PUBLIC LAW BOARD NO. 5081
BROTHERHOOD OF RAILROAD SIGNALMEN
VS.
NATIONAL RAILROAD PASSENGER CORPORATION (AMTRAK)
Award No. 8
Case No. 12
OUESTION AT ISSUE:
"Claim on behalf of M. Whalen, et al for a
total of 4480 hours at the straight time rate,
account of the Carrier violated the current
Signalmen's Agreement, as amended, particularly
the Scope Rule, when it contracted the
installation of 128 data communication cables,
installation of new power supply and battery
backup and contracted for the installation of
intercom and paging system at Thirtieth Street
Station, Philadelphia, Penn. Carrier File No.
NEC-BRS(S)-SD-476. GC File No. RM1992-18-90."
FINDINGS:
This Board, after hearing upon the whole record and all
evidence, finds that the parties herein are Carrier and Employee
within the meaning of the Railway Labor Act, as amended; that
this Board is duly constituted by Agreement of the parties; and
that this Board has jurisdiction over the dispute involved herein.
The question at issue identifies three (3) separate and
distinct issues which were originally separately initiated but
have become combined into one subject during the on-property
handling procedures. For the Board to fully understand and reach
a decision on the validity - or lack thereof - of these three (3)
claims, it is necessary that we begin by an examination of the
initial claim letters and proceed seriatim from that point.
6D8l-8
By a handwritten letter dated June 7, 1990, signed by
Stephen Carel, a penalty claim was submitted on behalf of the
following Communications department employees:
Martin Whalen Gary Nemick Barry Squires
Vincent welsh Stephen Carel Tony Garcia
John Apostoli James Hill
alleging a violation of the Scope rule when - according to the
claim - an outside contractor was used "to install 128 data
communication cables on the 2nd - 3rd - 4th and 5th floors in the
north tower of 30th St. Station." The claim as presented alleged
that the work in question was started on February 10, 1990, and
was completed on June 8, 1990, and took 3,000 man hours to
complete.
A second handwritten letter dated June 7, 1990, signed by
Stephen Carel submitted a penalty claim on behalf of the
following named Communications department employees:
Martin Whalen Vincent Welsh
Stephen Carel Tony Garcia
John Apostoli -
alleging a violation of the Scope rule when - according to the
claim - an outside contractor was used to install "a new power
supply, battery backup . . . for the new telephone switch." The
claim indicated that the work in question was performed during
"the first two weeks of May 1990" and took "approx. (sic) 500 man
hours" to complete.
A third handwritten letter dated June 7, 1990, signed by
Stephen Carel was submitted outlining a penalty claim on behalf
of the following Communications department employees:
Stephen Carel Vincent Welsh
John Apostoli Tony Garcia
2
~8 1-8
alleging a violation of the scope rule when - according to the
claim - an outside contractor was used "to install and (sic)
intercom and paging system in conjunction with the new telephone
switch." This claim indicated
IM
dates on which the work in
question was allegedly performed. The claim alleged that the
work amounted to "480 man hours."
These three (3) penalty claims amounted to a total of 3,980
man hours of work which was allegedly performed by outside
contractors all in alleged violation of the employees, scope
rule.
At the initial level of the on-property handling, these
three (3) separate claims were assigned separate claim numbers
and were rejected by a single letter from Carrier dated July 13,
1990, with no procedural exceptions taken relative to any aspect
of the claims.
Subsequently, by letter dated August 6, 1990, Stephen Carel
appealed the initial denial to the second stage of on-property
grievance handling. In the letter of appeal, the initial three
(3) claims took on additional size and scope. The appeal
repeated the earlier contentions relative to the installation of
an intercom and paging system plus the installation of the backup power supply and battery system in connection with the "new
PBX." However, in this appeal letter - for the first time - the
installation of the intercom and paging system was allegedly
performed "in the first two weeks of May 1990." As indicated
supra, this claim when initially presented contained no claim
dates. The total of 980 man hours for these two (2) claims
3
~g~-8
remained the same as initially presented - 500 man hours for the
power supply and battery backup aspect of the claims plus 480
man hours for the intercom and paging system portion of the
claims.
