. Because the track was still the Carriers at the time of the dismantling, they cannot hide behind the lack of ownership/control defense. Since the Carrier owned the track and since Rule 1 (b) specifically reserves dismantling work to BMWE forces, a violation of the Agreement was manifest.

Even if we were to get beyond the fact that the track was owned by the Carrier, there is a critical factual dispute which would have to be resolved. In its claim, the organization asserted that the contractor piled up the ties to be removed by the Carrier. The Carrier claimed the contractor removed everything. This would be critical. Selling surplus track and ties (from the top of the rail to the bottom of the tie) is one thing. However, having the contractor dismantle and remove the entire track unit but retaining a portion of it in the ownership, control, and for the convenience of the carrier would violate the
Pwwrd 112- -:)G (o0
Case No. 296
Page 3

Agreement. See Third Division Award 24280, where it was stated
in part:

      "The claim has merit to some degree, however, in that the dismantling and removing performed by the purchaser included work on behalf of the carrier which appears to the Board to be considerably more than incidental to the removal of the purchaser's property.


          "The Organization in its claim states that the

      purchaser was 'taking selected rails and ties and

      piling them for the Milwaukee Road . This

      material is and continues to be Milwaukee Road

      property.' Such contention was not denied by the

      Carrier. In its correspondence, the' Carrier states

      'The contractor may have also found it necessary to

      handle Milwaukee Road property to avoid damage . . .

      while he is attempting to remove his own personal

      property.'


      "Given this state of the facts, the Board finds that the Carrier caused outside forces to perform work customarily and normally performed by Maintenance of Way employes to the extent of dismantling and storing materials for continuing use of the Carrier."


While we don't have to get to this question, since the carrier owned the track at the time of the work, such a question may have to be addressed in future cases.

AWARD

The claim is sustained.

Gil Vernon, Chairman

D. D. Bartholomay Emplo ee Mem r

Dated:

I

J M. Harvieux
aier Member