PUBLIC LAW BOARD NO. 5567
AWARD NO. 1
NMB CASE NO. 1
UNION CASE NO.
COMPANY CASE NO. 900277 MPR
PARTIES TO THE DISP=E:
BROTHERHOOD OF MAINTENANCE OF
WAY EMPLOYEES
- and -
UNION PACIFIC RAILROAD COMPANY
(farmer Missouri Pacific Railroad Company)
STATEMENT OF CLAIM:
"Claim of the System Committee of the Brotherhood that:
(1) The Agreement was violated when the Carrier
assigned an outside contractor (Milam
Construction Company) to perform track work
(tie removal) at the North Little Rock
Terminal beginning March 5, 1990 and
continuing.
(2) The Agreement was further violated when the
Carrier failed to furnish the General
Chairman with advance written notice of its
intention to contract our said work as
required by the May 17, 1968 National
Agreement.
(3) As a consequence of the violations in Parts
(1) and/or (2) above, Machine Operators V. D.
Randolph and C. H. Burrows shall each be
allowed pay at their respective straight time
and overtime rates for an equal proportionate
share of the total number of straight time
and overtime man-hours expended by the
outside forces performing the work in Part
(1) above."
P(-O> tio.59-&7
AWARD NO. 1
NMB CASE NO. 1
UNION CASE N0.
COMPANY CASE NO. 900277 MPR
2
OPINION OF BOARD:
V.
D. Randolph and C. H. Burrows (Claimants) have
established and hold seniority as Machine Operators and also as
Trackmen, under the terms of a "dual seniority" Memorandum of
Understanding dated June 3, 1982. Due to force reductions,
Claimants had been assigned to "lower rated" Trackmen positions
on the Arkansas Division when this dispute arose.
In early March 1990, Carrier began a tie renewal project in
the 400 Yard at the North Little Rock Terminal- At various times
throughout the project, without notifying the BMWE General
Chairman, Carrier employed an outside contractor (Milam
Construction Company) to assist the MofW forces. Milam used its
own backhoe to remove and install switch ties, and a front end -
loader to unload and haul ties to the project area and remove old
ties. Two Milam employees operated the equipment.
On March 23, 1990, the Assistant General Chairman submitted
a claim on behalf of Messrs. Randolph and Burrows which stated:
"It is our contention that certain rules of
the current Working Agreement have been
violated, especially Scope, Seniority Datum
Rule (1), Seniority Rights Rule (2), Bulletin
Rule (11), Work Week Rule (14) and Article IV
of the May 17, 1968 National Agreement in
that carrier failed to notify the General
Chairman of their intent to subcontract out
said MofW work, and the December 11, 1981
'Good Faith' letter to reduce incidents of
subcontracting out MofW work.
Therefore, time is being claimed by and in
PL
$ N
e · -55
G%7
AWARD NO. 1NMB CASE NO. 1
UNION CASE NO.
COMPANY CASE NO. 900277 MPR
3
behalf of each Claimant for payment of all
wage loss suffered (straight time, overtime
and holidays), at the Machine Operator rate,
from March 5, 1990, continuing, for being
denied said 'work opportunity' to outside
concerns."
Carrier denied the claim asserting that:
"At the outset, based on the evidence
presented, it is apparent the Organization
has failed to research the validity of its
claim since you have failed to supply the
dates, number of employees or number of hours
allegedly worked each day. You have simply
made a blanket request for all hours worked
by contractor employees, (straight time,
overtime and holidays) and expect the Carrier
to supply you with the information to support
your allegations.
Investigation into the circumstances
surrounding your allegation reveals that
Milam did not have two employees on the
property at all times, nor were these
employees working 8 hours each day.It is
evident that you have mistakenly advanced
this claim on a continuous basis. It must be
pointed out that Milam was not working each
and every day and therefore, this does not
constitute a continuing claim as you have
implied."
Finally, with regard to allegations of a Scope Rule
violation, Carrier submitted that "Union Pacific has used
contractor service for this type of work traditionally and it has
created no loss of work opportunity for the MofW employees"; n
support of that position, Carrier attached a lengthy list of
previous occasions in which it had entered into similar
subcontracts without notice.
PL,8
No- 5~&_
AWARD NO. 1
NMB CASE NO. 1
UNION CASE NO.
COMPANY CASE NO. 900277 MPR
4
In this case, as well as some half-dozen other "Scope and
Not.i-.e" subcontracting disputes removed from the NRAB to this
Board, the Parties respectively urge me to blaze new trails and
depart from principles developed in a plethora of Third Division
decisions involving the same Parties, identical
issues
and
identical contract language.
