BEFORE PUBLIC LAW BOARD NO. 5546
BROTHERHOOD OF MAINTENANCE OF WAY EMPLOYEES
and
UNION PACIFIC RAILROAD COMPANY
Case No. 4
STATEMENT OF CLAIM: Claim of the Brotherhood that:
1. The Agreement was violated when the Carrier assigned or otherwise
permitted employees of an outside contractor (Brennan Construction
Company) to perform Maintenance of Way and Structures
Department work of preparing, forming, pouring and finishing of
concrete in the construction of a 20' x 60" pad at the north end of the
Wheel Shop at 237 E. Day Street, Pocatello, Idaho on May 14 and 15,
1992 (System File R-15/920464).
2. The Agreement was further violated when the Carrier failed to
provide proper and timely advance written notice of its intent to
contract the specific work involved herein or to hold good-faith
discussions prior to the contracting transaction.
3. As a consequence of the violations referred to in Parts (1) and/or (2)
above, furloughed Idaho Division First Class B&B Carpenters W. S.
Wallace and T. D. Stalder shall each be allowed sixteen (16) hours'
pay at their straight time rates and eight (8) hours' pay at their time
and one-half rates.
FINDINGS:
On May 14 and 15, 1992, the Carrier hired an outside contractor to pour a 20' x 60'
x 6' concrete slab at the north end of the Wheel Shop in Pocatello, Idaho.
The Organization filed the instant claim on behalf of Claimants Wallace and
Stalder contending that the Carrier never advised the Organization of its intent to hire an
outside contractor to perform the work that the Claimants were capable of doing and had
performed in the past. The Organization argues that the notice that the Carrier claims it
55zf h -Y
served referred to a different size pad located on the "west" side of the Wheel Shop
instead of the "north" side where it was finally laid.
The parties not being able to resolve the issues, this matter came before this Board.
This Board has reviewed the extensive record in this case and we find that the
Carrier was in violation of the Agreement when it failed to give proper notice
to
the
Organization of the proposed subcontracting so that the Organization could enter into
discussions with. the Carrier as contemplated by the Agreement.
The record reveals that on April 16, 1992, the Carrier's Superintendent of
Transportation Services gave notice to the Organization's General Chairman of the
Carrier's intention to solicit bids to contract out work involving the insulation of a 6 x 55'
concrete pad west of the Pocatello Wheel Shop and all associated work in conjunction
V
with the installation. In that notice, the Carrier's representative also stated, "In the event
you desire a conference in connection with this notice, all follow-up contacts should be
made with the Labor Relations Department".
The record also reveals that the Organization responded to the April 16, 1992
letter on April 27, 1992. In that letter, the Organization's representative objected to the
subcontracting of the work for the usual reasons. The Carrier replied to the
Organization's response on May 6, 1992 and once again indicated its willingness to
conference to discuss the notice. However, the record reveals that the conference
to
discuss this case of subcontracting did not take place until May 18, 1992. The
subcontracting work actually occurred on May 13, 14, and 15, 1992. Obviously, the
2
~5~f b ,~l
conference took place after the work had already been completed.
The purpose of the language of the Agreement relating to notice is to afford the
parties an opportuinity to sit down and discuss the Carrier's proposed subcontracting of
work. It is the Organization's goal in those conferences to prevail upon the Carrier to
utilize Organization members who are employed by the Carrier to perform the work that
the Carrier is considering sending to a subcontractor. If the Carrier does not hold the
conference to discuss the proposed subcontracting until after the work has already taken
place, the specific language of the Agreement has been violated and the principles behind
that language have been frustrated. It would be absolutely fruitless for the Organization
to engage in that belated conference.
In this case, since the Carrier did not hold the conference until after the
subcontracting work had already been performed, the Carrier was in violation of the rules
which require that the conference take place before the work is performed. Given that
violation by the Carrier, this Board finds that the Organization members who are named
in the claim are entitled to the relief sought. The record reveals that there were a total of
48 hours of work performed by the subcontractor. Therefore, we find that the claim must
be sustained.
3
f
AWARD
Claim sustained.