The appeal letter went on to repeat the claim relating to
the 3,000 man hours of work allegedly involved in the installation
of the 128 data cables which began on February 10, 1990, and
which was completed on June 8, 1990. However, the appeal letter
went on to allege an additional work item which had not been
mentioned in the original claim letters dealing- with an alleged
"installation of 150 jumpers and 38 phones on the 4th floor of
30th Street" which allegedly occurred on June 7, 8 and 9, 1990,
and consumed an additional 150 man hours plus "the installation
of 480 jumpers and 200 phones on the 2nd and 3rd floor of 30th
Street" which allegedly occurred on June 26, 27, 28, 29, 30, 1990,
and consumed an additional 350 man hours.
The initial three (3) separate claims amounting to 3,980 man
hours of disputed work which were submitted on June 7, 1990,
became, on appeal, four (4) claims amounting to a total of 4,480
man hours of work including claim dates
which are
later than the
date on which the original three (3) claims were initiated.
The second level handling of these claims was denied in
much the same manner as at the initial level again without any
procedural exceptions being taken by the Carrier to any aspects
of the claim handling or to the enlargement of the initial claim
including claim dates which postdated the filing of the initial
claims.
4
sn8 I
~'
When the dispute was advanced to the highest on-property
appeal level, the case numbers as assigned to the initial three
(3) claims were used to identify the subject being progressed.
At the highest appeals level, the Carrier accepted, without
exception, the expanded 4,480 man hours as the total amount of
the claims being progressed. Carrier did, however, for the first
time raise two procedural arguments, namely:
1. An alleged violation of Rule 47(a) because Stephen Carel
was not an accredited union representative and therefore
had no standing to initiate claims on behalf of anyone
other than himself; and
2. An alleged violation of Rule 47(a) because the claim
which covered the period beginning February 10, 1990,
had not been timely presented.
Rule 47 (a) of the schedule agreement reads as follows:
"RULE 47
CLAIMS AND GRIEVANCES
(a) All grivevances or claims other than
those involving discipline must be presented,
in writing, by the employee or on his behalf
by a union representative, to the Division
Engineer within sixty (60) calendar days from
the date of the occurrence on which the
grievance or claim is based."
Before the Board can begin to give consideration to the
merits of these disputes, we must first address the procedural
contentions which have been advanced. In the first situation,
there is no apparent argument relative to the status of Stephen
Carel. He is not a union representative. Therefore, he has no
status to initiate or progress claims on behalf of anyone other
5
5081-8
than himself. The reply of the organization to this issue after
it was raised by the Carrier is far from being persuasive or
convincing. The insinuation that somehow Carrier had a
responsibility in
this regard because Carrier had dismissed the
local chairman is specious. The designation of accredited union
representatives is the sole responsibility of the Union. Since
the General Chairman was aware that his local chairman had been
dismissed, it was his responsibility to promptly notify the
Carrier relative to who the "union representative" would be for
grievance handling as referenced in Rule 47(a).' His September
26, 1991, indication to the Carrier that it was his position that
"Mr. Whalen was acting as the duly authorized representative and
acted appropriately on behalf of the organization (underscore
ours)" does not come close to answering, Carrier's contention
relative to Stephen Carel's status as the initiator and
progressor of the claims involved in this dispute.
It is the determination of this Board that the only proper
claimant with whom we are concerned in this dispute is Stephen
Carel. The claims on behalf of the other named individuals in
the three claims are not properly before this Board and they are
dismissed.
As to the second contention raised by the Carrier relative
to the timeliness of the claim which allegedly began on February
10, 1990, we need only look to the clear and unambiguous language
of Rule 47 (a) which requires that claims must be presented
"within sixty (60) calendar days from the date of the occurrence
on which the grievance or claim is based." The only exception to
6
~g1-8
this rule requirement is found in paragraph (e) of Rule 47 which
reads as follows:
11(e) A claim may be filed at any time
for an alleged continuing violation of any
agreement and all rights of the claimant or
claimants involved thereby shall, under this
Rule, be fully protected by the filing of one
claim based thereon as long as such alleged
violation, if found to be such, continues.
However, no monetary claim shall be allowed
retroactively for more than sixty (60)
calendar days prior to the filing thereof.
With respect to claims involving an employee
held out of service in discipline cases, the
original notice of request for reinstatement
with pay for time lost shall be sufficient."
