AWARD NO. 23 CASE NO. 23

PUBLIC LAW BOARD NO. 6249

PARTIES ) BROTHERHOOD OF MAINTENANCE OF WAY EMPLOYEES
TO )
DISPUTE ) UNION PACIFIC RAILROAD COMPANY (FORMER SOUTHERN
PACIFIC TRANSPORTATION COMPANY (EASTERN LINES))

STATEMENT OF CLAIM

Claim of the System Committee of the Brotherhood that:


1. The Agreement was violated when the Carrier assigned an employe of an outside contractor (Pat Baker Contracting Company) to remove vegetation, grade and build a diesel storage facility at San Antonio, Texas beginning September 16, 1996 and continuing (System File MW97-31/BMW 97-72 SPE).


2. The Carrier further violated the December 11, 1981 Letter of Agreement when it failed to make a good-faith effort to reduce the incidence of outside contracting and to increase the use of its Maintenance of Way forces.


3. As a consequence of the violation referred to in Parts (1) and/or (2) above, Track Foreman C. R. Lohse, Track Laborer E. L. Rodriguez, Machine Operators J. E. Hasty, J. Salaiz, D. B. Wells, F. A. Hasty, K Magirl and M. F. Lieffler shall each be com-



OPINION OF BOARD
By notice dated August 26, 1996, the Carrier advised the Organization of its intent to contract out certain

work as follows:

Presently at San Antonio. Texas, locomotive diesel fuel is loaded into tank cars directly from tanker trucks at an uncontained area. The Company's plans in this regard are to construct a railroad tank car loading facility utilizing an existing fuel storage tank. Two (2) diesel fuel loading tracks along with a fueling platform and spill containment system will be constructed.


In connection with the above, it is the Company's intent to utilize a contractor(s) to perform the following work:


PLB 6249, Award 23

C. R. Lohse, et al.

Page 2



Company forces will be utilized in constructing the two (2) diesel fuel loading tracks. installing the prefabricated overhead fuel track/walkway platform and installing the spill containment system.


Conference was held. The Carrier contracted the work. This claim


followed.

In its appeals, the Organization maintained that maintenance of


way employees "... performed this exact type of work along with a carrier owned equipment in the past ... [t]he Carrier has their own machinery and no special equipment is necessary to do the work ... B&B employees recently completed with other Carrier maintenance of Way employees a diesel fueling facility at El Paso, Texas without contractor forces ... this work has historically

and traditionally been done by
Maintenance of Way Employees."
In its December 12, 1996 denial
from Engineer B. L. Reinhardt, the following:
Carrier stated:

Review of Carrier records indicates that on the dates in question, all employes mentioned above were working and were being utilized in conjunction with the contractor to perform work at Kirby Yard. The appropriate notice was filed with the organization regarding the work mentioned. There was no loss of time or job opportunity for these employes.


The Carrier further denied the Organization's appeals by letter dated March 12, 1997:


There is no basis for compensating Claimants "forty (40) hours of overtime. Arbitration Awards have consistently held that payment at the punitive rate is only for work actually performed.


Without prejudice to above, after making an investigation into this matter, Carrier's position is correctly stated in Mr. B. L. Reinhardt decision of December 12. 1996.


For your ready reference attached is a copy of statement from Division Engineer D. W. Morrow who has knowledge of this claim.


Per the attached "Daily Activity (DAR) Report". Claimants were on duty and were compensated for service performed on claimed dates, therefore, they were not available on dates claimed.


A statement from Division

Engineer D. W. Morrow added the

PLB 6249, Award 23

C. R. Lohse, et al.

Page 3


A review of our records indicates that on the dates in question all employes mentioned above were working and were being utilized in conjunction with the contractor to perform work at Kirby Yard. The appropriate notice was filed with the Organization regarding the work mentioned. There was no lost [sic] of time or job opportunity for these employes. It is for the reasons stated above that I feel that this claim lack [sicl merit and no violation of agreements exists, therefore it should be denied in it's [sic] entirety.


With respect to the Carrier's exclusivity argument, in Award 11 of this Board we stated the following:

The Carrier argues that the Organization has not shown that covered employees performed the disputed work on an exclusive basis. But. as we have held before, lack of exclusive performance of the work by covered employees is not a defense to subcontracting claims. See Award 13 of this Board:




The question is whether °[t]he work in dispute is '... work within the scope of the applicable schedule




As in Award 11, there can be little real dispute that the contracted work was work "within the scope" of the Agreement. The disputed work - described in the claim - is classic maintenance of way work which falls "... within the scope of the applicable schedule agreement ...." Lack of exclusive performance of the work is therefore not a defense the Carrier can rely upon for us to deny this claim.

Close examination of the record developed on the property shows the following correspondence from the Carrier:






PLB 6249, Award 23

C. R. Lohse, et al.

Page 4


The Carrier's obligations do not just flow from Article 36. While subject to much debate concerning the extent of what is required by it, there is a further obligation found in the December 11, 1981 letter:


The carriers assure you that they will assert good-faith efforts to reduce the incidence of subcontracting and increase the use of their maintenance of way forces to the extent practicable, including the procurement of rental equipment and operation thereof by carrier employees.


We can only decide these cases on the record developed by the parties. Here, for all purposes, we have a record from the Carrier consisting of a notice of subcontracting; a general denial of the claim; objections to the scope of the requested relief; and a defense which states that no-


tice was given and the employees were working. As found in Award 11 of this


Board:

... [T]o successfully defend a claim like this, the Carrier's obligations extend beyond merely stating that it gave notice and held a conference and the relief sought is improper. Here, given the nature of the Organizations challenge, in the development of the record on the property the Carrier must show some reason why it nevertheless continued with the subcontracting. The extent of the Carrier's obligations in these cases is often open to debate. But here, in face of the Organization's assertions that employees and equipment were available, the Carrier must do more in the development of the record than it did. On that basis, the claim must be found to have merit.


See also, Third Division Award 30182 ("... [O]ther than argument, the Carrier offered no evidence of justification at all in the on-property handling of the dispute.").

With respect to the remedy, as we stated in Award 11:


PLB 6249, Award 23

C. R. Lohse, et al.

Page 5


Make whole relief shall therefore be required. 1

The claim shall be sustained. Claimants shall be compensated in accord with the Agreement provisions based upon the number of hours worked by the contractor's forces. The matter is remanded to the parties to determine the amount of relief Claimants shall receive.


AWARD

Claim sustained in accord with the opinion.











Dated: 2' a`E -6 2

That rationale must apply in cases such as this where Claimants may have been working on the same project as the contractor's forces. There is no reason in this record to show why Claimants could not have been scheduled to perform the work or could not have performed the work on an overtime basis.