PUBLIC LAW BOARD NO. 5418
Case No. 41 Award No. 41
PARTIES
Brotherhood of Maintenance of Way Employes
to - and -
DISPUTE:
Springfield Terminal Railway Company
STATEMENT OF CLAIM:
Claim for Wayne Chapin, for 7 hours at the Work Equipment
Operators rate, account the Carrier assigned a junior machine
Operator to work overtime on Saturday, November 13, 1999.
FINDINGS:
The facts of this case shows that the Carrier had planned to work overtime with a
contractor on the Connecticut River Main Line on November 13, 1999. The Carrier states that it
was anticipated that the contractor's Track Excavator operator would not be available and/or
would be late reporting to the job site. Therefore, in view of this factor, they assigned Mr. John
Barlow to operate said equipment because he possessed the requisite license and experience.
The Organization emphatically states that Mr. Barlow did not operate the Track Excavator as
alleged by the Carrier, but rather, he showed up at the job site with a Bucket Loader and ran that
piece of equipment all day. Therefore, they contend the claimant being the senior available
equipment operator should have been assigned to said overtime work. To support their position,
they direct the Boards attention to the statement given by the Foreman in charge at the work site,
wherein he undisputedly stated that Mr. Barlow did not operate the Track Excavator at all on the
date in question,
Based on the undisputed statement presented in the record, it is clear that the claimant should
have been called to operate the equipment that the junior employee operated. Therefore, the
claim is upheld.
AWARD
: The claim is sustained.
Rw4 Nb· 41
PLB No, 5418 CfL1lA-41
Page 2
T. W. McNulty
Carrier Member
Fanc omz
I
ran omz
I
Neu em b
lb
B. A. Winter
Organization Member