PARTIES Brotherhood of Maintenance of Way Employes
to -and
DISPUTE: Pan Am Railways

STATEMENT OF CLAIM:



FINDINGS: The record presents a procedural issue as a threshold matter. The Organization

Asserts the Carrier violated Article 25.3 of the scheduled Agreement by failing to comply with

the time limits specified therein.














provisions of Article 25.3, the Board deems this case to be procedurally defective. `Therefore,

based solely on the time limit violation, the claim is sustained.

The Carrier is directed to implement the Award within 30 days of receipt.
PLB No. 5418 C-74JA-74
Page 2
AWARD: The claim is sustained.
Fr ' s J. Do lski
Ne ral Me r
A. F. Lomanto B. A. Vii ter
Carrier Member Organization Member

Dated: