BEFORE PUBLIC LAW BOARD NO. 7007
BROTHERHOOD OF MAINTENANCE OF WAY EMPLOYES
and
MASSACHUSETTS BAY COMMUTER RAILROAD
Case No. 10
STATEMENT OF CLAIM:
(1) The Agreement was violated when the Carrier assigned outside forces (Matrix) to
perform Maintenance of Way work (fabricate a fall arrest system) for use in
working on passenger cars at the CRMF-BET and delivered thereat on May 28,
2004 (Carrier's File MBCR-BMWE-14/0904).
(2) The Agreement was further violated when the Carrier failed to furnish the General
Chairman with written advance notice of its intent to contract out the work
described in Part (1) above, as required by Rule 24.
(3) As a consequence of the violations referred to in Parts (1) and/or (2) above,
Claimants N. Munro, P. Popczuk, D. Christian and J. Cronin shall now each be
compensated for a total of one hundred fifty (150) hours at their respective rates
of pay.
FINDINGS:
The Organization filed the instant-claim alleging that the Carrier violated the
parties' Agreement when it employed outside forces to fabricate a fall arrest system atop
passenger cars in the CRMF-BET, instead of assigning this work to its own B&B forces.
The Carrier denied the claim.
The Organization initially contends that the work at issue was ordinary work of
B&B mechanics, and there can be no question that the work accrued to the Carrier's
B&B forces in that it is undisputed that similar work was assigned to them the year
before. The Organization asserts that there also is no dispute that Claimant Munro, who
was the foreman over similar fabrication work that was performed under his jurisdiction a
1
PLB NO. 7007
Case No. 10
year earlier, was asked to provide the Carrier with an estimate for the work at issue here.
The Organization then maintains that the Agreement's advance notice provisions
require the Carrier to notify the General Chairman of its plans to contract out work within
the scope of the schedule agreement. The Organization argues that the work in question
is scope-covered, if not exclusively, then colorably for purposes of notice, particularly in
light of the Carrier's request for an estimate on the work from Claimant Munro. The
Organization emphasizes that exclusivity need not be shown to establish a "notice"
violation. The Organization contends that the Carrier's failure to provide such notice
goes to the very heart of this dispute and serves as a basis for questioning the Carrier's
good faith in handling this situation. The Carrier simply assigned the work in question to
outside forces without first giving advance notice to the General Chairman as required by
Rule 24, thereby precluding good-faith conference discussions. As has been found in
numerous Board Awards, this constitutes a direct and serious violation of the Agreement.
The Organization points out that under the circumstances, it is clear that the instant claim
should be sustained based upon the Carrier's undisputed failure to provide advance
notice.
The Organization goes on to assert that the Carrier waived exception to the
bona
fides
of the instant claim by failing to provide notice and precluding good-faith
conference discussions. Moreover, the Carrier cannot validly excuse its violation by
asserting that it was not purchasing "labor" when the contractor used materials of the type
that AMTRAK furnished the Claimants the years before to fabricate a similar system.
The Organization insists that the Carrier's "affirmative defense" is meritless.
2
PLB NO. 7007
Case No. 10
The Organization ultimately contends that the instant claim should be sustained in
its entirety.
The Carrier initially contends that the Organization has failed to meet its burden of
proof in this matter. The Carrier asserts that the claims are utterly frivolous and should
be dismissed in their entirety.
The Carrier argues that the Organization failed to demonstrate how the three
Claimants were harmed, or what positions the Claimants held that "normally" would
have done this work. The Carrier maintains that the Organization failed to submit any
evidence to show that the construction of the pre-fabricated system, as performed by the
vendor, constituted 150 hours for each Claimant. The Carrier emphasizes that the
Organization also failed to show that the Carrier's decision to purchase the pre-fabricated
assets violated the clear and unambiguous language of Rule 24.
The Carrier points out that no layoff of any employee in the BMWE bargaining
unit occurred as a result of the Carrier's procurement of the fall arrest components. The
Carrier contends, in addition, that the system was installed by BMWE employees. The
Carrier insists that there is no evidence that its procurement of pre-fabricated components
of the fall arrest system constituted work "normally performed" by and/or historically and
customarily accrued to the BMWE. The Carrier asserts that whether or not employees
previously had performed similar activity does not advance these claims. Moreover, the
Organization has failed to show that the work of building fall arrest systems comes within
the exclusive province of the BMWE.
