AWARD NO. 5 CASE NO. 5

PUBLIC LAW BOARD NO. 7096

PARTIES ) BROTHERHOOD OF MAINTENANCE OF WAY EMPLOYEES
TO )
DISPUTE ) UNION PACIFIC RAILROAD COMPANY (FORMER CHICAGO
NORTHWESTERN TRANSPORTATION COMPANY)

STATEMENT OF CLAIM

Claim of the System Committee of the Brotherhood that:




(3) As a consequence of the
violations referred to in

Parts (1) and/or (2) above, Claimants J. Lilly, R. Pichler and D. Zawistowski shall now each be compensated at the rate of pay applicable to the positions which Claimants could have held (Zawistowski and Lilly at Class B Machine Operator rate and Claimant Pichler at Trackman rate) for an equal share of the total hours of work performed by Contractor forces in performance of the brush cutting in the vicinity of Merrillan, WI on September 13, 14, 15 and 16 and any dates subsequent thereto.


OPINION OF BOARD

This is a factually similar dispute to the dispute decided in Award 3 of this Board involving the five year contract the Carrier entered into with DeAngelo Brothers, Inc. for brush cutting on various portions of the Carrier's right of way. For the same reasons expressed in Award 3, this claim shall be denied.

PLB 7096, Award 5

Lilly, etc.

Page 2


AWARD














Chicago, Illinois



Dated: