BEFORE PUBLIC LAW BOARD NO. 6671
BROTHERHOOD OF MAINTENANCE OF WAY EMPLOYES
and
NATIONAL RAILROAD PASSENGER CORPORATION (AMTRAK)
Case No. 2
STATEMENT OF CLAIM:
1. Did Amtrak violate its May 19, 1976 Agreement with BMWE (as amended)
when it contracted out the welding work identified in its letter dated
September 12, 2003?
2. If the answer to Question No. 1 above is "Yes," what shall the remedy be?
Introduction
By letter dated September 12, 2003, the Carrier advised the Organization of its
intent, pursuant to the January 28, 1977, Equipment Rental Agreement, to lease a Holland
Mobil In-Track Welder, with Holland operators, to perform track welding over the course
of several months with an Amtrak rail gang replacing rail on the Harrisburg Line and
New York Division. The Organization objected to the contracting out of this work. After
a conference between the parties failed to result in a resolution of this dispute, the parties
subsequently agreed to submit their dispute to this Board.
Position of the Organization
v
The Organization contends that this is a straightforward contract-interpretation
case. The Organization argues that the Scope Rule does not permit the Carrier to contract
out welding work. The Organization emphasizes that the Rule plainly provides that track
maintenance work from four inches below the base of the tie and up may not be
contracted out without the written concurrence, except in case of emergency, of the
appropriate General Chairman. The Organization maintains that there can be no question
that welding rail joints in connection with installing new rail is track maintenance work
that is above the base of the ties, so such work may not be contracted out without the
General Chairman's written concurrence, except in emergencies. There was no
emergency asserted in connection with this case, and the General Chairman did not give
his written concurrence. The Organization therefore contends that Amtrak violated the
Scope Rule when it contracted with Holland Company to weld rail joints in connection
with the replacement of rail by Amtrak rail gangs, pursuant to Amtrak's September 12,
2003, letter.
The Organization argues that the Scope Rule's exceptions to the clear prohibitions
on contracting out plainly have no application to the instant dispute. Side Letter No. 2,
dated January 22,
1987,
specifically provides that the Scope Rule's exceptions will not
apply to work of the scope and magnitude historically performed by BMWE forces. The
Organization emphasizes that there can be no question that welders represented by
BMWE historically performed rail welding work, including welding rail joints in
connection with the replacement of rail by Amtrak's production rail gangs. The
19831987
force account reports establish that Amtrak consistently maintained a large force of
welders to perform rail joint welding work, including large-scale production rail
installation projects. These force account reports, together with the written statement of
Edward J. Romecki, who has worked as an Amtrak welder since
1978,
make it
2
transparently clear that Amtrak welders historically performed joint rail welding work,
including the high volume of welds associated with production work. The Organization
therefore argues that there can be no question that BMWE forces historically performed
rail welding work of the scope and magnitude involved in this case. Accordingly, the
exceptions set forth in the Scope Rule do not apply to this case.
The Organization goes on to contend that even if the Scope Rule's exceptions were
applicable to this case, the Carrier has not and cannot establish the factual predicate for
applying those exceptions. The Carrier cannot show that a "lack of essential equipment"
would have prevented timely completion of the work. The Organization asserts that
Amtrak may have preferred to use the Holland equipment, but there is no question that
use of Holland equipment was not essential. To the contrary, the evidence demonstrates
that Amtrak forces have welded rail joints since the inception of Amtrak, using the boutet
and thennite processes; there is no reason that Amtrak forces could not have welded all of
the rail joints involved in this dispute if Amtrak had assigned an adequate number of
welders to the task. The Organization points out that, in fact, it was not "essential" for
Amtrak to weld the rail joints in question at all. Consistent with the Federal Railroad
Administration Track Safety Standards, Amtrak could have initially bolted the rail ends
together, then assigned a small dedicated welding gang, or even local welding forces, to
weld the joints as time permitted. Alternatively, Amtrak could have assigned a larger
welding gang to weld the joints as the rail was installed, using the boutet or thermite
processes. The Organization then asserts that even if the Holland welding unit can be
3
deemed "essential," there was no "lack" of such equipment because these welding units
are readily available for lease without Holland operators.
The Organization then asserts that the Carrier does not dispute that rail joint
welding is an integral part of maintaining the track above the base, and it therefore is
covered by the Scope Rule. The Organization points to the Carrier's reliance on the 1977
Equipment Rental Agreement to support its contention that it may contract out such work,
despite the Scope Rule's mandatory command that such work "may not be contracted
out" without the General Chairman's written concurrence. The Carrier's reliance on the
Equipment Rental Agreement is misplaced for several reasons. This 1977 Rental
Agreement was negotiated in conjunction with the Scope Rule in the May 1976 collective
bargaining agreement, but it must be read in conjunction with the new Scope Rule
provisions that took effect in January 1987. The Organization points out that the earlier
Scope Rule was silent with respect to equipment, and the 1977 Rental Agreement filled
that gap. The current Scope Rule, however, clearly limits Amtrak's right to rely on
equipment exceptions as an excuse to contract out work. Under the current Scope Rule
and Side Letter No. 2, Amtrak may rely on an equipment exception only when the work is
of a scope and magnitude greater than that historically performed by BMWE forces, and
when a lack of essential equipment would prevent timely completion of the work. The
Organization maintains that the Carrier has not and cannot establish that either of these
conditions exists in connection with the disputed work. The Organization contends that,
pursuant to the principle that one contract provision should not be interpreted so as to
4
render another provision meaningless, it is evident that the 1977 Equipment Rental
Agreement applies only in instances where Amtrak first has met the equipment exception
tests in Side Letter No. 2 and in the Scope Rule. The 1977 Equipment Rental Agreement
has no application to this case.
The Organization additionally contends that the Carrier cannot establish the factual
predicate to apply the Equipment Rental Agreement, i.e., that it did not have the
equipment available to perform the work or that such equipment cannot be rented or
leased. Amtrak has not and cannot deny that it owns boutet and thermite welding
equipment that is sufficient to perform the welding work at issue. Moreover, Amtrak
employees have been assigned to use that equipment for joint elimination work day in and
day out from Amtrak's inception to the present. The Organization emphasizes that there
can be no question that the boutet and thermite processes continue to be safe and effective
welding processes.
The Organization then points out that another problem with the Carrier's reliance
on the 1977 Equipment Rental Agreement is that the Carrier has the burden of showing
that the flash butt welding equipment "cannot be leased without an operator." The
Organization asserts that the Carrier readily could have rented or leased additional
equipment without an operator, including Holland brand welders. The Organization
maintains that there is no probative value or credibility to the unsigned September 2003
letter that the Carrier holds out as evidence that Holland Company will not lease its
mobile in-track welders without Holland operators. The Organization asserts that this
5
letter is, at best, the shilling of a Holland Company sales representative who will say
whatever Amtrak wants.
The Organization argues that the utter lack of credibility of this Holland letter is
best demonstrated by the prior agreements that Amtrak made with the Organization to
settle disputes on the operation of Holland welding units in 1996 and 1997. The
Organization points out that in the 1996 settlement agreement, the Carrier agreed to train
its own welders to operate flash butt welding units, and Amtrak further stipulated that this
training "is being done in anticipation of Amtrak's desire to purchase or lease an intrack
fiashbutt unit and staff it with BMWE employees." Similarly, in the 1997 settlement
agreement, the Carrier once again agreed to train its employees at the Holland facility in
Chicago, and Amtrak once again stipulated that the training "is being done in anticipation
of Amtrak's desire to purchase or lease an intrack flashbutt unit and staff it with BMWE
employees." The Organization emphasizes that these settlement agreements are in direct
conflict with Amtrak's belated assertion that it cannot lease Holland welding units
without Holland employees. Amtrak would not have paid to train its employees to
operate Holland welding equipment if it could not purchase or lease that equipment for its
employees to operate. The record shows that Amtrak employees operated a leased
Holland welder during 1996. The Organization further points out that it has made
agreements with other carriers to train and assign employees to operate Holland welding
units. In fact, one of these other carriers recently notified the Organization that it planned
to lease Holland welding machines for the 2004 production season and assign its own
6
employees to work with each of the leased machines to perform the welding and grinding
work. The Organization asserts that the Carrier cannot rely on the 1977 Equipment
Rental Agreement because Amtrak cannot prove that Holland welding equipment cannot
be leased without an operator. Holland welding units are available for Amtrak's
employees to operate.
The Organization argues that Amtrak is wrong, as a matter of fact and principle, in
asserting that prior settlement of welding disputes has no precedential value in this case.
The Organization emphasizes that the 1996 and 1997 disputes were resolved when
Amtrak agreed to provide training to its employees on Holland welding equipment and to
allow its employees to displace on Holland welding equipment working on Amtrak's
Southern District after completing that training. The disputes that arose in 1995 and 2002
were resolved when Amtrak agreed to pay BMWE-represented welders between 75% and
100% of the hours Holland employees performed welding work on Amtrak. The
Organization contends that it is not reasonable to believe that Amtrak would have entered
into such agreements if it did not recognize that the work in question was reserved to
BMWE-represented welders under the Scope of the Agreement.
The Organization additionally argues that the most compelling reason why Amtrak
cannot rely on the 1977 Equipment Rental Agreement in this case is that the clear and
unambiguous language of the agreement specifies that any proposal to implement that
agreement shall be furnished to the General Chairman "for his approval before any
contractor's equipment or employes are pennitted to perform work coming within the
scope of the current M. W. Agreement." The Organization points out that the Equipment
Rental Agreement makes three separate references to obtaining the General Chairman's
approval before Scope-covered work may be contracted out. In this case, the General
Chainnan not only refused to grant his approval, but vigorously protested Amtrak's
proposed contracting out of the track welding work. The Organization asserts that
notwithstanding the multi-layered issues presented by the parties in this matter, this case
can and should be decided in the Organization's favor based on the hornbook principle
that where contract language is clear and unambiguous, it must be enforced as written.
Based on the clear and unambiguous meaning of the word "approval" in the Equipment
Rental Agreement, Amtrak simply cannot rely on that agreement to support its position in
this case.
The Organization goes on to maintain that yet another problem with the Carrier's
argument concerning the Equipment Rental Agreement is its reliance on a Third Division
Award that, according to Amtrak, recognizes that Amtrak was free to contract out Scopecovered work pursuant to the Equipment Rental Agreement if it did not have equipment
available to perform the work and it could not rent such equipment without an operator.
The Organization maintains that the fatal problem with this argument is that this Third
Division Award involved a dispute that arose in May 1986, prior to the 1987 amendments
to the Scope Rule and the cancellation of the Minimum Force Agreements. The
Organization acknowledges that in May 1986, Amtrak did have broad latitude to contract
out Scope-covered work under the Minimum Force Agreements, as long as it maintained
8
the required minimum number of BMWE-represented forces. The Organization contends
that all of this changed with the 1987 amendments to the Scope Rule and the abrogation
of the Minimum Force Agreements. The Third Division proceeding cited by the Carrier
is not a "like" case, and is irrelevant here, because it was controlled by contract terms that
were substantially different than the contract terms that control the instant case.
The Organization then contends that although it is not necessary to rely on
bargaining history in order to sustain its position, an analysis of the parties' bargaining
history lends further support to the Organization's position in this matter. The
Organization points out that the Scope Rule that controls this case was preceded by the
massive federal funding associated with the NECIP, which led to the May 1980 Minimum
Force Agreements. The Organization maintains that by 1987, it agreed to free the Carrier
from the Minimum Force Agreements in exchange for scope language that would
maintain the vitality of the bargaining unit by guaranteeing that scope-covered work could
not be contracted out except under the very limited circumstances specifically included in
the January 5, 1987, Scope Rule. This January 1987 Agreement relieved the Carrier from
having to maintain an artificial number of Maintenance of Way employees, while it
guaranteed the Organization that when the Carrier had the resources to perform
maintenance of way work, that work would be performed by the bargaining unit. The
Organization argues that if the Carrier can contract out fundamental track maintenance
work, such as rail welding, by the simple expedient of failing to acquire new equipment
as technology advanced, then the entire
quid pro quo
inherent in the January 1987
9
Agreement would be a sham. The Organization emphasizes that it did not surrender the
May 1980 Minimum Force Agreements for such a hollow promise.
With regard to the Carrier's contention that the Amtrak Reform and Accountability
Act (hereinafter "the Amtrak Reform Act") expressly gives Amtrak the right to contract
out work previously denied it under its agreements with the Organization, the
Organization asserts that the Carrier's arguments relies wholly on a bootstrapping of the
general Congressional findings contained in the Amtrak Reform Act's preamble to
amend, by implication, the plain language of Section 121 of the Act, and by further
implication, amend the parties' collective bargaining agreement sub silentio. Although
the Carrier's arguments are clever, the Organization maintains that they are specious at
best and dishonest at worst.
The Organization contends that, contrary to the Carrier's assertions, the Amtrak
Reform Act did not create such a fundamental rearrangement of the parties' collective
bargaining relationship. The Organization emphasizes that Section 121 simply
transferred a restriction on Amtrak's ability to subcontract scope work from the statute
books into each labor organization's collective bargaining agreements with Amtrak.
Moreover, Section 121 obligated both Amtrak and all the unions representing its
employees to bargain over that term's continued inclusion in the agreements no later than
five years after the Amtrak Reform Act's enactment. The Organization asserts that if
Amtrak truly believed that Section 121 amended the collective bargaining agreements to
remove all subcontracting provisions save the statutory language, then it would have said
10
so in the contemporaneous December 1997 letter from its Vice President- Labor
Relations to its employees' representatives. Instead, as the Carrier well knew, Section
121 merely began a process that obligated the parties to bargain over the continued
existence of the former statutory provisions in the collective bargaining agreements,
nothing more.
