NATIONAL MEDIATION BOARD
PUBLIC LAW BOARD 6537
BURLINGTON NORTHERN SANTA FE, INC.
(FORMERLY ST. LOUIS-SAN FRANCISCO RAILWAY COMPANY)
(Carrier)
and
BROTHERHOOD OF MAINTENANCE OF WAY EMPLOYEES
(Organization)
Carrier File No. 12-99-0044
BMWE File No. B-2021-2
NMB Case No. 0102
Award No. 1
STATEMENT OF CLAIM
Claim of the System Committee of the Brotherhood that:
(1) The Agreement was violated when the Carrier assigned
outside forces to perform Maintenance Way work (operate one
front-end loader, three backhoes, five track hoes, three
trucks and lowboys, one train, and two earthmovers) in
connection with siding extension construction work in Palos,
Alabama between Mile Posts 710.85 and 715.18 on the
Birmingham Subdivision of the Southeastern Division
beginning December 28, 1998 and continuing.
(2) The Agreement was further violated when the Carrier
failed to provide the General Chairman with proper advance
notice of the Carriers intent to contract out such work or
to make a good faith effort to reduce the incidents of
subcontracting and increase the use of its Maintenance of
Way forces as required by Rule 99 and the December 11, 1981
Letter of Agreement.
(3) As a consequence of the violations referred to in
Parts (1) and/or (2) above, Special Equipment Operators
B.G. Oliver, E. Gulley, A.C. Hall, J.L. Wright,
R. Duckworth, J.D. Richardson, B. L. Hambrick, C.E. Green,
and three Senior Trackman Drivers were deprived of twelve
hours at their respective rates of pay for each day worked
by the contractor beginning December 28, 1998 and continuing
as long as the contractor continues to perform the disputed
work.
NMB Case No. 0102 2
Award No. 1
PT ,P rF1'1
FINDINGS
Upon the entire record and all the evidence, after the
March 27, 2003 hearing at the Carrier's office in Fort
Worth, Texas, the Board finds that the parties herein are
Carrier and Employees within the meaning of the Railway
Labor Act, as amended, and that this Board is duly
constituted by agreement and has jurisdiction of the parties
and of the subject matter.
DECISION
Claim denied.
A hearing was held in the above-entitled matter on
March 27, 2003 before Public Law Board 6537, comprised of
Roy C. Robinson, Organization Appointed Arbitrator:
William A. Osborne, Carrier Appointed Arbitrator: and
Daniel F. Brent, duly designated as Impartial Referee. The
claimant was notified of the time, date, and place of the
hearing. The claimant's letter submission dated
September 9, 2002 was considered by the Board.
NMB Case No. 0102 3
Award No. 1
r*n cc»
NATURE OF THE CASE
Claimants contend that they were improperly deprived of
work opportunity to perform maintenance of way work
operating various equipment during the construction of a
siding extension at Palos, Alabama between Mile Posts 710.85
and 715.18 on the Birmingham Subdivision of the Southeastern
Division of the Carrier. More particularly, the work
consisted of constructing a 2,960-foot-long track siding
extension on the north end and an extension of 12,050 track
feet on the south end of the existing siding at Palos,
Alabama.
This work was performed by outside contractor forces
who also constructed two storage tracks 8,397 feet in length
and 8,026 feet in length, respectively, as well as 31,435
track feet of new trackage. In addition, the outside forces
were utilized to install one No. 20 turnout, four No. 15
turnouts, three No. 20 cross-over frogs, and an unspecified
quantity of track retourments and realignments, including
one No. 20 turnout and two No. 15 turnouts. The work
commenced on December 28, 1998 and continued thereafter.
The outside contractor's forces worked from 6:00 a.m. to
6:00 p.m., six days per week.
