AWARD NO. 10
NMB CASE NO. MW-32430
UNION CASE NO.
PUBLIC LAW BOARD NO. 6086
PARTIES TO THE DISPUTE
:
TERMINAL RAILROAD ASSOCIATION
OF ST. LOUIS
- and -
BROTHERHOOD OF MAINTENANCE
OF WAY EMPLOYEES
STATEMENT OF CLAIM
:
(1) The Carrier violated the Agreement when it assigned outside forces (Osmose
Wood Preserving, Inc.) to perform Maintenance of Way and Structures Department
work (steel repairs) on the MacArthur Bridge beginning April 18, 1994 and
continuing (System File 1994-26!013-293-14).
(2) As a consequence of the violation referred to in Part (1) above, furloughed
B&B employes S. Millard, A. Rameriz, J. King and Messrs. S. Wolf, C. Lovett, A.
Cracchiolo, W. Vickers, C_ Carrico, A. Smoot, N. Libell and R. Pruitt shall each be
allowed ten (10) hours' pay at their appropriate straight time and overtime rates for
each regularly assigned workday and rest day the outside forces performed the work
in question beginning April 18, 1994 and continuing until the violation ceases.
OPINION OF BOARD:
Of note, this case is a companion claim to PLB 6086 Case No. 8 (Third
Division Dkt. No MW-32154), which was dismissed due to procedural irregularity in the on-
property appeal. No such procedural defect taints the present claim. Carrier sent the General
Chairman a separate Article IV letter in March 1994, concerning the work at issue in this claim.
Although both parties make occasional references to the ongoing nature of this project, they have
pL'B foo9lo
AWa
~o
AWARD NO. 10NMB CASE NO. MW-32430
UNION CASE NO.
COMPANY CASE NO.
mutually have treated this Spring 1994 claim
filed as aseparate and distinct matter from that which
we dismissed in Award No. 8.
On March 11, 1994, Carrier informed the Organization of its intent to contract out to Osmose
Wood Preserving, the work of certain steel repairs to the MacArthur Bridge. The following day,
March 12, 1994, the General Chairman replied to Carrier's notification, asserting that Carrier had
both the equipment and manpower to perform the "steel repair work"and that Carrier "has not
maintained, liked or tried to reduce any contracting". The General Chairman concluded his letter
by requesting that the proposed locations of work and a copy of the contract which Carrier entered
into with Osmose be provided to him prior to their scheduled conference date of March 24, 1994.
In reply to the General Chairman's letter, Carrier responded with the following:
1. Osmose is continuing steel repairs started last year which were not completed prior
to Carrier's seasonal winter reduction of forces and Carrier's notice to Osmose to
also discontinue work for the season. Contracting notice was served for this work
on September 10, 1993 and is currently in the claims process. Contractor will be
completing some repairs from last year as well as starting additional repairs for this
year. The steel left on the bridge was for the work not done and was paid for last
year.
2. The locations of the work to be performed are spread all
throughout the
massive
MacArthur Bridge and approaches, and will not be itemized in this letter. The
work involved consist of fabrication, cleaning, painting, erection and repairs of
various structural steel members and components.
3. You state that Carrier did not include the fact that this work to be performed is
'maintenance work'. Whether or not this work is maintenance work is irrelevant to
Carrier's letter of notification and Carrier's right to contract out certain work.
4. Regardless of
whether or
not our employees are capable of performing this work,
there exists too much short-term work to be performed by Carrier's own forces that
necessitates contracting out.
5. Becauseofotherprojectsscheduledforthisyear,theCarrierrsMaintenanceofWay
employees and equipment are already committed.
-a- -
PLI3 looS6
A0 to
AWARD NO. 10
NMB CASE NO. MW-32430
UNION CASE NO. _
COMPANY CASE NO.
6. You have requested a copy of the contract with Osmose for this work, but I must
deny this request as there are no agreement provisions or requirements governing
disclosure of same.
The conference was held as scheduled during which the General Chairman offered the
following options regarding the proposed contracting out:
1. Carrier could transfer some track employees to the bridge and
building department.
2. TRRA BMWE employees could work alongside the contractor
forces.
3. Some of the work, such as steel fabrication, could be done by TRRA
forces during the winter furlough.
