AWARD NO. 12
NMB CASE NO. MW-32587
UNION CASE NO.
COMPANY CASE NO.
PUBLIC LAW BOARD NO. 6086
PARTIES TO THE DISPUTE
:
TERMINAL RAILROAD ASSOCIATION
OF ST. LOUIS
- and -
BROTHERHOOD OF MAINTENANCE
OF WAY EMPLOYEES
STATEMENT OF CLAIM
:
(1) The Agreement was violated when the Carrier assigned Norfolk and Southern
employes to perform Maintenance of Way and Structures Department work (pulling
spikes on the inner guard rail) on the MacArthur Bridge, Merchants Bridge and West
Belt beginning July 25, 1994 and continuing (System File 1994-38!013-293-14).
(2) The Agreement was further violated when the Carrier failed to make a goodfaith effort to reduce the incidence of contracting out scope covered work and
increase the use of their Maintenance of Way forces as required by the December 11,
1981 Letter of Understanding.
(3) As a consequence of the violations referred to in Parts (1) and/or (2) above,
furloughed Track Sub-Department employes D. Bean, A. Ramirez, W. Wiley, J.
King, J. Gatlin, M. Kayser, M. Mitchell and Messrs. R. Gartner, W. Bailey, J.
Derochie, W. Green, R. Gray, D. Stogner, R Gower, R Glenn, J. West, L. Crouch,
D. Matthes, C. Jefferson, O. Rodriquez, J. Wilson, J. Headrick, J. Mason, R. Brown,
C. Laden, S. Gray, L. Gates, R White, Sr., E. Schuessler, J. Fenton, T. Allen, C.
Perkins, R. Stewart, R. McCranie, M. Hudson, E. Myers, C. Perry, A. McCarter, J.
Mason, T. Harris, C. Owens, C. Wicks, S. Millard, R. Kurtz, T. Reed, M. McCann
and D. Schindler shall each be allowed eight (8) hours' pay per day, at their
respective straight time rates, and any overtime performed by the N&S forces
beginning July 25, 1994 and continuing until the violation ceased.
OPINION OF BOARD: By letter ofJuly 6,1994, Carriergave the BMWE General Chairman Article
IV written notice of its intent to contract out
to
the Norfolk Southern the following projects on
TRRA property:
1) MacArthur Bridge- Valley Junction turnout, switches #222 and #224 to north end
of Crossover #1 at Valley Junction. Contractor to provide labor, equipment and
material to install new 1361b. CWR and OTM, and relocate trackage to the center
of the bridge. Also remove the existing 1001b. guardrail and realign the existing
115# jointed rail as inner guard rail.
2) MacArthur Bridge - Valley Junction turnout, Switches #222 and #224 to the ALS
Railroad hand-throw crossover. Contractor to provide labor, equipment and
material to install 15,000 linear feet of 1151b. CWR and OTM.
3) Merchants Bridge - Contractor to provide labor, equipment and material to install
6,200 linear feet of 115Ib. CWR and OTM, and relocate trackage to center of the
bridge. Also remove existing 1001b. guard rail, realign the existing 1151b. jointed
rail as inner guard rail and install six pairs of rail expansion joints.
4) Merchants Bridge - West Approach. Contractor to provide labor, equipment and
material to install 4,000 linear feet of 7361b. CWR and OTM.
5) MacArthur Bridge - Main Spans. Contractor to provide labor, equipment and
material to install 1361b. CWRand OTM, and relocate trackage to center of bridge.
Also remove existing 1001b. jointed rail inner guard rail and realign the existing
1151b. jointed rail as inner guard rail, and install six pairs of rail expansion joints.
6) MacArthur Bridge-North Approach. Contractor to provide labor, equipment and
material to install five #12 - 1361b. turnouts.
7) West Belt - Pennsylvania Avenue to Rock Island Junction. Contractor to provide
equipment and labor to install 1.9 miles of 1151b. CWR and OTM and removal of
existing 1001b. jointed rail and OTM.
8) Various locations - Contractor to provide equipment and labor to install 16,700
crossties.
Carrier asserted that the work was being contracted out because it "was not well equipped
to perform a project of this magnitude", because Carrier's own track force employees "were already
committed" to other projects. The Chief Engineer concluded the correspondence by informing the
-2-
!PLQ 6o$(. Awb lZ.
AWARD NO. 12
NMI3 CASE NO. MW-32587
UNION CASE NO.
COMPANY CASE NO.
General Chairman that should he desire to conference the issue, he would be available at the General
Chairman's convenience.
