BROTHERHOOD OF MAINTENANCE OF WAY EMPLOYEES

AND

CSX TRANSPORTATION, INC.




Statement of Claim:
In this case, it is the claim of the System Committee of the Brotherhood that the dismissal of Machine Operator C. A. Robinson for alleged safety and performance violations on April 29, 2002 was without just and sufficient cause. The relief sought is the reinstatement of C. A. Robinson with full back pay and seniority and with all other rights and benefits unimpaired. BackL7roend
On April 29, 2002, Claimant C. A. Robinson, a Machine Operator, was involved in the derailment of Ballast Regulator BR-9439, which he was operating. The accident resulted in minor injuries to Claimant as well as extensive damage to the machine, damage to the bridge structure, damage to the track structure, and delays and re-crews to trains. The incident occurred on the Lineville Subdivision, Milepost ANJ 960.6.
By letter dated May 1, 2002, Regional Engineer D. B. Spainhower charged Claimant Robinson with failure to secure auxiliary equipment on the ballast regulator for safe movement, in violation of CSXT On-Track Workers Safety Rule 712, MWI M-018 Part (6), along with violation of CSXT Operating Rules 501 (7 and 8).
























April 29, 2002, Claimant was operating the ballast regulator with a surfacing unit when it

derailed at a bridge and wound up sideways on the bridge. Investigation revealed that the

ballast regulator's west wing collided with the bridge and, in fact, fell off after a cable


                                          P L l3 lQ5 to 42) Wd o

broke. It was determined that the wing was in an extended position when it hit the bridge instead of resting in its cradle. Moreover, the lock-up device had not been used. Damage to the machinery was estimated to run between $30,000 and $35.000. (Tr. at 16).
Following a hearing that was held on May 16, 2002, Claimant was dismissed from the Carrier's service. The dismissal was based on the seriousness of the April 29 accident and other recent incidents in which Claimant put at risk not only his own safety, but the well-being and safety of co-workers and the general public. The Organization appealed the dismissal, and following failure by the parties to reach a mutually acceptable resolution, the dispute was submitted to this Board for adjudication. Findings
While Claimant testified that he had both of the ballast regulator's wings secured into their cradles, his testimony was not persuasive. This is because he had no logical explanation for how the accident occurred. Given the more credible testimony of Regional Engineer Track D. B. Spainhower, Regional Manager of Work Equipment J. S. Sorensen, and Production Foreman C. B. Curvin, it is clear that the mishap occurred because Claimant failed to secure his auxiliary equipment, i.e. the machinery's wings.
Claimant insisted that the wings were secured up into their cradles, but undisputedly, the west wing came out of the cradle and hit the bridge. It is unlikely that this would have occurred without the operator moving the controls. The Organization suggested that the cable might have been "in a bind" that "allowed slack in the cable" which, in turn, permitted the wing bucket to drop and hit the bridge. (Tr., at 44 and 48). But this argument is highly speculative and not supported by an reliable evidence in the Record.

3
                                          P I- ~) 1016 cD y Awd 140

Furthermore, Claimant testified that he had checked the cable on the ballast regulator and it was in good shape.
The Board is mindful that Claimant had 27 years of service with the Carrier. However, the Board is obligated to consider not only Claimant's seniority but also his record. That record reflects that shortly before the April 29 accident, Claimant received a 5-day suspension and then a 30-day suspension for safety-related incidents. Given these prior disciplines and the seriousness of the April 29 accident, the Carrier did not abuse its managerial discretion in concluding that Claimant's performance was no longer acceptable and that he posed a safety risk to himself, co-workers, and the general public. The Carrier has met its burden of proof in the instant matter and the Board, therefore, must respect its judgment. Award

    The claim is denied.


                          a

                (?J; Parker, Neutral Member


m. re
arrier M er Or lion Member
Dated: aG -Ll- o Dated: ~9,'~0~

4