BROTHERHOOD OF MAINTENANCE OF )
UNION PACIFIC RAILROAD COMPANY )
STATEMENT OF CLAIM:
Claim of the System Committee of the Brotherhood that:
Appeal by the Organization on behalf of D. Caspers regarding the Carrier's assignment
of work to outside forces to perform routine Maintenance of Way Roadway Equipment
Operator's work (disc right of way for fire guard) along the main track between Mile
Post 181 and Mile Post 234 on the Powder River Subdivision, from July 28, 2005
through August 4, 2005,1 instead of assigning the work to D. Caspers, a Roadway
Equipment Operator ("REO").
In addition, the Organization alleges the Carrier failed to furnish the General
Chairman with the proper advance written notice of its intent to contract the work in
dispute and failed to make a good faith attempt to reach an understanding concerning the
subcontracting of the work as provided by Rule 52 of the Agreement. As a remedy, the
Organization asks for D. Caspers to be compensated for forty (48) hours straight time and
forty eight (48) hours at time and a half rate of pay at the applicable rate of pay for the
lost of work opportunity.
FINDINGS:
The following facts are undisputed: Claimant has a seniority date of September 4,
1973. He holds seniority as a REO in Carrier's Roadway Equipment Subdepartment
since July 13, 1976. During the time in question, Claimant was assigned and worked
' All dates herein referred to the year 2005 unless otherwise specified.
PLB No. 7100
Award 12
operating a 644 end loader on Gang 5037, headquartered at Lusk, Wyoming, and His
regular work schedule was Monday through Friday, 6:30 a.m. to 3:00 p.m.
By letter dated January 3, entitled "15 Day Notice of Intent to Contract Work",
sent by Deland Humphreys, the Director of Track Maintenance, to General Chairmen
David D. Tanner and Kent Bushman', Carrier stated,
verbatim,
the following:
THIS IS TO ADVISE OF THE CARRIER'S IN`
THE FOLLOWING WORK:
PLACE: At various locations on the North Platte Service Unit.
TO CONTRACT
SPECIFIC WORK: Providing fully operated, fueled and maintained tractors,
mowers and other equipment necessary to control vegetation. Commencing
January 3, 2005 to December 31, 2005.
THIS WORK IS BEING PERFORMED UNDER THAT PROVISION OF THE
AGREEMENT WHICH STATES "NOTHING CONTAINED IN THIS RULE
SHALL AFFECT PRIOR AND EXISTING RIGHTS AND PRACTICES OF
EITHER PARTY 1N CONNECTION WITH CONTRACTING OUT."
SERVING OF THIS "NOTICE" IS NOT TO BE CONSTRUED AS AN
INDICATION THAT THE WORK DESCRIBED ABOVE NECESSARILY
FALLS WITHIN THE "SCOPE" OF YOUR AGREEMENT, NOR AS AN
INDICATION THAT SUCH WORK IS NECESSARILY RESERVED, AS A
MATTER OF PRACTICE, TO THOSE EMPLOYEES REPRESENTED BY
THE BMWE. '
IN THE EVENT YOU DESIRE A CONFERENCE IN CONNECTION WITH
THIS NOTICE, ALL FOLLOW-UP CONTACTS SHOULD BE WITH THE
LABOR RELATIONS DEPARTMENT.
By letter dated January 7, Tanner to Mac McNully,3 the Organization notified
Carrier it considered the notice vague and inadequate pursuant to the requirements of
z The Organization's Submission Exhibit A-2.
3 The Organization's Submission Exhibit A-2.
2
PLB No. 7100
Award 12
Rule 52 of the Agreement, inasmuch as it failed to identify the location or times for each
instance the work was to be performed. In addition, the Organization requested a
conference and made a request for certain information related to the work mentioned in
Carrier's notice.
On January 21, a conference was held between the parties to discuss Carrier's
intent to subcontract the work in dispute. Thereafter, by letter dated January 24, sent to
Tanner by T.M. Lee, the Manager of Labor Relations, Carrier advised the Organization it
was going to proceed with the contracting of the work in dispute stating its determination
was not in violation of the Agreement since "the Carrier has a strong mixed practice of
contracting out such work.