The Organization then maintains that the utter dishonesty of the Carrier's novel
position on the impact of the Amtrak Reform Act is demonstrated by the competing
House and Senate versions of the Act. The Organization emphasizes that the House
version of the Act proposed the outright repeal of all collectively bargained restrictions on
subcontracting. The purpose of the House version was the negotiation or arbitration of
entirely new provisions regarding "all issues" concerning subcontracting. The
Organization contends that the Carrier wants this Board to believe that this is what
Congress accomplished in enacting the Amtrak Reform Act, but this version never passed
the House and never was enacted into law. The competing bill that was introduced in the
Senate also initially contemplated a process that required bargaining and a negotiated or
arbitrated settlement of "all issues relating to subcontracting." Various amendments to
the Senate version, however, substantially changed the subcontracting provisions in
Section 121. The Organization emphasizes that the amended Senate version that
ultimately passed and became the Amtrak Reform Act applies, by its own terms, only to
subcontracting that "results in the layoff of an Amtrak employee," and not to "all issues
relating to contracting out by Amtrak of work normally performed by an employee in a
11
bargaining unit covered by a contract between Amtrak and a labor organization
representing Amtrak employees." The Organization maintains that the version of the Act
actually passed by Congress focuses only on the statutory restriction on subcontracting
that leads to the layoff of an Amtrak employees. The Organization contends that in the
Amtrak Reform Act, Congress did not seek to remove all restrictions on the Carrier's
ability to subcontract work.
The Organization then points out that the "no inference" provision in subsection
(d) of Section 121 actually supports the Organization's position. Contrary to the Carrier's
assertion, the Organization argues that this term means that nothing in the Amtrak Reform
Act should be read to affect the collectively bargained rights and restrictions on Amtrak's
ability to subcontract work. The Organization contends that those provisions remain
unchanged, and the parties were left to negotiate these provisions under the standard
Railway Labor Act process. The Amtrak Reform Act was a compromise bill that offered
Amtrak limited relief on the statutory restrictions on subcontracting. The Organization
argues that the Carrier's specious claims, seeking to breathe life into a bill that could not
pass the House or the Senate, should be summarily rejected by this Board.
The Organization goes on to assert that it is just plain frivolous for the Carrier to
argue that track welding work to eliminate rail joints is not reserved to BMWErepresented forces under the Scope Rule. The Organization emphasizes that Amtrak itself
has recognized that the work involved in this dispute is Scope-covered. Amtrak initiated
this dispute when it sought to contract out the work in question under the Equipment
12
Rental Agreement; this Agreement, by its own plain terms, applies only to work within
the Scope Rule. If the disputed work was not Scope-covered, then there would have been
no reason for Amtrak to attempt to implement the Equipment Rental Agreement.
Moreover, the work of welding rail ends to eliminate rail joints unquestionably is an
element of track maintenance, construction, and repair, and the Scope Rule clearly and
unambiguously reserves such work to BMWE forces.
The Organization emphasizes that the Carrier's attempt to distinguish between
flash butt welding and other methods for welding rail is a distinction without a difference
under the controlling contract language. The Organization asserts that the language of the
Scope Rule refers to "work," demonstrating that the collective bargaining agreement
preserves work, not the equipment or the method of performing it. BMWE forces have
performed the work at issue, fastening rail ends, and the employees have used a number
of methods, technology, and tools to perform this work over the years. The Organization
points out that fastening rail ends is an integral part of the rail construction, maintenance,
and repair work, and this historically has been performed on Amtrak by BMWE forces,
irrespective of the method used to perform that work. Such work unquestionably falls
within the Scope Rule of the Agreement.
The Organization ultimately contends that the instant claim should be sustained;
the track welding work should be returned to Track Department welders covered by the
May 16, 1976, Agreement, as amended; and the appropriate Track Subdepartment
welders should be compensated at their applicable rates of pay for an equal and
13
proportionate share of the hours expended by the contractor's forces in performing the
identified work. The Organization maintains that the instant claim should be paid for
100% of the hours worked because previous settlements in which pay was reduced to
75% of the hours worked obviously has not deterred the Carrier from repeatedly violating
the Agreement. The Organization contends that the instant matter therefore should be
remanded for a joint check of the Carrier's records to determine the number of hours
worked by the contractor's employees, and the appropriate claimants from the welder
seniority rosters.
Position of the Carrier
The Carrier initially contends that the January 28, 1977 Equipment Rental
Agreement is controlling here. The Carrier explains that the parties negotiated this
special agreement in recognition of the fact that certain work is covered by the Scope of
the Agreement and to expedite the handling of situations where Amtrak does not own
specific equipment necessary to perform maintenance of way work and that necessary
equipment cannot be leased without operators. If these two conditions are met, the
agreement provides for an automatic remedy- step-rating an equal number of employees
for the duration of the use of outside operators on the leased equipment on the project.
The Carrier argues that nothing in the contract restricts Amtrak's right to lease
necessary equipment, and Amtrak employees operate that equipment in the performance
of their assigned functions in many cases. The Equipment Rental Agreement was simply
to address those situations in which Amtrak seeks to rent equipment, but cannot obtain
14
equipment without outside operators. The Carrier further asserts that changes in the
Scope Rule have absolutely no impact upon the application of the Equipment Rental
Agreement. If the work is not Scope-covered, Amtrak is free to have the work performed
in whatever manner it deems appropriate and no remedy would be due to BMWE
employees. The Carrier asserts that in the absence of evidence that the parties specifically
agreed to eliminate or alter the application of the Equipment Rental Agreement in
connection with the 1987 Scope Rule revisions, that special agreement continues to exist
and applies to the instant dispute.
The Carrier maintains that in connection with the instant matter, it met the
requirements of the Equipment Rental Agreement. Amtrak provided ample notice to the
Organization that it does not own the track flash-butt welding equipment and intended to
lease this equipment from Holland Industries. The Carrier also provided evidence that the
equipment could not be leased without operators. The Carrier emphasizes that the
Organization never has argued in this case that the Carrier owns this equipment or that the
equipment could be leased without operators, and the Organization has asserted, in prior
cases before the Board, that the Carrier must satisfy these two conditions under the
Equipment Rental Agreement. The Carrier argues that it fulfilled its obligations under the
Equipment Rental Agreement, but the Organization now seeks to veto the rental of this
equipment, effectively abrogating the Equipment Rental Agreement.
The Carrier points out that although it has met all of the requirements for
application of the Equipment Rental Agreement, the Organization nevertheless contends
that this Agreement is not applicable here, arguing that Amtrak either should buy a
Holland Welder for BMWE employees to operate or should utilize one of the welding
processes perfonned by BMWE employees. The Carrier maintains that these arguments
do not constitute a basis on which to veto Amtrak's lease of the equipment, effectively
abrogating the provisions of the Equipment Rental Agreement. There is no provision that
prohibits Amtrak from utilizing different technology or methods of work performance
from that traditionally performed by BMWE members. In addition, there is no provision
that mandates that Amtrak use a less reliable and less efficient method of joining rail
lengths simply because the BMWE is capable of performing those methods. The Carrier
argues that it has a responsibility to utilize the most cost effective and reliable work
processes possible.
The Carrier goes on to argue that although it considered buying such equipment in
the late 1990s, and trained a number of BMWE employees on the flash-butt welding
process, it is not possible to purchase such equipment under Amtrak's current financial
constraints. Moreover, the limited need for such equipment would not justify the expense
of the equipment or the cost of employee training. The Carrier emphasizes that there is
no agreement provision mandating that Amtrak purchase equipment under these
circumstances.
