PUBLIC LAW BOARD NO. 4402
PARTIES ) BROTHERHOOD
OF MAINTENANCE OF WAY EMPLOYES
TO )
DISPUTE ) BURLINGTON
NORTHERN RAILROAD COMPANY
STATEMENT OF CLAIM
1. The discipline, suspension for five (5) days, imposed upon Track
Inspector R. G. Pearson for alleged violation of Rules A, 101 and
502(B) of the Burlington Northern Rules of the Maintenance of Way
Department was without just and sufficient cause and on the basis of
unproven charges (System File #4 Gr./GMWA 86-9-29).
2. The Claimant's record shall be cleared of the charges leveled against
him and he shall be compensated for all wage loss suffered.
OPINION OF BOARD
As a result of charges dated March 18, 1986, investigation eventually held on April
3, 1986 and by letter dated May 1, 1986, Claimant, a track inspector with approximately 16
years of service
(six as
a track inspector), was censured
and
suspended for five days for
failure to comply with instructions from proper authority and to fully protect trains against
any condition which interfered with their safe passage on March 13, 1986.
Inspection by a Missouri Department of Transportation inspector on March 12,
1986 revealed defects at mile post 14.50 which were repaired. MP 14.50 was in
Claimant's designated inspection area. Claimant was not disciplined for the defects found
on March 12, 1986. On March 13, 1986 Roadmaster L. J. Moloney, Assistant
Superintendent M. A. Oliver and Claimant discussed the difficulties and possible solutions
for the problems at MP 14.50. Claimant was instructed to to look the area over for ways of
resolving the problems existing at MP 14.50.
Later on March 13, 1986 Moloney went to MP 14.50 and discovered defects in two
bars. Specifically, one bar was broken and the other was cracked. Moloney then issued a
slow order to approaching trdirrs. Thereafter, Claimant arrived at MP 14.50. Claimant had
already inspected the area in his vehicle and had not yet discovered the defects. The instant
discipline followed
PLB 440. kward No. 18
R. G. Pearson
Page 2
Substantial evidence supports the Carrier's conclusion that Claimant failed to
comply with the given instructions and take the necessary protective action. MP 14.50 was
an obvious problem area and Claimant was instructed to look the area over for possible
solutions. In the course of his inspection, Claimant missed the cracked and broken bars.
The Organization's arguments that Claimant could not see the defects from his vehicle and
that the discipline was premature in that Claimant was in the process of performing the
given instruction and about to begin a walking inspection when Moloney appeared at the
location do not change the result. Given the type of defects that were found on the
previous day in the same area and the nature of the discussion between Claimant, Moloney
and Oliver earlier in the day and further considering the fact that MP 14.50 was a
designated problem area, the record substantiates the Carrier's conclusion that something
more was required than the initial effort undertaken by Claimant by the time Moloney
arrived.
However, we find that the amount of discipline imposed was excessive. Although
we have found that Claimant's inspection was less than adequate, under the given
circumstances a five day suspension in addition to a censure may have been an overreaction
to the fact that the Missouri inspector found defects near the same spot on the previous day
which had been repaired. In these circumstances, we believe a censure to be appropriate.
AWARD
Claim sustained in part. The five day suspension and censure shall be reduced to a
censure and Claimant shall be compensated accordingly.
Gr
Edwm . Bean
Neutral Member
kez
. J. Kallinen P. . wanson
Carrier Member Organization Member
Denver, Colorado
August 11, 1989