,4
In its letter, Carrier referred to a letter dated February 16,
1997, which contained several exhibits of listings provided by Carrier to the General
Chairman regarding past work contracted by the Carrier to outside forces.
By letter dated February 3, sent by Tanner to Toby Lees, the Assistant Director of
Labor Relations, the Organization reiterated its position the Carrier has not routinely
contracted the work in dispute to outside forces and stated in the past the work in dispute
has been performed by BMWE employees. The Organization also stated Carrier
possessed the equipment needed (vacuum trucks) to perform the work in dispute.
Further, the Organization stated the lists of work contracted to outside forces submitted
by the Carrier was not relevant to the instant case because the works mentioned were
performed after 1973 (where no notice was given) or are unrelated to the nature of the
work in dispute.
4
The Organization's Submission Exhibit
3
PLB No. 7100
Award 12
On Thursday, July 28, and continuing through Thursday, August 4, Carrier
assigned to Caylor & Genz Earth Movers, Inc. ("Caylor & Genz"), a contractor, the disc
right of way for fire guard along the main track between MP 181 and 234 on the Powder
River Subdivision.
The Organization argues disking the right of way for fires has been customarily
and historically performed since the inception of the Powder River Subdivision by
Maintenance of Way employees to help control the fires along side of the track. It
maintains the work involved did not require any special equipment or special skills to be
performed; and Carrier possessed or could have leased the necessary equipment in this
case. The Organization claims Caylor & Genz used one (1) employee (not covered by the
Agreement) who worked twelve (12) hours per day on six (6) of Claimant's regularly
assigned days and two (2) of Claimant's rest days to perform the work in dispute.
According to the Organization, Caylor & Genz' the employee used an "ordinary tractor
type machine to pull a disc attachment to perform the routine fine lane right of way
maintenance." Further, it argues Claimant is qualified to perform the work; has
performed the work in previous years; and was available to perform the work. The
Organization contends Carrier's assignment of the disputed work to Caylor & Genz was
in violation of Rule 1, 2, 3, 4 Group 19(a), 5, 52(a) of the July 1, 2001 Agreement.
RULE 1- SCOPE OF THE AGREEMET
This Agreement will govern the wages and working conditions of
employees in the Maintenance of Way and Structures Department
listed in Rule 4 represented by the Brotherhood of Maintenance of Way
Employees Organization.
4
PLB No. 7100
Award 12
RULE 2- DEPARTMENT
The Maintenance of Way ad Structure Department as used herein
means the Bridge and Building Subdepartment, the Track
Subdepartment, Roadway Equipment Subdepartment and
Miscellaneous Subdepartments as constituted as of the effective date of
this Agreement.
RULE 3- SUBDEPARTMENTS
The following subdepartments are hereby established within the
Maintenance of Way and Structures Department covered by this
Agreement:
Bridge and Building Subdepartment
Track Subdepartment
Roadway Equipment Subdepartment
Miscellaneous Subdepartment
Any subdepartment hereafter established, including Groups and
Classes within such Subdepartment, will be by negotiations and
agreement between the parties to this Agreement.
RULE 4- SENIORITY GROUPS AND CLASSES
ROADWAY EQUIPMENT SUBDEPARTMENT DISTRICT:
Group 19 (a) Roadway Equipment Operator
RULE 5- CLASSIFICATION OF WORK
Positions will be classified and paid in accordance with work
performed in conformity with the classification listed in Rule 6 through
12, and as established by Agreement, rules, and/or traditional practice.
RULE 52-CONTRACTING
1. By agreement between the Company and the General
Chairman, work customarily performed by employees covered
under this Agreement may be let to contractors and be
performed by contractors' forces. However, such work may
5
PLB No. 7100
Award 12
only be contracted provided that special skills not possessed
by the Company's employees, special equipment not owner
by the Company, or special material available only when
applied or installed through a supplier, are required, or
when work is such that the Company is not adequately
equipped to handle the work, or when emergency time
requirements exist which present undertakings not
contemplated by the Agreement and beyond the capacity of
Company's forces. In the event the Company plans to
contract out work because of one of the criteria described
herein, it will notify the General Chairman of the
Organization in writing as far in advance of the date of the
contracting transaction as is practicable and in any event
not less than fifteen (15) days prior thereto, except in
"emergency time requirements" cases. If the General
Chairman, or his representative, requests a meeting to
discuss matters relating to the said contracting transaction,
the designated representative of the Company will promptly
meet with him for that purpose. Said Company and
organization representative will make a good faith attempt
to reach an understanding concerning said contracting but
if no understanding is reached the Company may
nevertheless proceed with said contracting, and the
Organization may file and progress claims in connection
therewith.