The Carrier then asserts that the Organization cannot rely on the "approval"
provision of the Equipment Rental Agreement to support the contention that it has the
right to veto the lease of necessary equipment. Such a veto right would effectively
16
abrogate the entire agreement; this obviously was not the parties' intent. The Carrier
maintains that, consistent with the Organization's position in previous disputes, the
approval provision is simply to affinn that the Carrier has met the key requirements of the
agreement - that Amtrak does not own the necessary piece of equipment and that the
needed equipment cannot be leased without operators. If those requirements are not met,
the Organization need not approve the process. The Carrier maintains, however, that if
these requirements are met, the application of the agreement cannot be ignored or rejected
simply by withholding approval.
The Carrier argues that the lease of the Holland Welder is the type of project that
the Equipment Rental Agreement was specifically designed to address. There is limited
need for the equipment, Amtrak does not own it, and it cannot be leased without
operators. Because the agreement's requirements have been met, the Organization cannot
simply reject its application. As for the Organization's criticism of the document
provided by Amtrak to show that Holland will not lease their In-Track Welding Unit
without their operator, the Carrier argues that the Organization merely made assertions
about the document. If the Organization seeks to take an affirmative defense, then the
Organization is obligated to demonstrate that Holland Industries or another vendor will,
in fact, lease the equipment without operators. Because no such evidence has been
presented, the Carrier maintains that the fact remains that the equipment cannot be leased
without operators.
17
The Carrier goes on to assert that if the Board determines that Amtrak cannot lease
the equipment in question without BMWE approval, there is nothing in the Scope Rule,
as amended, that prohibits contracting out the work in dispute. The Carrier argues that in
December 1997, its labor agreements were amended by the Amtrak Reform and
Accountability Act of 1997 (hereinafter "the Amtrak Reform Act"), which provides that
Amtrak may not contract out work normally performed by bargaining unit employees if
the contracting out results in the layoff of an employee in the bargaining unit. The Act
further specifies that this amendment is without prejudice to Amtrak's power to contract
out work not resulting in the layoff of Amtrak employees. The Carrier maintains that this
amendment was intended to afford Amtrak greater flexibility in the use of outside forces
so that the Carrier could become more efficient and productive, thereby reducing the need
for federal subsidies. The Carrier argues that the language inserted into the contract was
not an addition to existing restrictions, but rather an overriding provision, consistent with
Congress' intent to improve Amtrak's financial and operating performance.
The Carrier argues that the Amtrak Reform Act was intended to ensure that
Amtrak make the most efficient use of its financial resources by eliminating restrictions
on the use of the most cost-effective means of accomplishing work, including broader use
of outside forces. The Carrier asserts that the only restriction that was preserved was that
Amtrak could not contract out work that resulted in the furlough of bargaining unit
employees. Moreover, by placing this provision in the contract, the parties had the ability
to bargain over the elimination of that remaining restriction. The Carrier points out that in
18
printing the agreement following the contract settlement and the Amtrak Reform Act, the
statutory amendment was simply inserted in the contract. The Carrier argues that this
does not mean that the parties agreed that this change simply was an addition to existing
provisions. In fact, the parties agreed that the reprint was a synthesis, intended as a guide,
and that the terms of the actual contract provisions would govern the resolution of
disputes. The Carrier asserts that the synthesis cannot now be used to support the
Organization's position that the prior restrictions continue to apply. The Carrier therefore
contends that the contracting out of the work at issue did not violate the Agreement, as
amended by the Amtrak Reform Act, as no employees were furloughed as a result of the
contracting out of this work.
The Carrier then argues that even if this Board rejects the fact that the previous
Scope Rule restrictions were eliminated by the Amtrak Reform Act, the Organization has
failed to establish that the disputed work, flash butt welding, is work reserved to the craft
under the contract. The Carrier submits that even if the Equipment Rental Agreement did
not exist, and the previous scope rule restrictions remained in effect, Amtrak would not be
prohibited from contracting out the work in question. The Carrier points out that the
Organization will argue that the disputed work is track maintenance, construction, or
repair that cannot be contracted out without the General Chairman's written concurrence,
but Amtrak maintains that this argument ignores the fact that this provision can restrict
only the contracting out of work originally reserved to the craft under the Scope Rule.
The Carrier points out that the Agreement's Work Classification Rule reserves only two
19
types of welding to the craft. Although Amtrak has trained and utilized employees to
perform other welding methods, the contract language does not reserve all methods of
welding to the craft. Where, as here, there is no broadening contractual language, only
those methods listed are reserved to the craft.
The Carrier contends that flash butt welding is not reserved to the craft under the
scope and work classification provisions of the Agreement. For this reason, as well as the
fact that Amtrak employees never have performed flash butt welding, Amtrak is free to
contract out the performance of this work. The Carrier points out that even if the Board
determines that flash butt welding was work reserved to the BMWE, it nevertheless is
true that because of the lack of essential equipment, a specific exception set forth in the
Scope Rule, Amtrak can contract out the work without BMWE concurrence. The Carrier
argues that because it does not own equipment capable of performing flash butt welding,
there is no prohibition on contracting out the work.
The Carrier then addresses the Organization's contention that prior "agreements"
resolving similar requests to lease Holland Welding equipment are somehow
determinative of this dispute. The Carrier maintains, however, that such agreements do
not amend the collective bargaining agreement or establish precedent for all future
handling of equipment rental issues. The Carrier readily admits that the April 1997
agreements expressly provide for the training of employees on the flash butt welding
process, but the Carrier emphasizes that the agreements clearly indicate that the training
was being done "in anticipation of Amtrak's desire to purchase or lease an intrack
20
flashbutt unit." The Carrier contends that its funding constraints have precluded the
purchase or long-term or lease of such equipment. More importantly, because of the
impact that these financial constraints have had upon capital improvement projects, the
Carrier argues that the need for such equipment has been virtually non-existent in the
years since these 1997 agreements.
The Carrier maintains that an agreement to train employees on a new welding
process does not automatically place the work under the Scope Rule, nor does it mandate
that Amtrak repeat that training exercise on the limited occasions when the lease of the
equipment is necessary. Moreover, although Amtrak trained a number of employees on
the process more than six years ago, the fact remains that Amtrak does not own flash butt
welding equipment; the trained employees therefore never have been able to utilize those
skills, much less develop proficiency in performance of the process. The Carrier further
points out that even if these employees have been able to retain those skills for all of these
years, the technology has changed substantially over the past several years, making the
skills learned by Amtrak employees in 1997 virtually obsolete. As for any payments
made to BMWE employees in connection with certain rentals of Holland Welding
Equipment, the Carrier argues that payments by subordinate officials do not establish
precedent in contract interpretations.
The Carrier ultimately contends that the instant claim should be denied in its
entirety.
21
The parties being unable to resolve their dispute, this matter came before this
Board.