NMB Case No. 0102 4
Award No. 1
*n Fm,-
According to the Organization, "The character of work
involved here is that which has been historically,
traditionally, and customarily performed by the Carrier's
Maintenance of Way employees throughout the Carrier's
property." The organization alerted the Carrier regarding
the nature of the work assigned to outside contractors'
employees. The Organization also advised the Carrier that
the equipment used by the outside forces was either owned by
the Carrier or could have been leased by the Carrier to be
operated by the Claimants. The Claimants thereafter filed a
grievance protesting the use of outside contractor's forces
to perform this disputed construction work.
The Carrier defended the propriety of its assignment,
contending that the disputed work was not within the
exclusive jurisdiction of the bargaining unit represented by
the organization, and that similar projects had often been
outsourced to contractors in the past. The Carrier further
contended that the scope and nature of the projects at
Palos, Alabama did not mandate that the Carrier rent
equipment for use by bargaining unit employees, and that the
Carrier had properly assigned the track laying portion of
the work to the bargaining unit.
NMB Case
No. 0102
Award
No. 1
PIP FSz7
OPINION
The carrier cannot invade or erode work reserved
exclusively for the bargaining unit by assigning such work
to outside contractors. However, where disputed work has
not historically been performed exclusively by the
bargaining unit and, as the evidence in the instant case
persuasively established, has been performed on many
occasions by outside contractors, the potential to perform
the disputed work by assigning bargaining unit employees
using rental equipment does not mandate that the Carrier
elect to assign the disputed work to bargaining unit
employees, assuming they possess the requisite skill and
ability to perform the work.
The construction project at issue in the instant case
was not simply track repair, maintenance, or replacement.
Culverts had to be installed, and major site preparation
work undertaken prior to the installation of the track,
which was performed by the bargaining unit with the
assistance of non-Carrier forces to perform unloading and
movement of some supplies. There has been an agreement in
effect since 1974 that Maintenance of way employees could
perform grading work, but there is no agreement guaranteeing
that bargaining unit employees would perform all the
carrier's grading work. The scope cf the Palos, Alabama
NMB Case No. 0102 6
Award No. 1
PLB 6537
project, coupled with the absence of demonstrated
exclusivity of jurisdiction over such work by the bargaining
unit, insulates the Carrier' s., decision from reversal as
violating the collective bargaining agreement.
The Organization contends that the appropriate test
should not be exclusivity of jurisdiction, a very difficult
standard to demonstrate, but whether the work has
historically and traditionally been performed by bargaining
unit employees. This less stringent standard has not,
according to the record, been expressly adopted by these
parties to guarantee a right to bargaining unit employees to
perform all site preparation and construction work related
to new construction projects, especially when no bargaining
unit employee is on layoff. Neither is the less stringent
standard generally applied throughout the railroad industry.
The Board need not determine whether bargaining unit
employees could have competently performed the work, as the
Carrier has not raised competence of the bargaining unit as
a defense. Rather, the Board's evaluation of the propriety
of the assignment of many aspects of this project to nonbargaining unit forces employed by outside contractors rests
on the Board's determination that similar work has
historically been performed on the Carrier's property by
outside contractors on many occasions, thus precluding a
NMB Case No. 0102 7
Award No. 1
PLB 6537
finding of exclusivity of jurisdiction for the bargaining
unit over the disputed work in the instant case. The Third
Division of the NRAB has held.similarly in Cases No.
36280,36282, and 36283, among others. The holdings in these
cases, especially as they involve the same parties as the
instant case, afford valuable precedent for the finding
herein.
Grading of road bed and compaction of substrate have
not been routinely assigned to bargaining unit employees in
all cases. Moreover, the portion of the work involving
laying and installation of track, work traditionally within
the expertise of the bargaining unit, was assigned to
bargaining unit employees.
Consequently, for all these reasons and based on the
evidence submitted, the decision of the Carrier was correct
and proper. The instant claim is hereby denied.
By Ord of is
Law
Board 6537
4A
~~ -
Daniel F. Brdnt,
Neutral Member Chairman
William A. Osborn#, Roy y 'Ac! . Robinson,
Carrier Member Orga ization Member
Executed On:
J-31,-7,003
NMB Case No. 0102 8
Award No. 1
PLB 6537