Organization File No. Contracting Out
Carrier File No. 013-295-27
PUBLIC LAW BOARD NO. 5384
PARTIES ) TERMINAL RAILROAD ASSOCIATION OF ST. LOUIS
TO )
j INTERNATIONAL BROTHERHOOD OF BOILERMAKERS, IRON
DISPUTE ) SHIP BUILDERS, BLACKSMITHS, FORGERS AND HELPERS
STATEMENT OF CLAIM:
1. That the Terminal Railroad Association of St. Louis,
referred to as the Carrier, violated Section 2, Article
II of the September 25, 1964 Agreement when failing to
. give notice of intent to subcontract work, that of
welding rail on the Carrier's Illinois Transfer, to the
Norfolk & Western Railroad and Holland Welding Company.
2. That the Carrier further violated said Article II by
subcontracting work belonging to the Boilermaker Craft.
3. That, accordingly, the Carrier be ordered to make
T. Shylanski, R. Sheppard, R. Wilder and A. Sak whole by
compensating at the pro rata rate of pay and time and
one-half rate of pay equal to the divided number of
respective hours of labor expended by the subcontractor
in said rail welding. In addition, R. Wilder and A. Sak
be made whole for all compensation lost as a result of
their being furloughed immediately after said
subcontracting was consummated.
FINDINGS:
The Board, upon consideration of the entire record and all of
the evidence, finds that the parties are Carrier and Employee
within the meaning of the Railway Labor Act, as amended, that this
Board is duly constituted by Agreement dated February 12, 1993,
that this Board has jurisdiction over the dispute involved herein,
and that the parties were given due notice of the hearing held.
Public Law Board No. 5384
Award No. 1
The Organization claims Carrier violated Section 2, Article II
of the September 25, 1964 Agreement when it subcontracted track
welding work to the Norfolk & Western Railroad and Holland Welding
Company, and failed to_give the Organization notice of its intent
to do so. According to the Organization, boutet welding work was
performed by persons who were not in the Carrier's employ between
November 11 and 17, 1991.
Carrier has not disputed the material facts in this case,
except that it denies that such work was performed on November 17,
1991, a Sunday. Specifically, Carrier admits the work performed is
within the scope of the Agreement between it and the Organization,
that it was performed by Norfolk & Western employees and by
employees of Holland Welding Company, and that it failed to notify
the organization of its intent to subcontract the work. Carrier
has denied this claim primarily on the basis that no claim was
fiI-ed until February 3, 1992, which Carrier argues constitutes a
violation of the time liIplt.rule found in the August 21, 1954
National Agreement, providing, in pertinent part, as follows:
(a) All claims or grievances must be presented in
writing by or on behalf of the employee involved, to the
officer
of
the Carrier authorized to receive same, within
60 days from the date of the occurrence on which the
claim or grievance is based. Should any such claim or
grievance be disallowed, the carrier shall, within 60
days from the date same is filed, notify whoever filed
the claim or grievance (the employee or his
representative) in writing of the reasons for such
disallowance. If not so notified, the claim or grievance
shall be allowed as presented, but this shall not be
Public Law Board No. 5384
considered as a precedent or waiver of the contentions of
the Carrier as to other similar claims or grievances.
Carrier bases this argument upon a January 7, 1965 Letter of
Understanding between J. E. Wolfe, Chairman, National Railway Labor
Conference, and Michael Fox, President, Railway Employes'
Department, AFL-CIO,1 which reads, in its entirety, as follows:
Memorandum of Understanding re Article VI of Mediation
Agreement of September 25, 1964 by and between the
participating carriers listed in Exhibits A, B and C of
said agreement represented by the National Railway Labor
Conference and the Eastern, Western and Southeastern
Carriers' Conference Committees, and the employees of
such carriers shown thereon and represented by the
railway labor organizations signatory thereto, through
the Railway Employes' Department, AFL-CIO.
