AWARD NO. 4
NMB CASE NO. 4
UNION CASE NO. C-94-5090-1
COMPANY CASE NO. MWA940601AB
PARTIES TO THE DISPUTE:
BURLINGTON NORTHERN SANTA FE
(Former Burlington Northern Railroad
Company)
- and -
BROTHERHOOD OF MAINTENANCE OF WAY
EMPLOYEES
STATEMENT OF CLAIM:
"Claim of the System Committee of the Brotherhood that:
1. The discipline [five (5) day suspension and
letter of censure] imposed upon Mr. D.L.
McKeon for alleged violation of Rule 62 in
connection with his alleged failure to safely
operate Tie Crane BNX 60-00082 on March 22,
1994 was unwarranted, on the basis of
unproven charges and in violation of the
Agreement (System File C-94-8090-1/MWA 94-7
5AA BNR).
2. As a consequence of the above-stated
violation, the Claimant's record shall be
cleared of the charge leveled against him and
he shall be compensated for all wage loss
suffered."
pL8 VD .5q"b
AWARD NO. 4
NMB CASE NO. 0106
UNION CASE NO. C-94-5090-1 -
COMPANY CASE NO. MWA940601AB
2
OPINION OF BOARD:
D. L. McKeon (Claimant) has been employed by Carrier since
1978, and qualified as a Machine Operator in 1985. On March 22,
1994, the date upon which this dispute arose, Claimant was
assigned to Tie Gang TP02 as the Machine Operator on Tie Crane
BNX-60-00082. At the end of the work day, Claimant, who was
pulling a pushcart loaded with ties, entered a stub track to put
his machine away for the evening. Shortly after entering the
side track, Claimant ran into Ballast Regulator BNX 06-00294,
causing damage to both the boom and the motor. Shortly after the
accident, a three (3) man inspection team, comprised of a Foreman
and two (2) Traveling mechanics, inspected Claimant's tie crane.
Said inspection revealed no defects with the track or equipment
which would have caused a failure in its operation.
As a result of the'incident and subsequent inspection ,
Carrier sent Claimant the following letter:
"Arrange to attend investigation in the
Welder's Office, Burlington Northern Depot,
at 14th and Grant Avenue, York, Nebraska, at
1000 hours, Tuesday, April 5, 1994, for the
purpose of ascertaining the facts and
determining your responsibility, if any, for
your alleged failure to safely operate Tie
Crane BNX-06-00082 which struck the head end
FLB (9n · S-qQ
AWARD NO. 4
NMB CASE NO. 0106
UNION CASE NO. C-94-5090-1
COMPANY CASE NO. MWA940601AB
3
of parked Ballast Regulator BNX 06-00294_ at
or about 1548 hours, Tuesday, March 22, 1994,
at Tamora, Nebraska, on stub track. Present
in this investigation in addition to yourself
will be Gordon McGill, work equipment
mechanic. Arrange for representative and/or
witnesses, if desired, in accordance with
governing provisions of prevailing schedule
rules. Please acknowledge receipt and
understanding by affixing your signature in
the space provided on copy of this letter."
Prior to the investigation, the Organization requested the
following:
"I would like to have a copy of the
maintenance log for the month of March for
the machine that Mr. McKeon was operating. I
would also like a copy of the Accident Report
that was filed and any documents or
statements that were made by Mr. McKeon. I
would also understand that their (sic) might
have been a three man inspection on this
incident. I would like a copy of any and all
reports they filed. I would also request
that those individuals that were involved in
this investigation be made available to
attend this investigation."
Carrier provided the requested information.
The investigation was postponed and subsequently held on
April 21, 1994. upon completion of the investigation, Carrier
determined that the accident was due to "Operator error" and not
due to a "mechanical failure" of the machine Claimant was
operating. Carrier assessed Claimant discipline of a five (S)
pt,
a
NO . Sg 0
AWARD NO. 4
NMB CASE NO. 0106
UNION CASE NO. C-94-5090--1
COMPANY CASE NO. MWA940601AB
4
day suspension and letter of censure.
The Organization protested the discipline premised upon the
following:
"In reviewing the transcript of the
investigation it is clear the discipline
assessed is improper and not supported by
factual evidence. The first item is the fact
this machine had a hydraulic leak and when
the crane swung in the proper direction the
oil would leak into the brakes as well as the
rail. In addition, the throttle on this
machine was broken and the Mechanic had
simply wired it to 'run it full'. The
Mechanic on this gang was well aware of the
hydraulic leak, yet he did not repair it.
The Machine Operator cannot force the
Mechanic to fix an item if they do not want
to do it. It is only the Roadmaster or the
Mechanic's Supervisor that can force a.
Mechanic to repair an item.
It is not just the Mechanic on the gang that
ignored the oil leak. It appears, through
reading the transcript, that the machine had
this leak when the gang first started.
Therefore, the shop that worked on this
machine during the winter also ignored the
oil leak. The Mechanic, Gordon McGill, and
Mr. McKeon both testified that two (2) new
brake shoes were in fact changed on this Tie
Crane shortly after it was put back in
service. After the oil leak was finally
fixed, the Mechanic also used starting fluid
to clean the brake shoes on the Tie Crane.
This obviously would not have been done if
there was not oil on them.
Foreman Ferguson testified that Mr. McKeon
Pc8 A),), VSb
AWARD NO. 4
NMB CASE NO. 0106
UNION CASE NO. C-94-5090-1
COMPANY CASE NO. MWA940601AB
S
was not operating his machine at an excessive
speed and he appeared to be in control.
Due to the above stated reasons I am
requesting Mr. McKeon be paid for all time
lost account of this improper discipline
being assessed. I also am requesting the
Claimant's personal record be cleansed of any
reference to this incident."
