PUBLIC LAW BOARD N0. 4768
BROTHERHOOD OF MAINTENANCE OF WAY EMPLOYEES
and
BURLINGTON NORTHERN RAILROAD COMPANY
AWARD NO. 2
Carrier File No. AMWB 87-08-26E
Organization File No. B-M-166
STATEMENT OF CLAIM
1. The Agreement was violated when the Carrier
assigned or otherwise allowed outside forces to
perform excavating work, i.e., digging holes and
related work, in the Great Falls Yard on June 9, 10
and 11, 1987 (System File B-M-167/AMWB 87-08-27B).
2. The Agreement was further violated when the
Carrier failed to give the General Chairman advance
written notice of its plans to contract out said work
as required in the Note to Rule 55.
3. As a consequence of the violations referred
to in Parts (1) and/or (2) above, Claimants D. Fritchen,
M. Letcher and C. Wombold shall each be allowed
twenty-four (24) hours' pay at their respective straight
time rates.
F I N D I N G S
This dispute arises from an order of the Montana Depart-
ment of Health and Environmental Sciences which directed the
Carrier "to identify and correct potential sources of ground-
G
PLB No. 4768
Award No. 2
Page 2
water contamination" at the Carrier's Montana fueling facilitizs.
The Carrier arranged to have such hydrogeological testing work
under an agreement with the Montana agency. To perform such
testing, the Carrier engaged the Ecova Corporation, a resource
engineering firm, as outside contractor and project manager
"to ensure", in the Carrier's words, "that the operations would
be conducted in accordance with all state and federal regulations".
As part of its work, the Ecova Corporation engaged another
outside firm, Roe and Sons, to perform excavation work ("digging
holes", as characterized by the Organization) at the Carrier's
Havre Yard. The Organization states that this work required
three Roe and Sons' employees three days each to complete.
It is this portion of the work (the excavation preliminary
to soil testing) which the Organization claims should have been
assigned to Carrier employees. Further, the Organization points
to Carrier's failure to advise the General Chairman in advance
concerning the work.
Directly involved here are the parties' obligations under
the Note to Rule 55 and the agreement letter of December 11,
1981. The extent of these obligations has been reviewed in
numerous previous Awards, including Award No. 1 of this Board.
PLB No. 4768
Award
No. Z
Page 3
The Board will not explore these rights and limitations further -
here, except by reference to the fully established positions
of the parties as expressed in other Awards concerning the con- -
tracting of work to outside contractors.
The claim herein does not dispute the propriety of assigning the principal portion of the testing work to the Ecova
Corporation as part of the Carrier's compliance with state law.
The Organization does, however, express its concern in reference to the work subcontracted by Ecova to Roe and Sons.
The Organization presents substantial evidence to show
that excavation of the type performed by Roe and Sons parallels
work performed by Carrier employees with equipment under the
Carrier's control. If such excavation stood by itself, the
Organization would have a viable argument as to the impropriety
of contracting out such work.
Here, however, the excavation work (or "digging holes")
is a component of the responsibility contracted to Ecova and
performed by its direction to its specifications. The Carrier
did not engage in subterfuge in the performance of this task;
rather, Ecova determined to assign the task to another contractor
as an integral part of Ecova's independent testing work.
In certain situations, Awards have concluded that advance
notice should have been given to the General Chairman, if only
to ~:Ltko
PLB No. 4768
Award No. 2
Page 4
with a view to determining whether a portion of the work proposed
to be performed by outside forces could effectively have been
piecemealed to permit participation by Carrier forces. In this
instance, the Board concludes that it would have been clearly
impractical, given Ecova's necessarily independent role in
providing test results to meet the requirements of the state
agency. Since the overall contractual relationship with Ecova
is not in question, it follows that the three days' work involving excavation was not violative of the Note to Rule 55 nor
other Rules cited by the Organization.
A W A R D
Claim denied.
HERBER~ L. MARX, JR., Chairman and Neutral Member
,N\A~
al:::A
WENDELL A. BELL, Carrier Member
MARK J. SCHAPPAUOH, Employee Member
NEW YORK, NY
DATED: