BEFORE PUBLIC LAW BOARD NO. 5896
BROTHERHOOD OF MAINTENANCE OF WAY EMPLOYEES
and
CSX TRANSPORTATION
Case No. 181
STATEMENT OF CLAIM:
Appeal of ten-day suspension of Claimant R.E. Paul for working on track without
authority, as a result of investigation conducted on September 18, 2001.
FINDINGS:
Claimant R.E. Paul was employed by the Carrier as a Welder Helper during the time
period relevant to this matter.
On September 13, 2001, the Claimant was notified to appear for a formal hearing and
investigation into charges. that he and Welder Cross had performed welding work on #1 track
outside of the eastern limit of the Welder's Form D, Line 4 Authority #H210 without proper or
additional authority. The hearing was conducted on September 18, 2001. As a result, the
Claimant was found guilty of violating NORAC Rule 132 and Carrier Roadway' Worker Safety
Rules, and assessed a disciplinary suspension of ten working days.
The Organization filed a claim on the Claimant's behalf, challenging the Carrier's
decision to suspend the Claimant. The Carrier denied the claim.
The Carrier contends that the violation at issue was discovered when the Claimant had to
flag down a train that was moving toward his unprotected work location at or near milepost 20.6
on the McCook Subdivision. The Carrier maintains that the Claimant was proven guilty as
charged in that he did occupy controlled track without proper authority. The Carrier asserts that
?L B 589 b
Auld 121
the Claimant admitted his violations, so the only remaining question is the issuance of the
discipline.
The Carrier acknowledges that Welder Cross primarily was culpable, but the Claimant
does bear responsibility in this matter because he failed to utilize the knowledge provided by the
Carrier for his own protection. The Carrier argues that given the severity of the situation and the
possibility of serious damage and harm, the ten-day suspension must be viewed as lenient.
The Carrier further asserts that the Organization's assertions regarding the dispatcher are
unsupported and irrelevant. The Carrier emphasizes that the issue here centers on the
inappropriate handling of the situation by the Claimant and Welder Cross. The Carrier
additionally argues that the transcript is complete, and the Organization's failure to point out any
specific fault demonstrates that its complaints about the transcript represents only the
Organization's attempt to skirt the serious issues present in this matter.
The Carrier contends that the claim should be denied in its entirety.
The Organization asserts that the transcript appears to be incomplete. The Organization
points out that its objection to a particular witness was not included in the transcript.
The Organization goes on to contend that because the transcript makes clear that Welder
Cross was the one primarily responsible for the incident at issue, the Carrier cannot justify giving
a ten-day suspension to the Claimant. The Organization emphasizes that at the time of the
incident, the Claimant had been an employee for only five months, and a welder helper for four
months. The Claimant was not physically qualified on the territory, did not read the authority,
and was not given a job briefing.
The Organization further argues that the transcript demonstrates that the Carrier has two
2
'F ,.B 589 b
A wd 18 I
sets of standards: one for BMWE employees and another one for train dispatchers. The
Organization maintains that the train dispatcher who issued the authority in this~incident was not
held accountable for his actions. Moreover, under NORAC rules, the dispatcher issues
authorities by control points, not mileposts. The Organization points out that Welder Cross
requested authority at Milepost 20.6, not a control point, but the train dispatcher issued the
authority without requesting a control point. The Organization argues that the transcript
demonstrates that the dispatcher issued an authority without knowing the location, yet the
dispatcher was not held responsible for his actions.
The Organization contends that the claim should be sustained, the Claimant made whole
for the ten-day suspension, and these ten days counted toward the Claimant's 2001 vacation
qualifying time.
The parties being unable to resolve the issues, this matter comes before this Board.
This Board has reviewed the evidence and testimony in this case, and we find that there is
sufficient evidence in the record to support the finding that the Claimant was guilty of violating
NORAC Rule 132 and Carrier Roadway Worker Safety Rules. The Claimant admitted his
wrongdoing and that he should have been more diligent in his behavior that day.
Once this Board has determined that there is sufficient evidence in the record to support
the guilty finding, we next turn our attention to the type of discipline imposed. This Board will
not set aside a Carrier's imposition of discipline unless we find its actions to have been
unreasonable, arbitrary, or capricious.
Given the seriousness of the wrongdoing and the relative leniency of the ten-day
suspension, this Board cannot find that the Carrier acted unreasonably, arbitrarily, or capriciously
3
?LB .5896
Acad /81
when it issued the ten-day suspension to the short-term employee. Therefore, the claim must be
denied.
AWARD:
The claim is denied.
ETER R. ME RS
Neutral Memb
Dated: ~ / ~
4