Following a requested conference on July 20, 1994, Carrier began utilizing the N&S to
perform the described work on July 25, 1994 and the General Chairman filed the instant claim on
August 29, 1994. That claim, on behalf offorty-seven (47) currently working and furloughed Track
employees, allege that Carrier's contracting arrangement with the Norfolk Southern Railroad violated
the current Schedule Agreement, as well as the 1968 Agreement on contracting. Specifically, in that
dual-basis claim, the General Chairman alleged on the merits and the good-faith aspects,
respectively, as follows (Spelling, punctuation and emphasis as in original):
In your letter dated August 18, 1994 you state that the carrier recognizes the fact that there are several
employees are laid off, I must point out to you that
there has been Seven (71 employees from the
N&S
not doing anything but pulline spikes sence July 25. 1994 on inner guard rail, this is still continuing
as I write this letter.
There is no excess for you not calling back these laid off employees this is there
agreed to work under there contract not other employees from other properties, and the statement of
piece meal, I would like to bring to your attention once more Board award No. 28998 on this property
that clearly states that there is noting wrong with separating work.
As of July 26, 1994 the
N&S
has had a Burro operator working moving rail on both the bridges on
regular time and overtime there is no reason why our burro operators are not also being allowed this
work opermnity.
In April 1994 the Carrier was already preparing for this contracting. The Carrier was already
unloading the 16,700 ties mentioned in your contracting notice, please see my claim 1994-23. Due
to your notice not being until July 6, 1994, I must state that this contracting was clearly not in good
faith. We fill (sic) this is truly unfaithful and not in compliance with the 1968 Agreement on
contracting of work and the letter of understanding to reduce contracting between the Carrier and
BMWR
The Chief Engineer denied the claim by letter of October 27, 1994. Regarding the General
Chairman's assertion that the work in dispute was contracted in bad faith prior to Carrier's July 6
notice, he stated:
AWARD NO. 12
NMB CASE NO. MW-32587
UNION CASE NO.
You mentioned that in April 1994 Carrier was preparing for'this contracting' by unloading 16,700 -
ties. This is totally untrue. Although the ties were ordered in early 1994 because of along lead time,
Carrier had not yet finalized its 1994 work program until later after evaluating various proposals. No
contract was executed to perform this work until several days after our conference of July 20, 1994.
The delivery, unloading and distribution of ties, which was all done by TRRA forces, started in April
but continued all through the summer. In fact, to date, there are still two more truck loads of ties due
for delivery.
With respect to the merits, the Chief Engineer denied the claim for the following reason:
`Very simply put Carrier's employees, equipment and supervisor (sic) people were already
committed to other work for the entire construction season" and the furloughs were "a seasonal
(winter) adjustment". Finally, he "took exception", for various reasons, to four (4) of the 47
Claimants which the General Chairman had fisted and, with respect to the remaining forty-three (43)
individuals, contended that they did not suffer any work loss during the contract work since they
had been employed on other work for Carrier, including working ahead of, or with, the NS track
forces distributing ties, rail and other track materials.
In the interim appeal letter dated December 20, 1994, the General Chairman conceded that
the claims of Messrs. J. DeRochie and R. Gartner were limited by periods of disciplinary suspension
but disputed the challenges to Messrs. King and Ramirez. With respect to the merits, however, the
General Chairman further asserted the following points:
[T]he carrier has a obligation to use its work force to perform this contracted work, the N&S
employees have worked from July 25, 1994 in good weather through this date, also in good weather,
while our employees have been laid off, these laid off employees have not been offered a recall or
allowed a job performing their classified work.
On the property awards No. 23928 allows employees compensation of equal proportionate share of
number of hours contracted out by the carrier, on the property Award No. 28998 states that that a
manpower shortage that is prolonged and persistent is not recognized as reason for contracting out
work belonging to a craft and class of bridge and building mechanics. Award No. 29938 that was
denied on this property stated that the carrier because it had tried to hirer employees and due to all
of its employees working the board denied the claim, in this claim the carrier has not hired since 1991,
has not replaced furloughed, sick our hurt employes over twenty six (26), since 1992.
-4-
PL 13 (ooh
As-#4a It
AWARD NO. 12
NMB CASE NO. MW-32587
UNION CASE NO.
Mr. Trices states that there are several employees that may not be proper claimants, I disagree these
employees ( Ramirez & King) have not been recalled under Rule 16 (King subject to appeal). Mr.
Trice would be correct on the other two employees as to limiting there claim.
The carrier now has around 37 track employees working and in 1991 had over 60 track employees,
and as you are aware this is not a sudden loss of employees, and since this time of 1991 the carrier,
has had more contractors on the property than employees.
The carrier has a obligation to maintain a force to perform the work that has been contracted out, Mr.
Trice understands and knows that we have perform this work in the past on the Eads Bridge, the
Merchants Bridge the MacArthur Bridge, on the main lines all over the property in St. Louis and IL,
when extra equipment was needed the carrier rented it. I have saw the work being performed with
these contractors and it is work that we have always done in the past.
