Parties
to the
Dispute
PUBLIC LAW BOARD N0. 3888
BROTHERHOOD OF MAINTENANCE
OF WAY EMPLOYES
VS.
MAINE CENTRAL RAILROAD C011PANY-PORTLAND
TERMINAL COMPANY
STATEMENT OF CLAIM
Claim of the Brotherhood (MW-84-10) that:
(a) The Carrier has violated the Scheduled Agreement, particularly Article IV of the 1968 Contracting Out Agreement,
as amended by the 1981 Mediation Agreement, when Contract,
Inc. (contractor) was employed by the Carrier to remove rail,
ties, and perform other maintenance of way work on the Hartland Branch, Division II Seniority District, between mile
post 102.45 and mile post 110.52, commencing on December 12,
1983, until completion in February of 1984.
(b) The following furloughed Maintenance of Way employees:
P. L. Sanborn
M. Namblet
E. F. Soucy
G. N. Patterson
D. S. Bubar
R. M. Merrithew
E. A. Wood
R. R. Hartsgrove
shall each be equally compensated at the trackman's rate of
pay for the total number of man hours expended by the contractor for work which is customarily performed by Maintenance of Way employees, as prescribed in the scope of the
Scheduled Agreement, for the Carrier's failure to discuss
this matter with the General Chairman and for the Carrier's
failure to abandon this line of railroad in accordance with
the provisions prescribed by the I.C.C. decision.
Case No. 2
Award No. 2
_p_
OPINION OF THE BOARD
From December 1983 to February 1984, Carrier contracted out the
work of dismantling and removing materials on the Hartland Branch,
a short branch line eight miles in length. The Organization filed
a claim on behalf of eight furloughed employes, alleging that the
work rightfully accrued to Track Department Forces.
For the Organization's claim to succeed, it must show, by Agreement, custom, history, or practice, that this work on abandoned
lines was exclusively with the scope of work performed by Organization
members. It did not do so. Carrier contended, and the Organization
did not refute the fact, that while, at times in the past, it has
used its own employes to assist in removal of materials, it had
also used an outside contractor without claim from the BMWE.
The Organization also argued that Carrier violated the Agreement
(specifically Article IV, Contracting Out, of the May 17, 1968 National
Agreement) when it did not hold a conference with the General Chairman
to discuss its intent to contract out. While there is no dispute
that Carrier did properly notify the Organization of its plans,
there is dispute over whether or when the Organization requested
a conference. Because the Organization waited until after the final
denial to contradict Carrier's allegation that the Organization had
not sought a conference, we cannot determine with certainty that a
a 3a8~3
_~-
-3-
conference was requested.
The question of whether Carrier did or did not have equipment
available is not germane under these circumstances, nor do we find
sufficient basis to support the Organization's contention that the
line was not properly abandoned at the time the work was performed.
AWARD
Claim denied.
C. H. Col , Ne tral Chairman
0~
B. L. Peters, arrier Member W. E. LaRue, Employe Member
''7
L3()
8 7
Datelof