The
Scope
Rule of the BMWE/MOPAC Proper (now Union Pacific)
Agreement here under construction has been in effect without
significant change since 1938. In more than a hundred
jurisdiction of work disputes, its job classification language
has ''.~Aen construed as "general" in nature by two generations of
NRAB Referees. In this case, however, BMWE urges me to revert to
dicta in Award 3-747 (Swacker), a 1938 remand decision which offhandedly referred to the Scope Rule as "specific". For its part,
Carrier argues that the generality of the Scope Rule obviates the
notice and consultation requirements of Article IV in the May 17,
1868 National Agreement and the good faith effort requirements of
the December 11, 1981 Letter of Agreement, unless the
Organization first demonstrates a past practice of exclusive
sys`2m.-wide performance. In short, Carrier urges that it may
ignore with impunity those notice and consultation obligations in
"mixed practice" situations.
This Board rejects each Party's respective overture to
abandon sound principles developed by the NRAB to govern such
matters. The Chairman reiterates his holdings in prior Third
.. pL,8 No, 554,7
AWARD NO. 1
NMB CASE NO. 1
UNION CASE NO.
COMPANY CASE NO. 900277 MPR
5
Division decisions to the effect that: 1) the Scope Rule here
under construction is "general" in nature since it does not
reserve specifically described work to listed job
classifications; 2) reservation of work to Agreement-covered
employees must be demonstrated by evidence of a custom, practice
or tradition of work performance
to
the practical exclusion of
others; 3) prior performance of the work by Agreement-covered
employees under a "mixed practice" obligates Carrier to provide
Article IV notice and opportunity to confer and to make good
faith efforts in accordance with the December 11, 1981 Letter of
Agreement to keep the work "in-house"; 4) Carrier is on notice
by Award 3-28849, issued June 25, 1991, that unmitigated failure
to abide by the notice requirements of Article IV or the good
faith effort commitments of the December 11, 1981 letter in such
"mixed practice" situations might well warrant an award of
monetary damages, irrespective of whether the underlying Scope
Rule claim is sustained; 5) for "mixed practice" disputes
arising prior to the issuance of Award 3-28849 on June 25, 1991,
a proven history of Organization acquiescence to Carrier's
subcontracting certain kinds of work without notice, mitigates
against an award of monetary damages. See Award 3-29792 and
awards cited therein.
Application of these principles to the proven facts of
record leads to a conclusion that Carrier's admitted failure to
give notice or to explore means of assigning Agreement-covered
pLS
NJ. 56-7 -
AWARD NO. 1
- NMB CASE N0. 1
UNION CASE NO.
COMPANY CASE NO. 900277 MPR
6
employees to this "mixed practice" work constituted plain
violations of Article IV of the May 17, 1968 National Agreement,
as reinforced by the December 11, 1981 Letter of Agreement.
Claimants were capable of performing the backhoe and front-end
loader work on claim dates as Machine Operators and would have
been available to do so if Carrier had not utilized them as
lower-paid Trackmen. Their demonstrated monetary damage is the
difference between what each earned as Trackman and what he would
have earned as Machine Operator had he, rather than a
subcontractor employee, operated the machine.
Compensatory damages clearly would be awarded if this claim
had arisen after the date of June 25, 1991, when NRAB Award 3- -
28849 was issued. However, this violation occurred in March 1990
and the record persuasively shows a history of acquiescence or
condonation of such notice and consultation violations in
connection with subcontracting of this particular type of work.
For reasons set forth in Award 3-28849, therefor, no damages are -
awarded in this particular case. See also Awards 3-2-9021 and 3
29792. No matter how appealing the urge to dispense his own
brand of justice, the Chairman is convinced that the disruptive
effect of disregarding established precedents between the same
Parties on the same issues under the same contract language must
militate against an award of money damages for Claimants.
lot_
a
ND-ss&7
AWARD NO. 1
NMB CASE NO. 1
UNION CASE NO.
COMPANY CASE NO. 900277 MPR
7
AWARD 7or reasons set forth in the opinion, the claim is sustained
in part and denied in part, as follows:
1) Part 1 of the claim is not proven.
2) Part 2 of the claim is sustained.
3) Part 3 of the claim is denied.
Dana Edward Eisc airman
Dated at Ithaca. New York on October 14, 1996
Unioi.- ember Company Member
Dated a
Dated t
on
~ L
fJ~~ on