Findings
The instant matter is one of three separate, but related, claims that the Organization
has pursued over the Carrier's decisions to contract out certain work to outside
contractors. This case specifically focuses on rail welding work. As is true of any
contract-interpretation matter, the analysis of the parties' respective positions must be
based upon the relevant language of the parties' agreements. Here, the Scope Rule in the
parties' collective bargaining agreement is the starting point, but other agreements and
statutes also come into play. The Carrier has pointed to both the Amtrak Reform Act and
the so-called exclusivity test, focusing on their respective impacts upon the proper
interpretation of the collective bargaining agreement's provisions relating to
subcontracting. The Organization has emphasized that Side Letter No. 2 must be read
along with the contractual Scope Rule for a full understanding of the collective
bargaining agreement's restrictions on contracting out and the exceptions thereto. The
logical first step in the Board's analysis of the proper interpretation and application of the
contractual Scope Rule is to determine whether and how the Amtrak Reform Act has
modified the Scope Rule.
The Carrier's position in this case rests heavily upon its assertion that the Amtrak
Reform Act eliminated the bargained-for restrictions on contracting out that appear in the
parties' collective bargaining agreement. The Carrier argues that the single restriction on
22
subcontracting that appears in the Amtrak Reform Act - prohibiting Amtrak from
contracting out work normally performed by bargaining unit employees if the contracting
out results in the layoff of a bargaining unit employee - serves to override the express
restrictions on contracting out that appear in the parties' collective bargaining agreement.
The Carrier maintains that the contracting out of the rail welding work at issue did not
violate the parties' collective bargaining agreement because it did not result in any layoffs
of bargaining unit employees.
Collective bargaining, of course, helps to form the very foundation of the
relationship between management and labor, and agreed-upon contractual provisions
cannot be lightly tossed aside. The Carrier's position here, however, requires a finding
that the Amtrak Reform Act operates to supercede bargained-for provisions relating to the
contracting out of work, replacing any and all mutually agreed prohibitions on contracting
out - in all of the collective bargaining agreements between Amtrak and the labor
organizations that represent its employees - with the single restriction that such
contracting out may not result in the layoff of bargaining unit employees. The Carrier's
suggestion that Congress intended to work such an extreme change upon these collective
bargaining agreements must, to be accepted, be supported by clear and credible evidence.
This Board, however, finds no support in the record for the Carrier's assertion
about the impact of the Amtrak Reform Act on the contractual restrictions on the
contracting out of bargaining unit work. If the Amtrak Reform Act actually was intended
to override specific provisions of the parties' collective bargaining agreement, then this
23
would unequivocally be stated within the Act itself. Nothing in the language of the
Reform Act itself, or in the cited legislative history, suggests that the Act was intended to
override any bargained-for provision with any of the collective bargaining agreements
between Amtrak and the labor organizations that represent its employees. In fact,
Section 121 of the Reform Act specifically states that any Amtrak collective bargaining
agreement is deemed amended "to include" the prohibition against contracting out work if
it results in bargaining unit layoffs, thereby demonstrating that this limitation is to be
added to whatever other limitations on contracting out already appear in the Amtrak labor
agreements. Moreover, Section 121 's general emphasis on party negotiations, which
underlines the importance of collective bargaining, is at odds with the Carrier's assertion
that the Reform Act should be read as superceding the contractual limitations on the
contracting out of work.
Based on its express language, we find that the Amtrak Reform Act cannot be
taken as overriding any part of the Amtrak collective bargaining agreements. Instead, this
Board finds that the language of Section 121 of the Act must be read and understood as
adding to, rather than superceding, the existing contractual restrictions on the contracting
out of work. Applying this to the instant dispute, it must be noted there is no allegation,
and no evidence in the record, that the contracting out of the rail welding work at issue
resulted in any bargaining unit layoffs. The Amtrak Reform Act's single limitation on the
contracting out of work therefore does not apply to this dispute, making the Reform Act
and its impact on the parties' collective bargaining agreement irrelevant to the resolution
24
of this matter. Accordingly, this Board shall determine whether the contracting out of the
rail welding work at issue constituted a contract violation based upon the Scope Rule
language as written in the parties' collective bargaining agreement, without any further
specific consideration of the provisions of the Amtrak Reform Act.
There can be no serious question that the welding of rail joints is covered by the
contractual Scope Rule. The Scope Rule expressly includes "track inspection,
maintenance, construction or repair work from four (4) inches below the base of the tie
up, and undercutting." Rail joint welding is an essential component of such work, and the
evidentiary record conclusively demonstrates that the Carrier's Track Department welders
historically have performed welding work of the scope and magnitude of the particular
work at issue here, involving large-scale rail installation and an associated high volume of
welds. The record shows that the Carrier's BMWE forces have performed this type of
work using a number of methods, technologies, and tools, but particularly the boutet and
thermite processes.
In notifying the Organization that it planned to contract out the welding work at
issue, the Carrier indicated that its decision was pursuant to the terms of the parties' 1977
Equipment Rental Agreement. The relevant portion of this special agreement essentially
addresses one particular situation: when Amtrak does not have equipment available to
perform maintenance of way work and that equipment cannot be rented or leased without
an operator. Although the Carrier owns the equipment necessary to complete the welding
work at issue if the boutet and/or thermite processes are used, the Carrier opted to have
25
this work completed using the flash-butt welding process, instead. The Carrier does not
own flash-butt welding equipment, and it has asserted that such equipment cannot be
leased without operators.
The Carrier certainly has the right to use different technologies to complete its
various building and maintenance tasks. In fact, it has an obligation to perform such
work in an efficient and cost-effective manner. If newer methods and technologies allow
certain work to be completed more quickly and/or more cheaply, without harming the
quality of the finished work, then the Carrier must have the right to utilize such newer
technologies as part of its on-going operations. If the Carrier chooses to adopt new
methods and technologies in connection with Scope-covered work, however, then it must
make it possible for its own employees to perform that work in accordance with the Scope
Rule. If the simple adoption of a new method or technology to perform work, requiring
the use of equipment that the Carrier does not already own, was sufficient to allow the
Carrier to contract out Scope-covered work, then the Scope Rule's protections would be
completely undercut. If the Scope Rule is to have any meaning, and it must, then the
Carrier must be obliged to have its own employees utilize such new methods or
technologies to perform Scope-covered work, with the only exceptions being those
expressly set forth in the Scope Rule.
The Carrier has pointed to one Scope Rule exception, "lack of essential
equipment," as justifying its decision to contract out the work at issue. Again, there is no
question that the Carrier does not own flash-butt welding equipment, but this does not
26
necessarily mean that the Carrier can avoid the Scope Rule and contract out covered work
by choosing to have certain work done by a new method, involving equipment that it does
not own, when its own employees regularly have performed the work using other
methods, with equipment owned by the Carrier.
In fact, the express language of the Scope Rule and Side Letter No. 2 demonstrates
the parties' intent to limit the Carrier's ability to contract out Scope-covered work under
the "lack of essential equipment" exception. As specified in Side Letter No. 2, the
exceptions set forth in Paragraph A.Lb. of the Scope Rule, including the "lack of
essential equipment" exception, do not apply to work "of the scope and magnitude
historically performed by members represented by the BMWE." This language is critical
to a proper understanding of the application of the Scope Rule to the instant dispute.
