PARTIES ) BROTHERHOOD OF MAINTENANCE OF WAY EMPLOYES
TO )
DISPUTE ) BURLINGTON NORTHERN RAILROAD COMPANY

STATEMENT OF CLAIM





















OPINION OF BOARD



Award 28 dealt with the Carrier's contracting out "in-track" tie treatment. This dispute

addresses the Carrier's contracting out "out-of-track" tie rehabilitation.



Wood, notified the Organization's General Chairman E. L. Torske as follows:





                              Page 2


        Denver Region's 1986 concrete tie program is as follows


                Location Concrete Tiea Wood Ti=

                1. Guernsey, WY 108,500 133,600

                2. Crawford, NE 20,000 24,600


        Installation of concrete ties on the Denver Region began August 18, 1986 near Ft. Laramie, Wyoming.

        The total process is as follows:

          1. Unload concrete ties using car mover (contractor) augmented

              by work train to feed new loads and remove empties.

              (Started July 10, 1986).

          2. Install concrete ties by BN Forces.

              a. Use auto sled with tie extractors to remove wood

                  ties.

              b. Insert concrete ties.

              c. Attach fasteners.

              d. Unload ballast and surface track.

          3. Pick up reclaimable ties with spikes, plates and anchors.

          4. Transport material to Denver Region reclaim site.

          5. Unload by contractor at reclaim site.

          6. Rehabilitation to be performed by contractor at Denver

              region reclaim site:


              a. Remove spikes from tie.

              b. Sort spikes, tie plates, ties, anchors.

              c. Reload spikes, ties plates, and anchors for reuse.

              d. Grade wood ties.

                  1. BN retained ties.

                  2. BN rejected ties .

              e. Apply liquid tie plugger.

              f. Adz ties and treat adzed with ADZ-Life.

              g. Apply stainless steel bands to both ends of split ties,

              h. Bundle, band and load reclaimed ties.


          Should there be any questions about the information given above, Mr. Lutzenberger or I will be happy to discuss.

      By similar letter dated February 25, 1987 the Carrier, through System Chief

Engineer W. E. Glavin, notified four General Chairmen that:
          This is to inform you of the Burlington Ncrthern's intent to have

                      PLB 4402, Award 33

                      Contracting of Out-o.`-Track Tie

                      Rehabilitation Work

                      Page 3


secondhand ties rehabilitated at Spokane and Denver by different independent contractors for the next six years starting at Spokane in late March, 1987.

The Burlington Northern ties scheduled for rehabilitation will be generated as a result of concrete tie projects undertaken during the 1987 - 1992 work seasons. Each rehabilitation location will process the following approximate quantities of wood cross ties and associated materials:

          1987 206,000

          1988 - 1991 412,000 per annum

          1992 206,000


These materials will be shipped into the rehabilitation facilities between March and November annually (the eight month work season).

The contractors will assume responsibility for the complete rehabilitation process including handling of all material at the work site and disposal of all waste material and scrapped ties. The rehabilitation process begins with the removal of all attached metal materials and sorting of the various grades of reusable ties from the scrap ties and those suitable for sale as landscape timbers. It continues with the plugging, adzing, treatment of the adzed areas and end plating of selected ties on a production line basis. In this process the contractor will utilize the following special equipment, not necessarily in the order listed, built into computer controlled integrated assembly line:
      1) A system that utilizes a weigh scale to aid in sorting

          and grading.

      2) Optical scanning equipmene to adjust the depth of

          adzing cut.

      3) Optical scanning equipment to determine tie plate

          size.

      4) Metal detection equipment to aid in orienting the tie

          for initial removal of the spike.

      5) Optical readers and scanners to sort various grades of

          ties after processing.

      6) Magnetic jig that would lift and feed 22 ties onto the

          starting conveyor.

      7) Liquid plugging equipment.

      8) Adz life tie treatment equipment.

                              PLB 4402, Award 33

                              Contracting of Out-of-Track Tie

                              Rehabilitation Work

                              Page 4


        The above described process must be performed by contract for the following reasons:

              1) The process requires utilization of special handling

                and processing equipment not owned by the

                Railroad. No such equipment is available to the

                Railroad which could perform the work with the

                efficiency necessary to make it practicable.

