PUBLIC LAW BOARD NO. 7035
CASE NO. 6
(Brotherhood of Maintenance of Way Employes
PARTIES TO THE DISPUTE: (Division - HIT Rail Conference
(
(and
(
(National Railroad Passenger Corporation
(Amtrak
STATEMENT OF CLAIM:
(1) The Agreement was violated when the Carrier failed and
refused to allow Mr. R. Foronda, following his return to work on
April 24, 2006, to place himself on the B&B foreman position that
was awarded to junior employe M. Mancini on April 24, 2006
(Carrier's File BMWE-530 NRP).
(2) As a consequence of the violation referred to in Part (1) above,
Claimant R. Foronda shall now `... be allowed to own the position
of B&B Foreman, be paid the difference in the rates of pay and be
placed on the roster ahead of Mr. Mancini as a remedy to the
Carrier's violations.' "
FINDINGS:
The Board, upon consideration of the entire record and all the evidence,
finds that he parties are Carrier and Employee within the meaning of the Railway
Labor Act, as amended; that this Board is duly constituted by Agreement; this
Board has jurisdiction over the dispute involved herein; and that the parties were
given due notice of the Hearing held.
Applicants for a temporary vacancy for a B&B Mechanic Foreman in Gang
M-301 headquartered in Rennselear, New York were required to demonstrate
qualifications for the position through the Carrier's written examination and
structured interview process. On February 2$, 2006, Claimant and "C" Operator
Form 1 Case No. 6
Page 2 PLB 7035
Michael Mancini were administered a written examination by the Carrier's H. R.
Dept.
The record indicates that Claimant received a 30-day Suspension (15 days
held in abeyance) and CSX barred Claimant from its Territory until cleared by K.
M. O'Toole of CSX. Said penalty was the result of a March 9, 2006 incident in
which Claimant negligently disabled an automatic grade crossing warning device
without permission from the Train Dispatcher and subsequently returned the track
back to service without notifying the Dispatcher. Claimant served his Suspension
from April 4 through April 18, 2006.
On April 12, 2006, during Claimant's absence, the Carrier advertised a B&B
Mechanic Foreman in Gang M-301, headquartered in Rennsalear, New York. Said
position required CSX qualifications. Applications were accepted until April 28,
2006. Both Mancini and Claimant submitted -bids for the position. Mancini was
interviewed on April 12. Claimant was not interviewed because he was in the
process of serving his 15-day Suspension and was barred from operating over CSX
territory, thus disqualifying Claimant from the position. The position was awarded
to Mancini on April 24, 2006. On April 28, 2006, the Carrier requested that CSX
consider lifting the ban against Claimant. On May 4, 2006, CSX did agree to lift the
ban, thus permitting Claimant to work on CSX territory. However, such action was
beyond the 7-day period in which Claimant was eligible to exercise his seniority.
By letter dated May 18, 2006, the Organization submitted a Claim on behalf
of Claimant for establishment of a seniority date on the B&B Foreman roster and
payment of lost earnings because he was not selected for the B&B Foreman position.
The Division Engineer denied the Claim in a letter dated July 12, 2006. The Claim
was appealed in the usual and customary manner.
According to the Organization, the Carrier violated Rules 5, 7, 8 and 15 of
the Agreement when it denied Claimant the B&B Foreman position. According to
the Organization, because Claimant was senior to Mancini, and because Claimant
had passed the qualifying exam, he should have been promoted to the position of
B&B Foreman. As a remedy, the Organization claims that Claimant should be
placed into the position of B&B Foreman, compensated for lost pay and be placed
on the B&B Foreman roster ahead of Mancini.
Conversely, the Carrier argues that the Organization cannot meet its burden
of proof that Claimant is entitled to the position of B&B Foreman. According to the
Carrier, Claimant did not have all of the requisite qualifications which included the
approval of CSX. At the time of the bid, Claimant did not have approval from CSX
based on his earlier disciplinary Suspension. The Carrier was justified in denying
Claimant the position.
Form I Case No. 6
Page 3 PLB 7035
After a review of all the relevant evidence, this Board finds that the
Organization has been unable to meet its burden of proof. One of the qualifications
of the B&B Foreman position is the ability to work on CSX Territory. It is clear
that Claimant, based on his earlier Suspension, was temporarily barred from CSX
Territory. The question of the ability to work on CSX Territory falls within the
purview of CSX and during the relevant time period, CSX had not yet allowed
Claimant to work on CSX Territory. The Carrier did not act unreasonably. The
Claim is denied.
The Claim is denied.
Form I Case No. 6
Page 4 PLB 7035
AWARD
Claim denied.
Dig! signdby5even6ierg
Steven
N: -nSteen Bietig, o=Steven
M. Bierig Attorney-Arbitrator
B i
e r i g
Mediator, °°'
email=arb438@comcast.net, c=US
Wm 2010.03.01 1593:38-06'00'
Steven M. Bierig
Chairperson and Neutral Member
6
0~00_)Zlli
4--l-
/,-I-
Bradley A. Winter Rachelle-A. Mie e
Organization Member Carrier Member
Dated at Chicago, Illinois this l" Day of March, 2010.