Quite simply, the Carrier may not rely on the "lack of essential equipment" exception to
support the contracting out of covered work of the scope and magnitude historically
performed by its BMWE forces. The evidentiary record clearly demonstrates that the
welding work at issue definitely is of the scope and magnitude historically performed by
Amtrak's BMWE forces, so we find that the Carrier cannot rely on the equipment
exception as a reason to contract out this work.
As stated, if the Carrier chooses to utilize a new method to perform Scope-covered
work, then it must give its own employees the opportunity to perform the work under the
new method, in accordance with the terms of the Scope Rule. Moreover, if the Carrier's
employees can perform the work in question, and meet the applicable quantity and quality
27
requirements, by using existing methods and equipment, then the Carrier must show some
justification for adopting a new method that results in the contracting out of the work due
to a "lack of essential equipment." If new equipment is "essential" only to the new
method, but the work in question can be properly, safely, and timely completed using
existing methods and equipment, then the Carrier cannot truly establish a "lack of
essential equipment," as that phrase is used in the Scope Rule.
These considerations similarly apply to the question of whether the Equipment
Rental Agreement justifies the contracting out of the welding work at issue, despite the
fact that such work is covered by the Scope Rule. The Equipment Rental Agreement's
authorization of contracting out of maintenance of way work, when the Carrier "does not
have equipment available to perform [the] work and said equipment cannot be rented or
leased without an operator," must be read in conjunction with the current Scope Rule. To
satisfy the Scope Rule's purpose of preserving bargaining unit work, and Side Letter No.
2's limitation on the use of the equipment exception, the Carrier has the burden of
showing why existing methods and equipment cannot be used to complete the work, and
why it therefore is necessary to adopt a new method that involves the contracting out of
work under the Equipment Rental Agreement. The fact is that in this case, the Carrier
certainly does have "equipment available to perform" the welding work at issue, albeit by
the boutet and thermite processes, rather than the flash-butt welding process. The record
in this matter, however, does not contain any evidence that shows that the work at issue
cannot be appropriately, safely, and timely completed by using the boutet and/or thermite
28
processes, nor is there any evidence that the flash-butt process is, in some way, materially
superior to these other methods. The Carrier therefore has not met the first requirement
of the Equipment Rental Agreement.
The Carrier also has failed to meet the second requirement of the Equipment
Rental Agreement, which is showing that the "equipment cannot be rented or leased
without an operator." Although the Carrier submitted an unsigned letter stating that
Holland mobile in-track welders cannot be leased without Holland operators, this
document's credibility does not hold up under scrutiny, particularly in light of the fact
that the Carrier previously trained its own employees to operate such equipment, and the
fact that another carrier notified the Organization that it planned to lease Holland welding
machines and use its own employees to perform welding work with these leased
machines. In light of this evidence, we find that the Carrier has failed to demonstrate that
the Equipment Rental Agreement properly applies to the situation at issue. Accordingly,
this Board finds that the Equipment Rental Agreement does not serve to justify the
Carrier's decision to contract out the welding work at issue.
This Board finds that the Scope Rule governs the question of whether the welding
work at issue may be contracted out. In light of the evidence in the record, the Equipment
Rental Agreement does not apply to this situation and does not justify the Carrier's
decision to contract out the welding work. Given the established fact that the welding
work at issue could have been properly, safely, and timely performed by Amtrak
employees using existing methods and existing Amtrak equipment, this Board finds that
29
the Scope Rule does not allow for the contracting out of this covered work under the
circumstances at issue here. In accordance with the terms and intent of the Scope Rule, if
the Carrier wishes to adopt the flash-butt welding method, then it must, as it has done
before, train its employees in this welding method, and then either buy or lease the
necessary equipment. This Board therefore finds that the instant claim must be sustained.
Award
The claim is sustained. Amtrak violated its May 19, 1976, Agreement with the
BMWE (as amended) when it subcontracted out the welding work identified in its letter
dated September 12, 2003. The track welding work should be returned to the Track
Department welders represented by the BMWE and covered by the May 16, 1976,
Agreement (as amended) and the Carrier must compensate the appropriate track sub
department welders at their applicable rates of pay for an equal proportionate share of
man hours expended by the contractor's forces in performing the work identified in
Amtrak's letter dated September 12, 2003. This case is remanded for a joint check of the
Carrier's records to determine the number of man hours worked by the Holland
employees and the appropriat t the B WE welder seniority rosters.
ET R ME E~
Neutral Membe
OR IZATION MEMBER CARRIER MEMBER
DATED:
Ile
DATED: S
30
Carrier Member's Dissent - Public Law Board No. 6671. Award No. 2 and 3
The Majority determined in these cases that the Amtrak Reform and Accountability Act
did not alter the Amtrak - BMWE Northeast Corridor Scope Rule and proceeded to
decide that Amtrak has equipment that could do the work and therefore, we cannot lease
other equipment without BMWE approval. The Majority not only exceeded their
authority, by interpreting the Amtrak Reform and Accountability Act, and did so
incorrectly, but it also effectively eliminated the Equipment Rental Agreement.
First, the Amtrak Reform and Accountability Act of
1997
amended Amtrak's collective
bargaining agreements. While the parties differed in their view of that amendment, the
Board exceeded its' authority by interpreting the Act.
Relative to the merits of this case, the
1977
Equipment Rental Agreement was negotiated
before the Minimum Force Agreements, continued through their existence and survived
their replacement. This was a special agreement and an exception to the scope rule and
contracting procedures. The reason for the tenure of that agreement is because it is not
affected by the scope rule or any changes to the scope rule.
The simple fact is that Amtrak has the unfettered right to lease whatever equipment it
wants or needs to meet operational requirements. The Equipment Rental Agreement was
negotiated in recognition that certain work is scope covered and when Amtrak elects to
lease equipment, and that equipment cannot be obtained without outside operators, there
is an automatic remedy - payment of the higher rate to an equal number of employees.
The decision in these cases effectively abrogates the Equipment Rental Agreement
and throws everything under the basic scope rule. If that had been the intent of the
parties when negotiating the 1987 scope rule changes, they would have eliminated the
Equipment Rental Agreement at that time. That clearly was not done, but the majority
here elected to take that action for the parties, which renders the Awards palpably
erroneous and in violation of the Agreement establishing the Board and the Railway
Labor Act. The Board is simply not authorized to re-write the terns of the agreement.
Carrier Member's Dissent - Public Law Board No. 6671 . Award No. 2 and 3 (continued
Further, without authority, the majority has in essence said that as long as there is a tool
on the property or an alternate method that could be used to reach the end goal, Amtrak
cannot utilize other technology or equipment. The Majority has determined that Amtrak
is obligated to buy equipment while no other railroad in the nation has such an obligation.
