|
When all is said and done, the Carrier did nothing more here than state that it simply did not have enough people to do the work on the Matteson building and satisfy its other obligations as well. In the throes of a true and time-sensitive emergency, the Board absolutely understands that such a challenge could well occur. However, the Carrier did not substantively argue that the work itself could not have been performed by members of this bargaining unit, or in the alternative that the operational circumstances were so dire (some five weeks later) that securing outside help became necessary in order to protect the Carrier's business interests in a crisis. Either or both of these realities would have to have been present to overcome the obvious classification of work conflict, and here, the Carrier failed to satisfy its affirmative burden to demonstrate that contracting out recognized bargaining unit work under these particular circumstances was a necessity. The disputed work was not performed concurrently, by any stretch, with the actual weather event that prompted the initial notice of intent to subcontract. Clearly, the Carrier did not consider the Matteson station roof to present an "emergency" within the normal understanding of that word, since work on it was deferred for more than a month after the precipitating event.2 The Carrier did not meet, to the satisfaction of this Board, its obligation show the "nature, extent and duration" of the stated emergency, and as such, the Board will rule that DeVito's claim indeed has merit.
|
|