The Organization's only response on the property to this
contention relative to the timeliness of this claim was that somewhat cavalier statement to "Lets (sic) not muddy the water . . . ."
At the hearing before the Board, the organization representative
valiantly attempted to answer this issue by arguing that
Carrier's failure to take exception to this time limits situation
at the first two levels of on-property handling constituted
"laying behind the log." Therefore, the Organization urged that
Carrier's contention in this regard should be rejected by the
Board.
Boards such as this have had numerous opportunities to
examine arguments relative to implied waiver of time limit
defenses by failure to assert them at the first opportunity and
have regularly and consistently held that there was no waiver if
the issue was raised at any time before the claim was appealed to
a Board of Adjustment.. For Example, Decision No. 5 of the
National Disputes Committee created to interpret the August 21,
7
5081-3
1954 National Agreement, specifically Article V thereof which
deals with time limits for claims handling, reads as follows:
"If the issue of non-compliance with the
requirements of Article V is raised by either
party with the other at any time before the
filing of a notice of intent to submit the
dispute to the Third Division, it is held to
have been raised during handling on the
property."
And again, in Third Division Award No. 14355, Referee Ives held
as follows:
"Carrier did not waive its right to invoke the
time limit provision by reason of its agent's
initially passing on the merits of the- dispute
without raising the timeliness of the claim as
contended by Employees. The issue of noncompliance with the requirements of Article V
was raised by Carrier on the property before
the filing of a notice of intent to submit the
dispute to this Board."
Therefore, it is the determination of this Board that the claim
which was initiated on June 7, 1990, covering the claim period
beginning February 10, 1990, was not presented in a timely
manner. The language of Rule 47(e) specifically limits claims of
this nature to not "more than sixty (60) calendar days prior to
the filing thereof." In this instance, Carrier's reference to
June 18, 1990, as the filing date and April 18, 1990, as the cutoff date has no verifiable support in the case record. The
unchallenged filing date of the 3,000 man hour claim was June 7,
1990, and is a proper claim retroactively for sixty (60) calendar
days prior thereto. That claim will therefore be considered
beginning April 8, 1990. The claim dates from February loth to
and including April 7th are dismissed as being untimely filed.
8
s~gl-8
The merits arguments which relate to these disputes had
their origins in 1988 when Carrier announced plans for a major
rehabilitation of the entire 30th Street Station complex. After
many meetings, exchanges of correspondence and much discussion
between the parties, an agreement was reached in settlement of
the issues involved which agreement was set forth in a letter
dated May 3, 1990, which stipulated as follows:
"Mr. R. E. McKenzie, General Chairman
Brotherhood of Railroad Signalmen
230 East Orange Street
Lancaster, Pennsylvania 17602
Dear Mr. McKenzie:
This has reference to our continuing discussions
pertaining to the rehabilitation of Thirtieth
Street Station, most recently May 1, 1990.
Without prejudice to either party's respective
position and not to be referred to by either
party in the future, the following resolution
of our dispute was agreed upon.
(1) Amtrak will perform the "riser" work as
outlined in Amtrak's letter of April 30,
1990, from Assistant Chief Engineer
C&S/ET J.A. Early, or guarantee 2,500 man
hours at pro rata to employees that would
have been used to perform such work if
Amtrak for some reason does not perform
the "riser" work. If for some reason
Amtrak performs only a portion of the
"riser" work, the 2,500 man hours will be
allowed on a proportionate basis to the
work not performed by Amtrak.
(2) Amtrak will allow three hundred (300)
hours of compensation at pro rata to be
divided among BRS represented employees
alleged to be aggrieved. The employees
names and respective hours to be allowed
will be provided to Amtrak by the BRS.
It is understood that the above agreement
resolves any dispute with regard to
installation work that may be of interest to
BRS in the rehabilitation project at Thirtieth
9
i5oo l-8
Street. If the foregoing accurately reflects
our agreement, please sign where indicated
returning one copy to me for Amtrak's record.
Very truly yours,
\s\ L.C. Hriczak
Director-Labor Relations
\s\ R. E. McKenzie
General Chairman"
As for the issues involved in the claims which relate to the
"new telephone switch" and the "intercom and paging system in
conjunction with the new telephone switch," there was a separate
series of communications and discussions between the parties.