As the BMWE pointed out, many freight roads utilize leased equipment, including the
Holland Welder and the Slot Train. While it may be that the BMWE is saying that trackwelding and scrap pick up is not reserved to the BMWE on the freight,railroads, in the
absence of such an admission, there is no conceivable basis on which to decide that those
railroads are able to lease such equipment while Amtrak cannot. The decision in these
cases is utterly absurd, particularly in light of the fact that Amtrak has a specific
agreement dealing with the lease of equipment with outside operators that defines the
remedy for that action. By implying that the BMWE has veto rights any time there is a
tool that can be used for the purpose, or an alternate way of doing the work, the Majority
has gone beyond preserving the BMWE's right to work and granted them the right to
determine how work will be performed.
These awards are not based on the language of the agreement and in fact change the
agreement by granting BMWE veto rights over equipment rental with operators. The
parties had already negotiated and reached a special agreement - the Equipment Rental
Agreement - on the applicable conditions for equipment rental issues requiring outside
operators and, the proper remedy in those situations. While the majority may have
viewed Amtrak's BMWE scope rule as different from those
in effect on
freight railroads,
that does not alter or undermine the application of the Equipment Rental Agreement.
While the freight roads may have to negotiate special agreements to permit utilization of
leased equipment with outside operators on their property, Amtrak already has an
agreement in place for that type of situation. This award goes against the basic tenet of
contract interpretation by ruling that the general rule supersedes the special rule.
_2-
Carrier Member's Dissent -Public Law Board No. 6671 . Award No. 2 and 3 (continued)
The facts remain in these cases that Amtrak met the requirements of the Equipment
Rental Agreement and there was simply no basis on which to conclude that this
ageement did not apply. The employees did not prove that Amtrak has either flash butt
welding equipment or slot train equipment available. While in the latter case, they
pointed to the Jimbo Crane, which is similar to the Slot Train equipment, we stated in
rebuttal that the one and only limbo Crane Amtrak owns was already assigned to material
distribution on the Harrisburg Line Improvement project and was not available.
Relative to the ability to lease without operators, it was inappropriate at best for the
majority to rule that Amtrak did not establish in these cases that the equipment could not
be leased without operators, particularly when that issue was never contested during the
conference discussions over the lease of the equipment. In neither case did the
employees ever contend at the initial meeting that the equipment in question could be
leased without operators.
More importantly, the employees failed to prove that the equipment could be leased
without operators. Prior Amtrak agreements involving the Holland Welder simply
involved training on the operation of that equipment. Amtrak employees were not
actually operating the Holland Welder. Similarly, the CSX Agreement provided by the
BMWE clearly states that BMWE employees will do set up and grinding of finished
welds.
That is not operating the equipment. The Board's ruling apparently is based
solely on the organization's characterization
of
the "intent"
of
two other ageements with
freight railroads, neither of which states that BMWE employees will "operate" the
Holland Welder following training. Both the 1HB and GTW agreements simply indicate
that the employees trained will "work with" the Holland Welder. There is no
commitment that they would actually operate that equipment.
-3-
Carrier Member's Dissent - Public Law Board No. 6671. Award No. 2 and 3 (continued)
As stated in Amtrak's submissions and presentation, if Holland or any other company
would lease their flash butt welding equipment without their own operators, or if
Georgetown Rail Equipment or any other vendor would lease a Slot Train without an
operator, the BMWE would have had correspondence from the company attesting to that
fact. At best, the Board should have viewed that issue as involving a dispute in facts and
remanded the matter to the parties to determine if the equipment can be leased without
operators.
Relative to the remedy in these cases, the Board has again exceeded its authority by
directing that the work be returned to the BMWE. The Board does not have the power to
direct Amtrak to, in essence, cancel a commercial contract. Similarly, it is well
established that arbitration boards such as this do not have the authority to direct the
establishment of positions. At most, the Board has the authority to find monetary
damages for a contract violation.
The awards in these cases are palpably erroneous. The Equipment Rental Agreement
applied to these disputes and the majority improperly determined that the general rule
superseded the special agreement. The decisions here create rather than resolve disputes.
R. F. Palmer
Carrier Member
Labor Member's Response
Corrected Cony
To Carrier Member's Dissent
To
Awards 2 And 3 Of Public Law Board No. 6671
With the exception of his newfound position concerning the Amtrak Reform and
Accountability Act, the Carrier Member's Dissent is largely an attempt to reargue points that were
fully aired in the written briefs of the parties, oral argument and in an extensive Executive Session.
As the Neutral Member so carefully explained in his well-reasoned award (as well as in Executive
Session), these arguments simply have no merit under standard principles for interpreting contract
language and evaluating evidence. I urge the Carrier Member to simply accept the plain meaning
of the Scope Rule and to abide by its terms rather than engendering future disputes and the
attendant monetary liability that will almost certainly redound to Amtrak if it continues to violate
the Scope.
While I hesitate to be pejorative, there is no way to describe the Carrier Member's position
on the Amtrak Reform and Accountability Act other than to label it as frivolous. I agree that as
a general matter, Section 3 tribunals do not have the authority to interpret statutes. However, in
this case, the Amtrak Reform and Accountability Act was made a part of and physically inserted
into the collective bargaining agreement. In other words, it became a contract term and was
therefore clearly subject to interpretation and application by the Board pursuant to Section 3
Second of the Railway Labor Act and the terms of the Agreement establishing Public Law Board
No. 6671. Moreover, it was Amtrak, and not BMWE, who raised the Amtrak Reform Act in
defense of its position in this case. Hence, it is more than a little disingenuous for the Carrier
Member to complain that the Board exceeded its jurisdiction by interpreting the language of the
Amtrak Reform Act when it was Amtrak itself that raised the Reform Act as a defense in this
case.
The Carrier Member's continuing attempt to rely on the Equipment Rental Agreement
seems to be nothing more than a stubborn refusal to recognize the obvious. As the Organization
painstakingly documented in its submission, Amtrak's attempt to rely on the Equipment Rental
Agreement in Case Nos. 2 and 3 was blatantly wrong for three reasons. First, that agreement,
which was negotiated in 1977 in connection with the Scope Rule of the May 19, 1976 collective
bargaining agreement, must be read in conjunction with the new Scope Rule provisions which
were negotiated effective January 5, 1987. The Scope Rule of the May 19, 1976 Agreement was
silent with respect to equipment and the 1977 Equipment Rental Agreement filled that gap.
However, Paragraph A, l.b. of the Scope Rule in the January, 5, 1987 Agreement very clearly limits
Amtrak's right to rely on equipment exceptions as an excuse to contract out work. In fact,
pursuant to Side Letter No. 2 dated January 22, 1987, Amtrak may not rely on equipment
exceptions at all if the work in question is work of the scope and magnitude historically performed
by BMWE members, as was the case in Award Nos. 2 and 3. BMWE submits that the failure to
read the 1977 Equipment Rental Agreement in the context of Paragraph A.l.b. of the January 5,
1987 Scope Rule and Side Letter No. 2 would, in essence, abrogate the entire meaning of these
latter two provisions. It is axiomatic that one contract provision should not be interpreted in a
manner that destroys another. When this principle is applied to the contract language in the cases
decided by Award Nos. 2 and 3, it is clear that the 1977 Equipment Rental Agreement applies only
in instances where Amtrak has first met the equipment exception tests in Side Letter No. 2 and
Paragraph A.Lb. That is, before Amtrak may resort to the Equipment Rental Agreement, it must
first show: (1) the work involved is of a scope and magnitude greater than that historically
performed by BMWE-represented employes; and (2) Amtrak's lack of essential equipment to
perform the work within required time limits. In these cases, Amtrak did not and could not meet
those tests. Consequently, the 1977 Equipment Rental Agreement has no application in the cases
decided by Award Nos. 2 and 3.
