BEFORE PUBLIC LAW BOARD NO. 6239
BROTHERHOOD OF MAINTENANCE OF WAY EMPLOYEES
and
CSX TRANSPORTATION
Case No. 61
STATEMENT OF CLAIM:
Appeal of the thirty-day actual suspension (time served) issued to Claimant
A. J. Gerakis as a result of investigation held on July 26, 2005, in regards to
Claimant's failure to properly follow Carrier Operating Rules, Safety
Rules, and Procedures resulting in damage to Carrier property, specifically
Regulator BR9832 and Locomotives CSXT8105 and CSXT7366
FINDINGS:
The Claimant was employed by the Carrier as an `A' Operator at the time
of this claim.
On June 23, 2005, the Carrier notified the Claimant to appear for a formal
investigation to determine his responsibility, if any, in regards to an incident that
occurred on the SKCT CAT Surfacing Unit on June 8, 2005, on the Indianapolis
Line Subdivision near Milepost QI191.3 at West Ansonia, Ohio. The Carrier
notified the Claimant that as a result of his failure to follow Carrier Operating
Rules, Safety Rules, and Procedures, Carrier property was damaged by Train
Q34907, specifically Regulator BR9832 and Locomotives CSXT8105 and
CSXT7366.
After one postponement, the hearing took place on July 26, 2005. On
August 11, 2005, the Carrier notified the Claimant that he had been found guilty of
'PLB W13q
Awd
to I
all charges and was being assessed discipline of a thirty-day actual suspension
(time served), which began on June 9, 2005, and ended on July 8, 2005.
The parties being unable to resolve their dispute, this matter comes before
this Board.
This Board has reviewed the evidence and testimony in this case, and we
find that the Carrier has failed to meet its burden of proof that the Claimant was
sufficiently responsible with respect to an incident that occurred on the SKCT
CAT Surfacing Unit on June 8, 2005, on the Indianapolis Line Subdivision near
Milepost QI191.3 at West Ansonia, Ohio. There is no question that there was a
regulator, BR9832, working in the Claimant's workgroup that was struck by Train
Q34907 that caused damage to the regulator and two locomotives. However, a
thorough review of the transcript of the investigation involving the Claimant
reveals that there is simply insufficient evidence to connect the Claimant to any
responsibility for that incident.
It is fundamental that the Carrier has the burden of proof in cases of this
kind It is not enough to prove that an incident occurred; it must be shown that the
Claimant violated certain Carrier rules or, in some way, failed to take the proper
precautions and thereby caused the incident in question. In this case, the Carrier
has failed to make that connection, or nexus, and, therefore, this Board holds that
there is an insufficient basis to support the thirty-day suspension that was issued to
the Claimant.
Therefore, this Board must find that because of the Carrier's failure to meet
2
?I.8 4a3q
A wd (of
its burden of proof, the claim must be sustained. The suspension shall be removed
from the Claimant's record and he shall be made whole.
AWARD:
The claim is sustained
1 TER ERS
Neutral Member
Dated: S
~W
~~ (o
3