Under the provisions of Article VI, Section 19,
disputes arising under Article III - Assignment of Work,
Article IV - Outlying Points, and Article V - Coupling,
Inspection and Testing, are to be handled in accordance
with Section 3 of the Railway Labor Act. It is clear
that with respect to such disputes subject to handling
under Section 3 of the Act any claim or grievance is
subject to the time limits and procedural requirements of
the Time Limit on Claims Rule.
A different situation exists with respect to
disputes arising under, Article I - Employee Protection,
and Article II - Subcontracting. Article VI provides a
"Shop Craft Special Board of Adjustment" for the purpose
of adjusting and deciding disputes arising out of those
two Articles (Article VI, Section 1), and specifically
provides (Article VI, Section 8) that the Board shall
have exclusive jurisdiction over disputes between the
parties growing out of grievances concerning the
interpretation or application of those two Articles.
'The National Railway Labor Conference serves as the
bargaining agent for the nation's rail carriers, including the
Carrier herein. The Railway Employes' Department, AFL-CIO, was
composed of the various "shop craft" organizations, including the
organization herein, and conducted bargaining on their behalf.
Public Law Board No. 5384
Award No. t
Page 4
During our negotiations, it was understood by both
parties that disputes under Articles I and II need not be
progressed in the "usual manner" as required under
Section 3 of the Railway Labor Act, but could be handled
directly with the highest officer in the interest of
expeditious handling. Sections 10 through 13 set up
special time limits to govern the handling of submissions
to the Special Board, thus providing special procedures
which are intended to supersede the provisions of the
standard Time Limit Rule. Therefore, such disputes being
processed to a conclusion through the Shop Craft Special
Board are not subject to the provisions of the standard
Time Limit Rule.
However, if there should be any claims filed for
wa a loss onTn a
al
o a name cla imant arisen out
a e e violation o Article II - u contractin ee
Section
4
ot-Artic a VI such claims s tor wage loss
should e i e rompt an within sixty ays o the
iI-in o
f
the arle~iolation~ic
u contracting, wit the same carrier officer as to w om
sucKvioTation~ Article II was directed the General
airman o the cra t or cra is invo ve , or- is
repre3entative. [Emphasis added.] I such a c aim is a
continuous one, it cannot begin to run prior to the date
the claim is presented. If the alleged violation of
Article II - Subcontracting, is then submitted to the
Shop Craft Special Board of Adjustment, it will be
considered that the special procedural provisions of
Article VI have been complied with.
Failure to handle as set forth in the preceding
paragraph shall not be .considered as a precedent or
waiver of the contentions of the carriers or employes as
to other similar claims.
This understanding is a supplement to Article VI of
the September 25, 1964 Agreement and will become
effective as of this date.
In addition, Carrier relies upon Awards 124 and 126 of Special
Board of Adjustment No. 570, both with Gene T. Ritter serving as
Neutral Member. Both disputes involved alleged violations of
Article I of the September 25, 1964 Agreement. In the former, the
Public Law Board No. 5384
Award No. 1
Page 5
Organization did not file its notice of intent to file a submission
within nine months of the decision of the highest designated
officer on the property. In the latter, the organization did not
make its claim within sixty days of the alleged violation. Both
claims were dismissed for lack of jurisdiction. In Award 124, the
Board wrote:
This neutral has carefully examined each of the
above awards together with the dissenting opinions and
has come to the conclusion that Awards 68 and 69 contain
the better reasoning and comply with the standards of
contract interpretation. It is thus found that the
special time limits set up by Sections 10 through 13, "to
cover the handling" of disputes while before the Board
supersede prior provisions while such disputes "are being
processed to a conclusion" by it. While such disputes
are "being processed to a conclusion" they are not
subject to prior provisions. However, the memo of
understanding in re Article
VI of
the Mediation Agreement
of September 2S-,-n64, does not release the Organization
from being subjected to prior time limits or other
provisions. It is further found that the Mediation
Agreement did not supersede the 60 day provision for
presentation in decision on the property; nor did it
supersede the 9 month limitation for progression to the
Board. In the 4th paragraph of the Memorandum of
Understanding, it states that both parties understood
that disputes under Arxicle I and II were-not required to
be progressed in the "usual manner" as required under
Section 3 of the Railway Labor Act but could be handled
directly with the highest officer in the interest of
expeditious handling. (Emphasis in original.] This
paragraph-Turt e-
r
states that Sections 10
through 13
set
up special time limits to cover the handling of
submissions to the Special Board, thus providing special
procedures which are intended to supersede the provisions
of the standard Time Limit Rule. This paragraph
concludes that, therefore, such disputes being processed
to a conclusion through the Shop Craft Special Board are
not subject to the provisions of the standard Time Limit
Rule.