            2) Without the utilization of a highly efficient

                production facility, the rehabilitation of the wood ties

                recovered from the concrete tie program would not

                be practicable, because the handling costs per tie

                must not exceed the economic value of the remaining

                life of the secondhand wood ties.

            3) In the absence of an economically feasible method of

                reusing these ties, they would create a monumental

                disposal problem which the Railroad is not equipped

                to handle. Used railroad ties in large volumes cannot

                be left on the right-of-way, cannot be burned in the

                open and cannot be chipped and disposed of because

                of local, state and federal environmental laws and

                regulations.

              4) The rehabilitation process itself involves hazardous

                  material handling requirement and waste disposal

                  problems which the Railrozd is not equipped to

                  handle and for which it has no employees trained and

                  licensed to handle. The "adz life" tie treatment

                  material requires a certified handler.


          If ties are adzed in the track the disposal of the adzing material (approximately one pound per tie) does not constitute a disposal problem In a rehabilitation location this pound of shavings constitutes a ton per day and therefore becomes hazardous to dispose, store, and handle. The contractor is assuming this risk and also disposing of scrap ties that would be a liability to Burlington Northern.

On November 5, 1987 the Organization filed the instant claim concerning the performance of the above-described tie treatment by Judd Brother's Company at Denver, Colorado.
The rules governing the analysis of this dispute are detailed in Awards 20 and 21 of this Board. As set forth in those awards, in a dispute concerning the contracting out of work, under the Note to Rule 55 it is not necessary for the Organization to demonstrate that
                              PLB 4402, Award 33

                              Contracting of Out-of-Track Tie

                              Rehabilitation Work

                              Page 5


the employees exclusively performed the work at issue, but the Organization need only demonstrate that the employees "customarily performed" that work. For the sake of discussion, we shall assume that the Organization can make that demonstration in this case. Nevertheless, we must deny the claim.l
Initially, we find that the Carrier met its notification obligations. The correspondence from the Carrier set forth above clearly meets the requirements under the Note to Rule 55.
We also find that the exceptions set forth in the the Note to Rule 55 apply thereby permitting the Carrier to contract out the disputed work. Putting the nature of die disputed work into perspective, due to the installation of concrete ties for the first time, the work involved has not been previously performed and involves the rehabilitation of ties on a large scale through the use of a sophisticated assembly line process, which process, in tam, requires the use of another procedure utilizing Adz-Life and its attendant requirements for certified operators (of which at the time, the Carrier had none). Thus, and for reasons fully explained in Award 28 of this Board concerning the use of Adz-Life, we must find that the exceptions in the Note to Rule 55 concerning special skills, special equipment, and special material available only when applied and installed through the supplier must govern?

l There is a serious question concerning the validity of the Organization's showing that the affected
employees "customarily performed" the work in dispute. While the Organization points to standard
language found in the scope rule and the rosters in the Track Sub-Department which generally address the
kind of work at issue and further while there is reference in the record to the fact that employees have
performed some kinds of out-of-track tie rehabilitation (see e.g., the Organization's letter of November 5,
1987 at p. 4), the Carrier has pointed out that this process is quite unique; there has been an extensive
history of contracting out similar work; and that employees represented by another organization (TCU)
perform related work now claimed by the Organization. However, for the purpose of this discussion, we
shall give the Organization the benefit of the doubt and assume that it has made the "customarily
performed" showing required by the Note to Rule 55.
That fact that the contractor allegedly employed day labor to perform some of the duties does not change the result. Similarly, the fact that covered employees use claw bars, tie plugs and an Adz is not dispositive. The entire process and not just small parts of the work must be examined and we are satisfied that examination brings the exceptions specified in the Note to Rule 55 into play.
                              PLB 4402, Award 33 -

                              Contracting of Out-of-Track Tie

                              Rehabilitation Work

                              Page 6


      We shall therefore deny this claim.


AWARD

    Claim denied.


                    Edwin Berm

                    Neutral Member


E.-II Kallinen P. S. Swanson
Carrier Member Organization Member
"/-V!l -
Denver, Colorado /~r~
April 26, 1991 ,fo ~l~Cmz~ ,