The Carrier then argues that as to the claim that it failed to provide advance notice
3
PLB NO. 7007
Case No. 10
of its intent to contract out, the Carrier did not act in bad faith, and the rule does not
provide, either explicitly or implicitly, for a monetary award in the event of a failed
notification. The Carrier insists that the Organization's claims are entirely excessive,
lacking in merit, and warrant denial.
The Carrier then argues that the Organization's referral to a tribunal, dated
December 14, 2006, was untimely. Rule 14 of the Agreement requires such referrals to
be initiated within 185 days of the Carrier's denial, which occurred in this case on
December 8, 2004. The Carrier maintains that the claims are flawed at this point and
should be denied.
The Carrier ultimately contends that the instant claim should be denied in its
entirety.
The parties being unable to resolve their dispute, this matter came before this
Board.
This Board has reviewed the record in this case, and we find that the Organization
has met its burden of proof that the Carrier violated the parties' agreement when it
employed outside forces to fabricate a fall arrest system atop passenger cars without
giving the required written advance notice of its intent to contract out the work to the
Organization. Therefore, the claim must be sustained, in
part.
Rule 24 states the following:
1. In the event the Carrier plans to contract out work
within the scope of the schedule agreement, the Chief
Engineer shall notify the General chairman (sic) in writing
as far in advance of the date of the contracting transaction
as is practicable and in any event not less than 15 days
4
PLB NO. 7007
Case No. 10
prior thereto.
2. If the General Chairman requests a meeting to
discuss matters relating to the said contracting transaction,
the Chief Engineer or his representative shall promptly
meet with him for that purpose. The Chief Engineer or his
representative and the General Chairman or his
representative shall make a good faith attempt to reach an
understanding concerning said contracting, but if no
understanding is reached the Chief Engineer may
nevertheless proceed with said contracting, and the
General Chairman may file and progress claims in
connection therewith.
3. Nothing in this Rule shall affect the existing rights
of either party in connection with contracting out. Its
purpose is to require the Carrier to give advance notice
and, if requested, to meet with the General Chairman to
discuss and if possible reach an understanding in
connection therewith.
The record reveals that there was no advance written notice given to the General
Chairman as required by Rule 24. Consequently, there were no good-faith conference
discussions that took place. Although the Carrier states that it was not purchasing labor,
the record reveals that the contractor used materials similar to those that the Carrier
furnished the Claimants in previous years to fabricate a similar system. Consequently,
this Board finds that the notice should have been given to the Organization and, by failing
to do so, the Carrier violated the Agreement.
Once this Board has determined that there was a violation of the Agreement
because of the failure to issue a notice, we next must determine what the remedy should
be. In this case, the Organization requests 150 hours for four Claimants, for a total of 600
hours. There is no question that employees are entitled to pay, even if they were fully
employed at the time of the subcontracting, for violations of this rule. However, it is up
5
PLB NO. 7007
Case No. 10
to the Organization to provide the evidence to the Board for it to be able to determine
what the appropriate number of hours are owed to the Organization members. In this
case, there is no evidence in the record to assist the Board in determining the amount of
hours that were lost to the Organization employees as a result of the subcontracting.
Consequently, this Board must find that it will retain jurisdiction for a period of 180 days
while the parties make an effort to obtain the contracts and determine the number of man
hours that it took for the subcontractor to perform the work at issue. This Board is
optimistic that once that number of hours is determined, the parties will be able to resolve
the matter on its own. We reserve jurisdiction only for the purpose of assisting the
parties in resolving the matter of the remedy if they are unable to do so on their own.
AWARD:
The claim is sustained in part. The Carrier violated the parties' agreement when it
failed to provide the required notice pursuant to Rule 24. The parties are ordered to
attempt to determine the number of man hours that it took the subcontractor to perform
the work at issue and then reimburse the Organization members who would have
performed that work had it not been subcontracted. This Board retains jurisdiction for a
period of 180 days to assist the parties in the event that they are unable to reach
6
PLB NO. 7007
Case No. 10
agreement as to the amount of the remedy ordered b this Board.
P ER . ME RS
,;
Neutral Member)
y
i ~
j.
ORGANIZAT ON MEMBER CARRIER MEMBER
DATED: ~ b DATED:
7