PUBLIC LAW BOARD NO. 5418
Case No. 44 Award No. 44
PARTIES
Brotherhood of Maintenance of Way Employes
to - and -
DISPUTE:
Springfield Terminal Railway Company
STATEMENT OF CLAIM:
Appeal of David L. LaFountain, Sr., regarding
Discipline of disqualification as a Foreman until
he has a review of RWTR plus 15 working days
suspension imposed on October 27, 2000.
FINDINGS:
Subsequent to a hearing held on October 13, 2000, claimant was found guilty of
failing to follow the Carrier's Roadway Worker On-Track Protection Policy (RWP). It was alleged
that he removed track protection and cleared the track he was working on while his vehicle was
fouling the track, which resulted in the truck being hit by a road freight train in the process of
yarding their cars.
Facts gleaned from the lengthy hearing transcript shows that on August 9, 2000, the claimant
was a Welding Foreman assigned to repair a frog on number 10 and 11 switch in the yard at East
Deerfield, Massachusetts. There is no doubt that the claimant properly applied on track protection
while performing his assigned task. The question of whether the claimant actually gave up
(cleared) the track after his welding work was completed is clearly in dispute and is left to
interpretation. The heading transcript is wrought
with
contradictions from those involved at the
scene of the accident, and it would serve no useful purpose to elaborate on these differences.
The record shows that after the claimant completed his work he removed the track protection
and then called the yard office to report that he would be clear in a minute. Thereafter, the
claimant and his helper went to his truck that was parked adjacent to the track, and attempted to
leave but their vehicle would not start. The claimant then called his supervisor and requested a
push to jump-start his truck. The supervisor advised him that he would be there in
PLB No. 5418 C-44IA-44
Page 2
approximately 10 minutes. During the interim, a road freight conductor had conversation
with the claimant regarding whether there was sufficient clearance for their cars to pass
the stalled truck. Here again, there is conflicting testimony between the conductor and
the claimant as to what actually transpired. However, it is a fact that the claimant and his
helper remained in the staled truck while the freight cars began to pass.
Suffice to say that after a thorough review of the hearing transcript, we conclude the
claimant's poor judgment at the time contributed to the accident. Clearly, with the
knowledge that his truck would not start and that it was perilously close to the track, the
claimant, in our view, should have used common sense and taken several remedial
steps which would have prevented the accident. First, he should have immediately
contacted the yard office to inform them that his truck was stalled and was fouling the
track. Second, he should have taken the initiative and told the conductor to wait until his
truck was moved.
Considering all of the evidence presented in this case, it is our judgment that the
Carrier was on valid grounds when it concluded that the claimant did not fulfill his
responsibility as a Welding Foreman arid that discipline was warranted. However, the
Board concludes, that based on the entire record, and in light of claimant's 22 years of
relatively good service, we deem the suspension to be excessive and it shall be reduced
to a 5 day suspension.
AWARD
: As specified in the Findings.
PLB No. 5418 C-"A-44
Page 3
Fra s' . Domz i
Ne tr Membe
T. W. McNulty A. Wi er
Carrier Member Organization Member
Dated:
6
-/ 8-dool