AWARD NO. 14 CASE NO. 14

PUBLIC LAW BOARD NO. 7096

PARTIES
TO
DISPUTE

STATEMENT OF CLAIM

Claim of the System Committee of the Brotherhood that:

BROTHERHOOD OF AWNTENANCE OF WAY EMPLOYEES

UNION PACIFIC RAILROAD COMPANY

The Agreement was violated when the Carrier assigned outside forces (Bannock Paving Company, Inc.) to perform Maintenance of Way work (clean right of way and preparation work for installation of track) at Mile Post 459.20 in the West Nampa, Idaho Yards on January 10, 11, and 14, 2002, instead of Idaho Division Truck Operators D. Hanson, E. Ibarra, D. White, Roadway Equipment Operators C. Gossage, M. Dunn, Foreman D. Stone and Sectionmen M. Cabutti, J. Marsing, B. Grever and E. Eckhardt (System File J0252-53 / 1305119).



tenance of Way forces as required by Rule 52 and the December 11, 1981 Letter of Understanding.



OPINION OF BOARD

The dispute in this case concerns the Carrier's contracting of clean up of the right of way and preparation work for the installation of track after a derailment in the West Nampa, Idaho Yard, which work was performed on January 10, 11 and 14, 2002, with the Organization contending that such was an improper

PLB 7096, Award 14

Hanson, etc.

Page 2


contracting of scope covered work and no notice was given by the Carrier as required by Rule 52. In pertinent part, Rule 52 pro-

vides

RULE 52 - CONTRACTING

(a) By agreement between the Company and the General Chairman, work customarily performed by employees covered under this Agreement may be let to contractors and be performed by contractors' forces. However, such work may only be contracted provided that special skills not possessed by the Company's employees, special equipment not owned by the Company, or special material available only when applied or installed through supplier, are required; or when work is such that the Company is not adequately equipped to handle the work; or when emergency time requirements exist which present undertakings not contemplated by the Agreement and beyond the capacity of the Company's forces. In the event the Company plans to contract out work because of one of the criteria described herein, it shall notify the General Chairman of the Organization in writing as far in advance of the date of the contracting transaction as is practicable and in any event not less than fifteen (15) days prior thereto, except in "emergency time requirements" cases. If the General Chairman, or his representative, requests a meeting to discuss matters relating to the said contracting transaction, the designated representative of the carrier shall promptly meet with him for that purpose. Said carrier and organization representatives shall make a good faith attempt to reach an understanding concerning said contracting, but if no understanding is reached, the carrier may nevertheless proceed with said contracting and the organization may file


and progress claims in connection therewith.




(d) Nothing contained in this rule shall impair the Company's right to assign work not customarily performed by employees covered by this Agreement to outside contractors.

Rule 52 applies in this case because the type of work - clean up of the right of way (including after derailments) and preparation work for


the installation of track - is work which has been performed by Claimants and is therefore "... work customarily performed by employees covered under this Agreement ..." under Rule 52(a).

The Carrier's argument that the Organization must show that the covered employees performed the disputed work on an exclusive basis has been rejected in Awards 1, 2, 3, 5, 9, 11, 12 and 13 of this Board.

PL13 7096, Award 14

Hanson, etc.

Page 3


In its March 13, 2002 letter, the

Carrier asserted that:

The work cited in your claim was performed in connection with a derailment. This was unplanned work undertaken on an emergency basis.


The Organization disputed the Carrier's assertion that an emergency existed.

The Carrier's obligations under Rule 52(a) are excused "... when emergency time requirements exist which present undertakings not contemplated by the Agreement and beyond the capacity of the Company's forces." So the question here is whether the evidence shows that "... emergency time requirements existed[ ..."?

The Carrier's Manager, S. R. Adams, provided the following state-


ment:

The work performed by the said contractor, was under the jurisdiction of the mechanical department to remove derailed cars and parts, and to clear material out of their way to load and remove damaged cars, which they are under contract to do on derailments. Removing of damaged track and ties at derailments historically is done by outside contractors. The building of the track after the derailment was done by gag 6083 and 6384 along with local section forces ....


According to an employee statement (Claimant White), "[t]he Derailment was not on the main line, it was in the yards on yard tracks and no main line trains were ever stopped." Further, according to the Organization in its January 8, 2002 letter, "[the main line was not effected and there was not a stoppage of trains either on the Main Line or


in the Yard Tracks."

In Third Division Award 38349, the parties faced the same issue involving the same contractor with an emergency asserted by the Carrier caused by another yard derailment. The Third Division sustained the


claim and held:

A review of Third Division Awards reveal that the existence of an "emergency" in a derailment situation requires a case by case analysis. (See, e.g., Third Division Award 37644 where the Board stated "(d]erailments are not `one-shoefits-all,"; See also Award 31036 where the Board determined that the specific facts of that case supported the conclusion that the emergency ceased where the contractor's work forces began to fluctuate "thereby suggesting that the emergency condition did not exist for the entire period in which the work was performed." Further review of Third Division Awards support the conclusion that any claimed emergency must be bona fide where time is o f the essence thereby rendering the Carrier's obligation to supply a Rule 52 notice impractical given the exigencies that then exist. (See, e.g. Third Division Award 30868 where the Board stated "the Organization

PLB 7096, Award 14

Hanson, etc.

Page 4



We do not find Third Division Award 38349 palpably erroneous and shall follow it.

In this case, the Carrier asserted that an emergency existed. But the contracted work lasted three days and involved cleaning up right of way and preparation work for installation of track after a derailment on a yard track. The state of the record as presented by the Organization is that trains were not stopped on main line or yard tracks as a result of the derailment and clean up work. We must therefore find that the Carrier has not shown that the conditions which existed on the three days in question were "... when emergency time requirements exist which present undertakings


not contemplated by the Agreement and beyond the capacity of the Company's forces" so as to support its position that an emergency existed which could excuse its obligations under Rule 52. Without that kind of showing, we cannot find that an emergency existed.

Rule 52 gives the Carrier significant managerial latitude with respect to contracting out scope covered work. But there are preconditions and obligations that nevertheless exist in that rule, which were not met in this case - particularly with the Carrier's need to show that, in fact, an emergency existed as asserted by the Carrier. On that basis, we shall sustain the claim.

Because Claimants were deprived of potential work opportunities they shall therefore be made whole for those lost work opportunities. See Award I of this Board [quoting Third Division Award 32862]:


... Our discretion for fashioning remedies includes the ability to construct make whole relief. The covered employees as a whole are harmed when the Carrier takes action inconsistent with the obligations of the Agreement ... to contract work within the scope of the Agreement . ...

PLB 7096, Award 14

Hanson, etc.

Page 5




AWARD




Edwin H. Berm

Neutral Member








Chicago, Illinois