PUBLIC LAW BOARD 210. 5567
AWARD NO. 2
NMB CASE NO. 2
UNION CASE NO.
COMPANY CASE NO. 890405 MRP
PARTIES TO TEE DISPUTE:
BROTHERHOOD OF MAINTENANCE OF WAY
EMPLOYEES
- and -
UNION PACIFIC RAILROAD COMPANY
(former Missouri Pacific Railroad
Company)
STATEMENT OF CLAIM:
"Claim of the System Committee of the Brotherhood that:
(1) The Agreement was violated when the Carrier
assigned outside forces-to perform material
hauling work (hauling black top material) in
connection with repairing grade crossing on
the New Orleans Lower Coast between Mile Post
0 and Mile Post 22 beginning February 3, 1989
and continuing.
(2) The Agreement was further violated when the
Carrier failed to furnish the General
Chairman with advance written notice of its
intention to contract out said work as
required by Article IV of the May 17, 1968
National Agreement.
(3) As a consequence of the violations in Parts
(1) and/or (2) above, Trackmen Gabriel and
Towle shall each be allowed pay for an equal
proportionate share of the total number of
man-hours expended by outside forces
performing the work in Part (1) above.,,
19(-lS
No. 55'&'7
AWARD NO. 2
NMB CASE NO. 2
UNION CASE NO.
COMPANY CASE NO. 890405 MRP
2
OPINION OF BOAU:
On February 3, 1989, Carrier employed an outside contractor
(Greene Construction) to haul cold mix asphalt to various road
crossing work sites on the Louisiana Division. Two (2) Greene
Construction employees worked in conjunction with Carrier Gangs
1649 and 1680 between New Orleans MP 0 - MP 22 on the New Orleans
Lower Coast.
On April 3, 1989, the Organization submitted a claim
alleging that Carrier had violated Rules l and 2 of the
Agreement, Article IV of the National Agreement and the December
1981 Berg-Hopkins "Letter of Understanding." According to the
General Chairman, Carrier's decision to hire the outside
contractor resulted in a "loss of work opportunity (truck driver
job) for the Claimants."
Superintendent of Transportation Services responded to the
claim submitting:
~~ As a result of my investigation into the
merit of your claim, your claim for Loss of
Work Opportunity is completely
unsubstantiated and irrelevant to this case.
Contrary to your contentions, the Carrier has
customarily and traditionally utilized
outside forces to perform the type of work
you describe in this case, and we understand
that outside forces have historically
performed such service without protest from
your Organization. Additionally, such work
is not covered by the Scope of the Agreement;
moreover, even if such work was reserved to
employes of your craft, the fact remains that
none of the employees involved in this case
were actually deprived of a work opportunity.
pLB .po. 5567
AWARD NO. 2
NMB CASE NO. 2
UNION CASE NO.
COMPANY CASE NO. 890405 MRP
3
Based on the above, this claim is
respectfully declined in its entirety."
The Organization appealed the Transportation
Superintendent's decision contending:
"In the past, Carrier had a dump truck
which performed this task and have even
carried this mix in the back of gang trucks.
On March 16 and 17, 1989, a grapple truck was
also used to aid in the work.
Carrier contends that this is not work
falling within the guidelines of our
agreements. However, work of this character
has customarily, traditionallyand
historically been performed by the Carrier's
Track Sub-department forces and is
contractually reserved to them under the
provisions of the Scope Rule. The Carrier's
unilateral and arbitrary action in
prematurely contracting this work to outside
forces was unquestionably contrary to and in
violation of Article IV of the National
Agreement of May 17, 1968.
These Claimants are qualified as
trackman/drivers, are entitled to this work,
and by Carrier allowing a contractor to
perform this work the Claimants are deprived
of a work opportunity. Therefore, it is our
contention that Carrier is in violation of
certain rules of our current working
Agreement of April 1, 1975, especially Scope
Rules 1, 2, 10, 11, Article IV-Contracting
Out, and the Hopkins 'letter of
understanding."
Carrier denied the claim asserting that the Organization had
"failed to identify the actual dates the work was done, how many
hours were required, and who actually performed the work."
Carrier went on to note that the Organization had failed to
demonstrate that the work in dispute had been performed
"historically, customarily and exclusively by the Claimants.,,
PG B wo.
557
AWARD NO. 2
NMB CASE NO. 2
UNION CASE NO.
COMPANY CASE NO. 890405 MRP
4
Carrier readily admitted that it had not served "Notice" to the
General Chairman, maintaining that notice was "insignificant as
the work in this case is not Scope covered." Carrier included a
"partial list" of "similar projects" which had been contracted
out in the past, noting that it did not serve notice on those
occasions either.
Finally, Carrier asserted that:
"A review of our payroll records reveals
that both Claimants were fully employed
throughout the claim period and have suffered
no monetary loss. Both Claimants were, in
fact, receiving considerable overtime
compensation during the claim period. Even
if the Organization were to prevail in
establishing that the Agreement was, in fact,
violated, there is no basis for awarding
monetary relief. I have no intention of
enriching the Claimants for a loss which
never occurred."
During a claim conference, Carrier continued to maintain
that the Scope Rule upon which the Organization premised its
claim is "general in nature" and that the Organization had
"failed to demonstrate that the contested work had been performed
exclusively by the BMWE employees throughout the system by either
custom, tradition or practice."
For its part, the organization reasserted that the work in
dispute is "routine" track work, "normally" performed by
Maintenance of Way track employees on a daily basis. The
Organization went on to note that:
"We have a 'dual' seniority Memorandum of
Agreement signed June 3, 1982, whereby a
Maintenance of Way Employee may hold rights
Pad ?~0.35~7
AWARD NO. 2
NMB CASE NO. 2
UNION CASE NO.
COMPANY CASE NO. 896405 MRP
5
in two departments at the same time. This
Carrier should have bulletined these
positions under Rule 11 to the track employe
and roadway machine department. Under such
the Claimants could have bid in and been
assigned to same. Claimants could have had
the opportunity to be assigned to such
machines. However, in the past, the track
employes have performed the same work
without backhoes, and used small tools and
their hands for many,- many years."
When it became apparent that the Parties were unable to resolve
the dispute, it was placed before this Board for adjudication.
Aside from a difference in dates and Claimants, this case
presents another claim of admitted failure by Carrier to give
Article IV notice and opportunity for good faith consultation
with the Organization prior to contracting out work which has in
the past been performed both by Agreement-covered employees and
outside contractors. This Board developed its principles for
determining such "mixed practice" disputes in Awards 1,4 and 6.
For reasons set forth in more detail in those decisions, we find
that the Organization has not proven a violation of the Scope
Rule but it did prove violations of Article IV of the May 17,
1968 National Agreement and the December 11, 1981 Letter of
Understanding. For reasons set forth in Award No. 1, however, we
shall not award monetary damages in this particular case.
,4-1-
B Na. -l5&?
AWARD NO. 2
NMB CASE NO. 2
UNION CASE N0.
COMPANY CASE NO. 890405 MRP
6
AWARD
For reasons set forth in the Opinion, the claim is sustained
in part and denied in part, as follows:
1) Part 1 of the claim is not proven.
2) Part 2 of the claim is sustained.
3) Part 3 of the claim is denied.
Dana .Edward Eischen, Cha~
Dated at Ithaca, New York on July 23. 1995
Union M er Company Membe
Dat t - Dated at
0M"`-~24S 1GA
on '~ z~
i4'.~
on
®C"~o
6~.-
! l 99 to