Public Law Board No. 5384
· Award No. 1
Page 6
Since no mention was made of superseding the 9 month
limitation for progression of claims to the Board, and
since this Memorandum of Understanding was evidently made
"in the interest of expeditious handling", it is
concluded that this Memorandum of Understanding did not
eliminate either the 60 day provision for presentation
and decision by the Carrier or the 9 months for
progression to the Board. It in no way superseded Rule
31-A, paragraph c, of -the schedule agreement with the
System Federation No. 17.
The Organization has argued that time limit rules are not
applicable to disputes involving Article II of the September 25,
1964 Agreement. -,In support of its position, it has offered
numerous Awards of Special Board of Adjustment No. 570. The most
persuasive of these is Award 335, on which Gene T. Ritter again
served as Neutral Member. In that dispute, which involved a
violation of Article II, the Board wrote:
Carrier's contention that this claim is barred
barred (sic] by the Time Limit Rule is hereby rejected.
Although disputes arising under Articles III; IV and V of
the September 25, 1964 Agreement must be presented in
writing by or on behalf of the employe involved to the -
officer of the Carrier authorized toreceive the same
within 60 days from the date of the occurrence on which
the claim or grievance .is·based. (see Article VI,
Section 19 - Disputes Referred to Adjustment Board.) By
not specifying that the same procedure would apply to
disputes arising under Articles I and II, then it must be
presumed that the parties to the Agreement did not intend
for the standard time limit procedure to be applied to
disputes arising under Articles I and II of the
Agreement. Articles I and II are subject to the
Memorandum of Understanding dated January 7, 1965, which
takes these two Articles out of the realm of the standard
time limit rules. In the past, this referee has held
that the Memorandum of Understanding only did away with
the necessity of going through the usual appellate
procedure on the property by allowing the Organization to
progress a claim directly to the highest officer. This -
referee has in the past held, that the claim must be filed
Public Law Board No. 5384
Award No. t
within 60 days after the occurrence and must be appealed
within nine months after final declination on the
property. However, this referee has found himself in the
distinct minority, and in the interest of consistency,
will bow- to the majority opinions contained in Awards
Nos. 8,
44,
53,
140,
158
and others.
. Clearly, then, Awards 124 and 126 of Special Board of
Adjustment
No.
570 are no longer considered "good law," if they
ever were. The highlighted sentence of the January 7, 1965 Letter
of Understanding must have some meaning, though. Taken in context,
it is evident to this Board that Messrs. Wolfe and Fox recognized
that claims of subcontracting might be difficult to file on a
timely basis when the carrier fails to inform the organization that
it has contracted out covered work, particularly when such work is
performed off the property. Accordingly, the parties agreed the
organization would not be subject to a sixty day time limit.
However, in the underlined text, the parties further agreed that
there would be a time limit for claims for wages lost by named
claimant arising out of such subcontracting. The time limit,
though, is sixty days from the filing of the original grievance
that the work was improperly subcontracted. Therefore, once the
organization is aware of the possibility of a subcontracting
violation, it must file wage loss claims promptly. To eliminate
any question as to when the organization has such notice, the
parties agreed that the filing of the original claim will govern.