Carrier rejected each of those proposals and contracted out the work in dispute and by claim letter
dated May 23, 1994, the General Chairman initiated this dual-basis claim.
There is no evidence on this record that Carrier failed to comply with the good-faith notice
and conference requirements of Article IV and the December 11, 1981 Borg-Hopkins Letter. Thus,
the case is joined on the merits of the Organization's claim that the contacting out of this particular
work, described as "fabrication, cleaning, painting, erection and repairs of various structural steel
members and components" was reserved to Agreement-covered employees by custom, practice and
tradition of
performance under the Scope Rule of the Schedule Agreement.
Rule 2, "Classification", Rule 3 "Seniority", Rule 5 "Consideration"Rule 6 "Department
Limits" and Rule 8 "Assignments" do not expressly reserve work and Rule 1 "Scope" is general
rather than specific in its wording. Carrier argues that the claim must fail if the Organization does
not prove that it has "exclusively" performed the claimed work in the past. However, authoritative
precedent involving these same parties establishes that the Organization can prevail in a contracting-
-3-
pl.B (00$b
Awc to
AWARD NO. 10
NMB CASE NO. MW-32430
UNION CASE NO.
COMPANY CASE NO.
out case under the "general" Scope Rule even if it cannot prove `exclusivity". See NRAB Third
Division Award 32748.
In subcontracting orout-sourcing claims under a general Scope Rule, the Organization makes
out a prima facie case by proving a custom, practice and tradition of regularly and consistently
performing the claimed work on more khan a "mixed practice" basis. The rational for that holding
is well-described in Third Division Award29007,involvingthesamecontractlanguagebutdifferent
parties, as follows:
Our review of the Agreement suggests that the Exclusivity Doctrine is not an appropriate test for
Scope coverage vis-a-vis employees and outside contractors. The language of Article IV of the
parties' Agreement clearly demonstrates, to us, an intent to establish an environment whereby the
Organization should, under appropriate circumstances, be able to agree to the contracting out of
bargaining unit work without suffering permanent erosion of the pcotectedwork. Such a cooperative
environment is also consistent with the provisions of the December 11, 1981 National Letter of,
Agreement. Yet such cooperative agreements would be incompatible with an exclusivity requirement. After workhadbeenperformedbyanoutsidecontractor,albeitbyagreement,theOrganization
would no longer be able to prove exclusive performance by the employees- Such a result is not
logically consistent with the cooperation terms of Article IV of the Agreement or the December 11,
1981 National Letter of Agreement. We conclude, therefore, that evidence demonstrating something
less than strict exclusive performance is sufficient to establish Scope coverage .... [However] the
Organization has the burden of proving by a preponderance of evidence that the disputed work is of
a character customarily and historically performed by the employees it represents.
In order to put Carrier to its proof that one of the contracting out exceptions applies, the
Organization must first make out a prima facie showing of such work reservation by practice under
the general Scope Rule. Careful analysis of the record evidence shows that in this particular case -
the Organization has not carried its burden ofpersuasion on that critical point. Disputed bare general
assertions by the General Chairman and statements written by B&B employees in 1990, describing
their experience in pouring and finishing concrete, do not suffice as proof that Agreement-covered
employees regularly and consistently performed the work of steel bridge structural fabrication and
renovation which is the subject of this May 1994 claim. While, as described earlier, this evidentiary
-4-
?(.8
(ooe6 A-1D to
AWARD NO. 10
NMB CASE NO. MW-32430
UNION CASE NO.
COMPANY CASE NO.
burden does not to require a showing of exclusive performance, it does require proof of more than
a shared or mixed practice.
On this record, we find that the Organization's evidence falls short of demonstrating such regularity, consistency and predominance in the performance of the disputed work of "fabrication,
cleaning, painting, erection and repairs of various structural steel members and components" to
warrant a finding that it has customarily and historically performed that work. In this particular
case, the Organization has not satisfied its initial burden of proving that the disputed work is
reserved to the Agreement-covered employees by regular and, consistent performance under the
general Scope Rule in the Schedule Agreement.
AWARD
Claim denied.
1
-1
Dana Edward Eischen, Chairman
Signed at Spencer, NY on August 26, 2000
Union
s
ember _r
/3//o O
Company Member
-5-