The details of these functions were set forth in a letter dated
May 10, 1990, from the Carrier to the organization which reads as
follows:
"AS I
advised in conversation April 30, 1990,
Amtrak will be purchasing nine'(9) state of
the art PBX switches. Six (6) of those
switches will be installed at locations on the
Northeast Corridor. New switches will be
installed at New York, Philadelphia, Trenton,
Newark, Wilmington and Baltimore.
In view of the complexity of the switches, the
advanced software associated with these systems
and the warranties involved, the switches will
(sic) be purchased on an installed basis.
Installation must be performed by installers
certified to perform such work in order to
protect the warranties. The first switch is
scheduled to be installed at Thirtieth Street
Station, Philadelphia, in the near future.
Should you have further questions or desire to
meet on this matter, please contact me to
arrange a mutually convenient time."
The Organization eventually replied to Carrier on this issue
as follows:
"This refers to our meeting of July 19, 1990
concerning installation and Amtrak's ownership
of six new PBX's on the corridor. After
10
~8r-8
discussions with Mr. Tate, it was considered a
productive meeting, having reached many
understandings in principle to the following:
1. After installation and expiration of a one
year warranty the BRS would assume all
trouble-shooting and maintenance
responsibilities of each PBX.
2. Amtrak would provide the necessary
training for trouble-shooting and repair
of each PBX.
3. All preparation work to be performed by
the BRS.
4. BRS would be willing to work out an
agreement establishing a quick response
team to handle severe PBX problems:
It is our desire to work together and to
finalize these understandings as soon as
possible. Hopefully, we can start putting
some issues to rest. Looking forward to a
meeting as soon as possible to finalize."
During the handling of these claims before the Board, the
organization argued that the Board need not address the
applicability of the Scope rule inasmuch as both parties have
recognized the applicability of the Scope by the nature and
extent of the notices, discussions and agreements reached in
connection with the rehabilitation work. The Board fully agrees
with this position.
In our determination of the merits of these claims, we have
read, re-read and studied the language which is found in the May
3, 1990, agreement and the letters of understanding reached in
conjunction with the PBX claims. The Board must accept the
language of the written agreement and letters of understanding
as being the intent of the parties who wrote them. We must
presume that the authors of the agreement and letters of
11
~8 (-g
understanding were knowledgeable individuals who knew the
circumstances which were involved in the discussions which led to
the agreement and who by their agreement and concurrence
acquiesced in the settlements reached.
The May 3, 1990, agreement contains clear, unambiguous and
far reaching language. It clearly refers "to our continuing
discussions pertaining to the rehabilitation of
Thirtieth Street
Station . . . ." It clearly provides that the agreement reached
"resolves any dispute with regard to installation work that may
be of interest to BRS in the rehabilitation project at
Thirtieth
Street." This agreement by its language goes far beyond the
"riser" work which is referenced as only one of the items
involved in the agreement; which "riser" work, according to
uncontroverted statements by Carrier, was actually performed by
Carrier's employees (Brotherhood Exhibit No. 4) thereby negating
the 2,500 man hour guarantee mentioned therein. The agreement
resolves any dispute which may be of interest to BRS in the
rehabilitation project. These agreed upon words can be given no
other meaning.
As for the "new telephone switch" and the attendant work in
conjunction therewith, the May 10, 1990, and July 25, 1990,
letters of notice and understanding give tacit indication of
approval by the organization to the use of the supplier's
employees to make the initial installation of the equipment. The
organization acknowledged that "after installation and expiration
of a one year warranty . . ." the responsibility for and control
of the equipment would accrue to the organization represented
employees. This language too can be given no other meaning.
12
It is, therefore, the conclusion of the Board that the
complained of work in these claims is covered by the provisions
of the May 3, 1990, agreement and the May 10th/July 25th letters
of understanding. There has been no showing by the Organization
to the contrary. The claims which were properly and timely
presented to the Board are denied.
AWARD:
Claim denied.
ames E.
hairman
Mason
and Neutral Member
W.H. Ro inson, Jr//
Carri Member
Issued at Palm Coast, Florida
May 26, 1994
Q A 014
a-Li
Charles A. McGraw
Employee Member
.3