In additional correspondence predating the Carrier's final denial letter of March 22, 1995,
January 25, 1995 interim denial letter, the General Chairman also protested the layoff of several of
the Claimants in December 1994 and January 1995, while the N&S track forces continued to
perform the work which is the subject of this claim. In that connection, the General Chairman's
letter of February 15, 1995 reads as follows:
Please refer to your letter of denial dated January 25, 1995, on system file & claim 1994-38 on the
behalf of 47 track employees and Bridge employees this claim is due to the carrier allowing the N&S -
track employees to perform work on the Merchants Bridge, and the West belt main lines while several
employees were laid off prior to the contracting started on July 26, 1994, during, and after up to
December 16, 1994. A additional 20 employees were laid off again on January 4, 1995 as well as the
seven that has been laid off all through this contracting, the N&S employees were allowed to return
to the property on January 10, 1995 even after this lay off please see my letter to you dated January
10, 1995, on January 10, 1995 at there end of tour of duty the N&S employees were removed from
the property and work was completed with the carriers forces that had not been laid off.
Finally, during claims conferencing the General Chairman supplemented his own undisputed
statements concerning prior performance by Agreement-covered employees of work identical to the
work claimed in this case with written statements dated August and November 1994 from Claimants
Bailey, Stogner and Wilson describing their prior performance of this work.
In response, Carrier's Director Labor Relations and Personnel issued a generic denial by
letter of March 22, 1995, reading as follows:
_g_
:FL$ bo9b
AmsD IZ
AWARD NO. 12
NMB CASE NO. MW-32587
UNION CASE NO.
COMPANY CASE NO.
This will confirm our conference of February 21, 1995, wherein we discussed claim identified by
Organization File
No. 1994-38, on behalf of various Track and B&B employees account contracting
out work on the MacArthur Bridge, Merchants Bridge and the West Belt.
The instant claim must fail for the following reasons:
1. The Organization was properly notified in accordance with the contracting-out provisions
contained in the
1968 Agreement between the parties.
2.
The work to be performed, considerable bridge work and work on the West Belt, is not work
that cannot be subcontracted out.
3. Carrier forces are not well-suited to handle projects of the magnitude involved in the instant
claim.
4.
The disputed work is of a character customarily and historically contracted out.
5. The BMWE Scope is a general Scope Rule and does not reserve exclusively the disputed
work to BMWE-represented employees.
There is simply no valid basis for overturning Chief Engineer Trice's decision of the instant claim,
which decision is herewith reaffirmed and claim remains respectfully declined in its entirety.
There is insufficient evidence in this record to support the allegation that Carrier violated the
good faith notice and conference requirements of Article IV and the Borg-Hopkins letter in this case.
But for reasons fully explained fully in Awards 3,4,6,10, 11 and 13 of this Board, the Organization
presented persuasive detailed record evidence of a prima facie violation of the Scope Rule in the
contracting out of the work which is the subject of this particular claim. None of that evidence was
addressed in the initial or interim denials and generic unsupported counter-assertions in the final
denial letter are not an effective rebuttal to the Organization's detailed evidence. Finally, Award
29998 is distinguishable on its facts and it does not overrule the earlier on-property holding in
NRAB Third Division Award 28998 that a prolonged and persistent manpower shortage does not
justify
contracting out the Agreement-covered work of furloughed employees
-6-
fLa boat
Ih.'fl 11.
AWARD NO. 12
NMB CASE NO. MW-32587
UNION CASE NO.
As this Board held in Awards 3, 6, 11 and 13, citing NRAB Third Division Awards
28998,31756 and 32748, between these same Parties, there is ample precedent for requiring Carrier
to make the named Claimants whole for the proven violation of the Scope Rule in this case. There
is a divergence of authority on this property concerning payment of monetary damages to "fully
employed Claimants", but for reasons articulated by the Third Division in Awards 31756 and 32748,
we find such damages appropriate in this case. Cf., Third Division Awards 29938 and 30829. As
in Third Division Award 31756, we will remand the matter to the property for the Parties to
determine the number of hours outside contractor forces spent performing the work described in the
notice letter of July 6, 1994, during the period July 25, 1994 through January 10, 1995, which is the
subj ect matter of this claim. Once the final determination is made as the number of such hours and
damages have been calculated at the applicable wage rates, we further order that the liquidated
damages be divided equally among the employees named as Claimants in the instant case (including
Claimant Ramirez, unless Carrier can show that he released or waived this claim, but with
appropriate limitations on the damages for Claimants J. Derochie and R. Gartner).
_7_
pL Q
(pasta
hw o 12
AWARD NO. 12
NMB CASE NO. MW-32587
UNION CASE NO.
COMPANY CASE NO.
AWARD
1) Claim sustained to the extent indicated in the Opinion. -
2) Carrier shall implement this Award within thirty (30) days of its execution by a
majority ofthe Board.
Dana Edward Eischen, Chairman
Signed at Spencer, NY on August 26, 2000
Union ember r9 /3 /OO Company Member
_g_