PUBLIC LAW BOARD NO. 4431
BROTHERHOOD OF MAINTENANCE OF WAY EMPLOYES:
Parties .
to the V. Case No. 6
Dispute .
BURLINGTON NORTHERN RAILROAD COMPANY
STATEMENT OF CLAIM
1. The Agreement was violated when the Carrier assigned
rail grinding work on East Portland Seniority District
between Spokane, Yakima and Wishram, Washington, to
outside forces on a continuous basis beginning
February 4, 1986.
2. The Carrier also violated the Agreement when it did
not give the General Chairman advance written notice
of its intention to contract out said work as
stipulated in the Note to Rule 55.
3. As a consequence of the aforesaid violations, Welder
Foreman E.E. Wendel and Grinders P.W. Wolf, D.C.
Ellis, E.L. Gill, J.E. Tovar and R.L. Gill shall each
be allowed eight (8) hours' straight time for each day
and all overtime hours worked each day by contractor
forces beginning February 4, 1986_ and continuing until
this violation ceases.
OPINION OF THE BOARD
Between February 4, 1986, and February 17, 1986,
Carrier utilized the Loram Rail Grinder on the East Portland
Seniority District. The Union contends that by
subcontracting rail grinding work, Carrier violated Rule 1_,
yq31 -to
2
(Scope) of the current Agreement. It argues that employes
in the Welding Subdepartment classified as Grinder Operators
have the exclusive right to perform all grinding operations
on Carrier's rails. It also contends that Carrier failed
to properly notify the General Chairman of its intent to
contract out the rail grinder work and finally that it did
not make a good faith effort to acquire the machines needed
to perform the work in the same manner as the subcontractor.
Carrier denies all allegations and asserts that it has
a right under the Note to Rule 55 (which reads in pertinent
part as follows) to subcontract rail grinding of the type
performed by Loram:
Note to Rule 55
By agreement between the Company and the General
Chairman, work as described in the preceding paragraph
which is customarily performed by employes described
herein, may be let to contractors and be performed by
contractors' forces. However, such work may only be
contracted provided that special skills not possessed
by the Company's employes, special equipment not owned
by the Company, or special material available only when
applied or installed through supplier, are required; or
when work is such that the Company is not adequately
equipped to handle the work, or when emergency time
requirements exist which present undertakings not
contemplated by the Agreement and beyond the capacity
of the Company's forces. In the event the Company
plans to contract out work because of one of the
criteria described herein, it shall notify the General
Chairman of the organization in writing as far in
advance of the date of the contracting transaction as
is practicable and in any event not less than fifteen
(15) days prior thereto, except in 'emergency time
requirements' cases. If the General Chairman, or his
representative, requests a meeting to discuss matters
relating to the said contracting transaction, the
designated representative of the Company shall promptly
meet with him for that purpose. Said Company and
Organization representative shall make a good faith
attempt to reach an understanding concerning said
contracting, but if no understanding is reached the
Company may nevertheless proceed with said contracting,
and the organization may file and process claims in
connection therein.
This Board has reviewed the record and studied
Petitioner's arguments in detail. At the outset, the Board
concludes that Carrier did properly notify the General
Chairman of its intent to subcontract the rail grinding
work. This Board considers the December 16, 1985, letter,
together with the January 3, 1986 letter (Carrier's Exhibits
1&2), as proper notice under the Note to Rule 55. This
Board also concludes that Carrier did not act in bad faith
in this instance and has not violated the letter or spirit
of Rule 55
or
the December 11, 1981, Hopkins to Berge
letter.
The Board has also carefully reviewed the Scope Rule
arguments put forth by the parties and we are forced to
conclude that the work performed by the Lomar self-propelled
rail grinder is work of the magnitude and quality never
contemplated by the Scope Rule of the Agreement. The work
of a Grinder operator as described in paragraph L of
Rule 55, is outlined as follows:
r
NN3l-6
L. Grinder Operator.
An employe assigned to the operation of a
grinding device, performing all grinder
operations, either preparatory or finishing,
and including the use of the cutting torch,
shall be classified as a grinder operator.
This language cannot be read to include the operation of a
self-propelled Rail Grinder the size of two or more diesel
engine units. Carrier correctly cited the Note to Rule 55
(Special equipment not owned by the company) as
justification for contracting with Lormar for such a big
rail grinding job.
AWARD
The claim is denied .
.. . ~' ~`~,,~,'',~, 7
I
R.·. Dennis, Neutral Member
Maxine Timberman, Carrier Member B ~ e Glover, Employe Member
~s 3 /~I ~ l
r
Date pproval