Claim of the System Committee of the Brotherhood that:
1. The Agreement was violated when the Carrier assigned outside forces (North American Railway Service and Benton & Brown, Inc.) to perform Bridge and Building and Roadway Machine Subdepartment work (make repairs, remove and replace bridge ties) on the railroad drawbridge in the vicinity of Mile Post 95.0, Calumet, Louisiana beginning December 26, 1996 through January 11, 1997 (System File MW-9785/ 1048346 SPE).
2. The Agreement was further violated when the Carrier failed to furnish the General Chairman with advance written notice of its intent to contract out the work described in Part (1) above in accordance with Article 36.
4. As a consequence of the violations referred to in Parts (1) and/or (2) above, Messrs. A. J. Dalfrey, R. Alex, L. Huval, D. P. Barras, M. J. Boney, H. G. Olivier, R. W. Leger and M. E. Hanks shall
Without prior notice to the Organization, the Carrier contracted the work described in the claim to outside forces.
The claim in this case raises similar issues decided in Award 28 of this Board. For reasons fully discussed in Award 28, this claim shall be sustained with the same remedy.
Claim sustained in accord with the opinion.