Second, even if Amtrak could show that the 1977 Equipment Rental Agreement applied
in Award Nos. 2 and 3 (which it does not), Amtrak would next have to show that, "... Amtrak,
Northeast Corridor does not have equipment available ***" to perform the work in question. In
this case, Amtrak never even asserted, much less proved, that it did not have equipment that was
sufficient to perform the disputed welding and material handling work. Indeed, Amtrak could not
credibly make such an assertion because the records showed that Amtrak employes had been
performing such work with Amtrak's own equipment since the inception of Amtrak.
Finally, the third and most compelling reason why Amtrak could not rely on the 1977
Equipment Rental Agreement in these cases is that the clear and unambiguous language of the
agreement provides that any proposal to implement that agreement shall be furnished to the
General Chairman, "...
for his approval before any contractor's equipment or employes are
permitted to perform work coming within the scope of the current M.W. Agreement."
(emphasis in bold added). In this case, General Chairman Dodd not only refused to grant his
approval, but vigorously protested, in writing, when Amtrak proposed to contract out the work
involved in Award Nos. 2 and 3. Consequently, Amtrak could not validly rely on the 1977
Equipment Rental Agreement in these cases.
The Carrier Member is also stubbornly refusing to recognize reality when he continues to
assert that the Organization failed to prove that the necessary equipment could be leased without
operators. The record clearly showed that Holland Welders are leased for operation by BMWErepresented employes on the IHB, GTW and CSXT railroads. However, what makes the Carrier
Member's assertion truly astonishing is that subsequent to the rendering of Award Nos. 2 and 3,
Amtrak made agreements with BMWE to implement those awards and those agreements clearly
show that Amtrak was able to obtain Holland Welders and the GREX Slot Machine for its
BMWE-represented employes to operate. In a Letter of Agreement dated June 21, 2004 to
implement Award No. 2, the parties agreed as follows with respect to Holland Welding Machines:
-2-
"This is in reference to our June 10, 2004, meeting and subsequent discussions
regarding the above subject and implementation of Award No. 2 of Public Law
Board No. 6671.
The parties agreed to permit the utilization of the Holland Flash Butt Welding
Units currently working on the property under the following conditions:
1. Amtrak will obtain the Holland Flash Butt Welding Units (the
Holland Welder) to be operated by employees coming under the
scope of the Amtrak - BMWE Northeast Corridor Agreement,
to perform field welds on the Keystone Corridor Improvement
Project, support the work of the TLS Unit and, to perform field
welds on the New England Division.
2. The Holland Company will supply supervision to direct the
operation of the Holland Welder and to perform maintenance and
repair of the equipment.
3. The Holland Company will train BMWE employees to operate the
Holland Welder. Holland Company may supply those employees
necessary to train BMWE members, but such. employees will not
operate the Holland Welder except incidentally when necessary for
the instruction of BMWE employees.
All operation of the Holland
Welder will be performed either by a BMWE member being
trained under the direction of a Holland employee or, by a
quailed BMWE employee.
8. Following the FY 04 production season, Amtrak will again post
three (3) training positions, under the 1977 MW Training
Agreement, for each Holland Welder anticipated to be used in the
next production season. Employees who commenced training or
were awarded positions under paragraph 4 above shall have first
rights in seniority order to these training opportunities on their
respective districts. Successful applicants for these positions will
attend formal training at Holland Facilities in Chicago, Illinois.
Upon successful completion of that training, the employees will
be assigned to the Holland Welder for the FY 05 production
season, with preference in seniority order to available positions.
Employees who are not assigned under this paragraph will be
-3-
subject to assignment under paragraphs 4 and 5 above." (Emphasis
in bold added)
Similarly, in another Letter of Agreement dated June 21, 2004 to implement Award No. 3,
the parties agreed as follows with respect to the GREX Slot Machine:
"This is in reference to our June 10, 2004, meeting and subsequent discussions
regarding the above subject and implementation of Award No. 3 of Public Law
Board No. 6671.
The parties agreed to permit the utilization of the GREX Slot Machines currently
working on the property under the following conditions:
1.
Amtrak will obtain the GREX Slot Machines (the Slot
Machines) to be operated by employees coming under the scope
of the Amtrak - BMWE Northeast Corridor Agreement,
to
perform material distribution and pick-up on the Keystone Corridor
Improvement Project, as well as other locations on the MidAtlantic,
New York and New England Divisions.
2. The GREX Company will supply supervision to direct the operation
of the Slot Machines and to perform maintenance and repair of the
equipment.
3. The GREX Company will train BMWE employees to operate the
Slot Machines. The GREX Company may supply those employees
necessary to train BMWE members, but such employees will not
operate the Slot Machine except incidentally when necessary for the
instruction of BMWE employees.
All operation of the Slot
Machine will be performed either by a BMWE member being
trained under the Direction of a GREX employee or, by a
qualified BMWE employee.
8.
Future rental of Slot Machine equipment shall include
advertisement of an operator position for that equipment.
Employees already qualified on such equipment shall have first
rights in seniority order to these positions on their respective
districts.
In the event there are no qualified applicants, the
provisions of paragraph 5 of this agreement shall apply." (Emphasis
in bold added)
-4-
The above-quoted Letters of Agreement make it crystal clear that, contrary to Amtrak's
assertions (and the assertions of many freight carriers), Holland Welding Machines and the GREX
Slot Machine are available for least
without contractor operators so that BMWB-represented
employes may be assigned to operate these machines. It is clear that Amtrak was less than candid
during the claim handling when it falsely asserted that it could not lease the machines in question.
It is even more incredible that the Carrier Member would continue to insist that the machines
could not be leased without operators now that Amtrak has signed Letters of Agreement providing
that it would lease the machines for BMWE-represented employes to operate.
Finally, the Carrier Member is simply wrong when he asserts that the Board exceeded its
authority by directing that the work in question be returned to the BMWE. Public Law Board No.
6671 was established pursuant to Section 3 Second of the Railway Labor Act which grants the
Board broad discretion to resolve disputes growing out of the interpretation or application of
agreements concerning rates of pay, rules, or working conditions. Hence, the Board had broad
discretion to resolve the instant dispute pursuant to the Railway Labor Act itself. Moreover, the
Questions At Issue referred to the Board by the parties make it clear that once the Board found
that Amtrak had violated the May 19, 1976 Agreement (as amended), it had broad discretion to
determine "... what shall the remedy be?".
Awards 2 and 3 of PLB No. 6671 could hardly have been reasoned or written more clearly.
If future readers accept the inexorable logic that the precedential value of an award is proportionate
to the clarity of reasoning in the award, then Award No. 1 of this Board will indeed carry powerful
precedential value.
Respectfully submitted,
Ahl
-5-