In the case before this Board, the General Chairman filed the
claim that the Carrier improperly subcontracted the work on
Public Law Board No. 5384
Award No. 7
February 3, 1992, some 72 days after the work was performed.
Because the time limit rule was not applicable to this portion of
the claim, it is not barred. The claims for wage loss were
contained in the same letter, thereby complying with the
requirement that they be filed within sixty days of the filing of
the original grievance.
Carrier next asserts Claimants are not entitled to monetary
relief because they were employed and under pay at the time the
work was performed by the contractor's forces. According to
Carrier, Claimants were working ten hours per day, six days per
week at the time of this claim. Two of the Claimants were on paid
vacation on November 15, 1991. Carrier relies upon the language of
Section 14, Article VI of the Agreement, which states:
If there is a claim for wage loss on behalf of a
named claimant, arising out
of
an alleged violation of
Article II, Subcontracting, which is sustained, the
Board's decision shall -not exceed wages lost and the
other benefits necessary to make the employee whole.
Citing Award 61 of Special Board of Adjustment No. 570, Carrier
argues Claimants suffered no wage loss, and would be entitled to no
additional
compensation.
The Organization does not dispute the fact that Claimants were
fully employed between November 11 and 16, 1991, but insists work
was also performed Sunday, November 17, 1991, a day on which
Claimants did not work. According to a summary prepared by
Claimant Shylanski, in his capacity as Local Chairman, one thermit
Public Law Board No. 5384
Award No. 1
welding team of three men worked for seven hours on that day. The
Organization also notes that two Claimants, Sheppard and Wilder,
were furloughed following this work. Bulletin No. 2, issued
November 19, 1991, indicates their jobs were abolished at the end
of their tour of duty on November 25, 1991. While acknowledging
these jobs are subject to seasonal abolishment, the Organization
argues these abolishment would have been delayed had the work not
been subcontracted.
We agree with Carrier's assertion that Claimants must show a
wage loss to be compensated. We find, however, that a wage loss,
at least to some extent, existed. Despite Carrier's denial, we
find there is sufficient evidence to conclude 21 hours of work was
performed on November 17, 1991. If no work had been performed, as
Carrier contends, documentation from either Norfolk & Western or
Holland Welding could have been obtained as evidence to refute the
organization's assertion.
While it is possible, Sheppard's and Wilder's jobs might have
been abolished later than November 25, 1991, had the Carrier not
subcontracted this work, we cannot make such a presumption in light
of the fact that these jobs are regularly subject to seasonal
abolishment. Here, the burden of proof of actual wage loss falls
on the Organization. There is insufficient evidence to carry that
burden.
Public Law Board No. 5384
Award No. 1
To remedy these losses, we will award each of the four
Claimants 5.25 hours pay at the rate specified in the Imposed
Agreement following Presidential Emergency Board No. 219, for
November 17, 1991, to equal the 21 hours worked by the
subcontractors' employees.
We also find that Carrier violated the Agreement by failing to
give the Organization advance notice of its intent to subcontract
the work. This remedy is also provided by the Imposed Agreement
following Presidential Emergency Board No. 219, and we will award
Claimants pay for the 594 hours worked by the subcontractors'
employees at the rate of pay set forth in the Imposed Agreement.
At the hearing before the Board, the Carrier questioned the
applicability of the Imposed Agreement as the contract to have the
work performed was executed on July 26, 1991, before the Imposed
Agreement was effective. However, the Board finds the violation
occurred when the work was performed, which was subsequent to the
Imposed Agreement.
AWARD: Claim sustained in accordance with the aboveFindings.
a ry N. Simon
harman an eutral Member
6Robert Reyno R. P. Mat ewson
Employee Member Carrier Member
Date:
7 / % 93 --_._~___ _ _.._-_
Arling n eig ts, I inois