The organization further asserted that Carrier neglected to allow
Claimant to inspect the rail or machine condition for himself,
and that although he was allowed to "assist" with the written
report regarding the incident, a Carrier clerk had actually
written the accident report in which it was stated that the
primary cause of the collision was "Code H402", the meaning of
which was "unknown" to Claimant, according to the Organization.
Finally, the Organization asserted that "unbeknown" to Claimant
and his representative, Carrier's finding of guilt had actually
occurred on the date of the incident, March 22, 1994, prior to
the actual investigation which was not held until April 21, 1994.
Carrier denied the claim maintaining that:
"I have received your letter of June 2, 1994
appealing the decision to discipline Mr. D.
McKeon for violation of Rule 62 of the
Burlington Northern Railroad Maintenance of
Way Rules for failure to safely operate tie
crane BNX 60-00082 on March 22, 1994 at
Temora, Nebraska.
Pl,g
NJ' 5-q5l,
AWARD NO. 4
NMB CASE NO. 0106
UNION CASE NO. C-94-5090-1
COMPANY CASE NO. MWA940601AB
6
In answer to questions raised in your letter,
testimony at the investigation conducted by
Mr. Chartraw on April 24, 1994 revealed that
although the machine may have had a hydraulic
leak the 3 man inspection conducted after the
incident revealed that the rail was dry and
there was no oil on the brake shoes.
Further, the fact that the throttle was wired
open has absolutely no impact on the braking
system whatsoever. You also note in your
letter that 2 new brake shoes were changed on
the tie crane after it was put back into
service. At the same time, the remaining
brake shoes were cleaned in accordance with
regular maintenance procedures. Finally,
your assertion that the Carrier was
prejudiced prior to the investigation is
simply incorrect."
At the outset, the Organization asserted that Claimant
failed to receive a fair and impartial investigation when
Carrier's finding of guilt occurred on March 22, 1994, a month
prior to the investigation. Additionally, the Organization noted
that Claimant was not notified until "just prior to the closing
of the investigation" that Rule 62 had been cited as part of the
charges leveled against Mr. McKeon. However, those assertions
were raised belatedly and numerous awards hold that such
objections must be raised during the course of the investigation,
or they are considered waived. See for example, Third Division
Award No 22456. __-
n` yA ~~
LLllrrrWAJRD NO.
4
NMB CASE NO. 0106
UNION CASE NO. C-94-5090-1
COMPANY CASE NO. MWA940601AB
7
Further, the Organization failed to show how the FRA code
entered on the F-27 to describe the accident has, in any way,
prejudged Claimant's case. Moreover, the record indicates that
both the Claimant and Roadmaster Nutz provided all of the
information contained in the F-27 to a trained F-27 Clerk who
entered this information into the report just as Claimant and Mr.
Nutz described it. In short, there has been no showing by the
Organization that any irregularities occurred in the filing of
the F-27 report, nor has the organization shown that the
information contained in that report prejudged the Claimant in
any way.
Turning to the merits of the issue, there is no dispute that
on March 22, 1994, the weather was "clear and sunny".
Additionally, the report from the three (3) man inspection team
revealed that there was no oil or viscose-material on the rail ox
brake shoes of the Tie Crane which would have impaired or
diminished the machine's braking ability. In that connection,
Traveling Mechanic McGill, a witness to the accident, testified
that the Tie Crane did not have a history of brake problems, nor
had the Claimant notified him of any problems with the braking
system prior to the accident. Finally,
we-look
to Mr. McKeon's
(L8 )JD
-ST~-J
AWARD NO. 4
NMB CASE NO. 0106
UNION CASE NO. C-94-5090-1
COMPANY CASE NO. MWA940601AB
8
testimony in which he stated:
Q. "You had used the brakes previous to the
accident to aseure that they were working?
A. Yes. I tapped them on the other side of the
crossing to slow down for vehicles. It was
clear so I proceeded on.
Q. But you had used the brakes earlier in the
day to stop your machine?
A. Yes.
Q. With ties on your push cart?
A. Yes.
Q. Did you notice any oil or grease on the rail
prior to the incident?
A. No."
Although much ado has been made of allegations that the Tie
Crane's throttle control was not working properly and that
hydraulic oil had been leaking from the tie crane's oil well,
neither the Claimant nor the Organization offered any evidence on
this record to support that contention. Bare assertions are
insufficient to carry the evidentiary burden on that point. In
fact, in that connection, Mr. McKeon stated:
Q. When you are working your machine out on the
main line, do you operate the machine at full
throttle while you are working it?
A. Yes.
Q. And when you are working it, do you often
start and stop when you are running at full
throttle?
PL'5
'Vi)
.5175D
AWARD NO. 4
NMB CASE NO. 0106
UNION CASE NO. C-94-5090-1
COMPANY CASE NO. MWA940601AB
9
A. Yes.
We can only conclude that the above testimony dispelled any
contentions relative to the braking capabilities of the Tie Crane
when operating at full throttle.
Based on the results of the investigation conducted on March
22, 1994, the date of the incident, and the evidence adduced at
the April 21, 1994 investigation, the Carrier has adduced
sufficient evidence to carry its burden of proof that Claimant
was culpable for the collision. The penalty cannot be deemed
arbitrary, unreasonable or excessive. This claim must be denied.
.7,0G6
/(,o-~a
AWARD NO. 4
NMB CASE NO. 01_06
UNION CASE NO. C-94-S090-1
COMPANY CASE NO. MWA940601AB
AWARD
Claim denied.
Nanny Faircloth Murphy, Chair
Dated at Memphis. New York on October 27. 1997
Union Me/fiber
Dated at
on
Company Member
Dated at
on
-ZLt ~r .. l 3 1 y `i~