s>
· PUBLIC LAW BOARD N0. 4353
· BROTHERHOOD OF MAINTENANCE
Parties OF WAY EMPLOYES
to the . Case No. 11
Dispute and · Award No. 3
NATIONAL. RAILROAD PASSENGER CORPORATION
· (AMTRAK)
STATEMENT OF CLAIM
1. Beginning on November 3, 1987, the Carrier
· . violated the Agreement when it assigned Signalman
' W. Amarer and Signalman Helper S. Visconti, in-
stead of assigning Maintenance of Way Department
' Engineer Work Equipment Operators R. D'Amato and
J. F. Nadeau to operate Maintenance of Way Depart
ment Work Equipment backhoes #30-15 and #30-16
in the vicinities of Newington and Meriden, Con
necticut, respectively (System Files NEC-BMWE-SD
2123 and NEC-BMWE-SD-2124).
2. As a consequence of the violation in Part (1)
hereof, Claimants R. D'Amato and J. F. Nadeau
shall each be compenaated at the Engineer Work
Equipment (EWE) rate of pay for all hours =anrkec'
by Signalman W. Amart!r and Signalman Helper 8.
Visconti respectively, beginning November 3, 1987
and continuing until the violation is corrected.
_2_
FINDINGS
On November 3, 1987, Carrier assigned two Signalmen in the Communication and Signal Department to operate backhoes in the vicinity
of Meridan and Newington, Connecticut, in conjunction with work involving the installation of signal and switch cables. The Organization
.., maintained that this work was contractually reserved to employes of
the Maintenance of Way Department under the Work Classification Rule
of their Agreement.
That Rule reads in pertinent part as follows:
B. WORK CLASSIFICATION RULE
ARTICLE I - BRIDGE AND BUILDING AND TRACK DEPARTMENTS
The description of each position title outlined in this Article is intended to cover
the primary duties of that position and, in
addition, it
is
understood that each title
comprehends other work generally recognized
as work of that particular classification.
21. Engineer Work Equipment - Operates and
makes minor repairs to cranes, on or off rail,
movable or fixed and other heavy equipment
assigned to the M. of W. Department agreed upon
as requiring the assignment of an EngineerWork
Equipment.
A claim was consequently filed for all hours worked on the job
on behalf of R. D'Amato and J. F. Nadeau, who hold seniority as Trackman/
k-I3153 -3
Engineer Work Equipment Operators (EWES) in the Maintenance of Way
,
Department. Several arguments were advanced by Carrier for denying
the claims. Primary among them was the contention that the Organization
was unable to show that digging in general or the operation of backhoes
in particular belonged exclusively to BMWE-represented EWES by practice
or rule.
"' While the Organization cited several examples of occasions when
EWES operated backhoes in conjunction with Signal Department work (as
well as the payment of one claim for such work), Carrier ultimately was
more persuasive in showing that digging work done with a backhoe had,
over the years, been performed by C&S personnel and others. It did so
via the introduction of written statements by officers throughout the
system writing about operations before and after Amtrak assumed ownership.
Although it goes without saying that Maintenance of Way Employes
are not bound by the terms of the Signalmens Agreement, that Agreement
does provide insight into the practice of allocating work on the
property. The Scope Rule of that Agreement reads in pertinent part
as follows:
UNDERSTANDING: The line of demarcation of the signal
forces in relation to associate departments is the
point the following work terminates - namely: the
signal men shall handle all signal work, up to and
connections with the secondary leads of Service Transformers, all equipment for train stop, train control
and cab signals up to and attached to the rails, all
signal system wiring up to and including connections
Lt3'53 3
of terminals of aerial wires, serial cables,
underground conduit system cables and submarine
cables; also the placing of all signal parkway
or signal trenchlay cable but mt the excavating
that would involve the tracks, ties or ballast.
All other digging in connection with signal installation will be done by signal forces. All
concrete foundations for signal and interlocking
apparatus to be done by the signalmen except
foundations
for
signal bridges (emphasis supplied).
According to Carrier, the work at issue here was the relocating
and burying of signal cable for new switch locations. In its initial
claim, the Organization maintained that the work consisted of digging
on the right of way adjacent to and under the tracks. in his response
to Claimants on January 27 and February 1, 1988,-Division Engineer B.
R. Pohlot wrote that the incumbents in the positions "did not dig under
(across) the track structure as you allege in your claim." Director,
Labor Rblations L. C. Hriczak reiterated this contention in a letter
to General Chairman J. J. Davidson on August 26, 1988. ("Their digging
did not disturb the integrity of the track structure.") Given the fact
that the Signalmen's Scope Rule limits their excavation to work that
does not include "excavating that would involve the tracks, ties or
ballast," the question of what type of digging was performed here becomes
critical.
The record, however, is devoid of any evidence to settle the basic
factual dispute as to whether the work on and after November 3, 1987
X53-3
in Newington and Meriden, Connecticut, was limited to digging adjacent
to the track or whether it also included digging under the track
structure. As a consequence, this Board is unable to issue an Award
dispositive of the matter. Thus, the claim must be dismissed.
AWARD
Claim dismissed.
C. H. Gold,
N
utra Chairman
(- Ir
(~f'l,/
d
C. E. Voo ock, Carri ember
J. J. Davis n,EmPloye Member
R 9l
Date of o tion