II. Nothing contained in this rule will affect prior and existing
rights and practices of either party in connection with
contracting out, its purpose is to require the Carrier to give
advance notice and if requested, to meet with the General
Chairman or his representative to discuss and if possible
reach an understanding in connection therewith.
Ill. Nothing contained in this rule requires that notices be given,
conferences be held or agreement reached with the General
Chairman regarding the use of contractors or use of other than
maintenance of way employees in the performance of work in
emergencies such as wrecks, washouts, fires, earthquakes,
landslides and similar disaster.
Iv. Nothing contained in this rule shall impair the Company's right
to assign work not customarily performed by employees
covered by this Agreement to outside contractor.
(Emphasis added)
6
PL13 No. 7100
Award 12
December 11, 1981
Mr. O. M. Berge
President Brotherhood of Maintenance
Of Way Employes
12050 Woodward Avenue
Detroit, Michigan 48203
Dear Mr. Berge:
The Carrier assure you that they will assert good-faith efforts to reduce
the incidence of subcontracting and increase the use of their maintenance of
way forces to the extent practicable, include the procurement of rental
equipment and operation thereof by carrier employees.
The parties jointly reaffirm the intent of Article IV of the May 17,
1968 Agreement that advance notice requirements be strictly adhered to and
encourage the parties locally to take advantage of the good faith discussions
provided for to reconcile any differences. In the interests of improving
communications between the parties on subcontracting, the advance notices
shall identify the work to be contracted and the reasons therefore.
The Organization further contends the work performed by Caylor & Genz falls within
the Track Subdepartment and the Roadway Equipment Subdepartment as defined in Rules 2,
3, 4 Group 19(a) of the Agreement. It asserts the statements submitted by Claimant and
twenty (20) other employees shows the work performed and the equipment used, was
recognized by the employees on the Powder River Subdivision as Maintenance of Way's
work. It also insists the equipment used to perform the work in dispute has been ordinarily
used by these employees. Specifically, Claimant states as follows:
7
PLB No. 7100
Award 12
January 24, 2006
To Whom It May Concern:
This is in response to Mr. D.A. Ring's letter dated 1-05-06 File #1433247
organization File # UPRM 968T concerning right of way fire guard disking,
so as to put the carrier in compliance with Wyoming State Law requiring a
twenty foot fire guard path be disked and maintained on both sides of RR
right of way.
Mr. Ring states the B.M.W.E. has not proven that this work has been
performed by B.M.W.E. in exclusion of all others on a system wide basis.
1, David A. Caspers 0030600, 32 year seniority CNW 1973-1996; UPRR 1996
to present; working in South Dakota, North Dakota, Nebraska and the colony
line state of Wyoming; the issue of disking fire guard never came up. Neither
BMWE nor contractor did it. It wasn't required.
I first became aware of the fireguard disking requirements upon the inception
of the CNWRR Powder River Coal Line MP159-MP271. This disking began
in the mid 1980's and continues to present, and has always been done by
B.M.W.E employees. Usually two road equipment operators working in relay,
one disking and one opening gates and other support duties
The CNWRR purchased a new Rome construction grade disc at this time (mid
1980's) for the exclusive purpose of fire guard disking.
The disc was pulled by a John Deere Crawler tractor JD850B, machine #
174038, owned by the railroad. This crawler tractor was modified to pull
above names disk. The John Deere Crawler tractor #174038 has since retired
in 2002.
The UPRR has since leased rubber tracked crawler tractors to pull abovementioned disk.
Road equipment operators of the B.M.W.E. have also always operated the
lease equipment.
In closing, fireguard disking has always been done by B.M.W.E. forces on the
Powder River Subdivision. One exception, that being the time claim UPRR9684T, now in dispute
Sincerely
David A. Caspers
8
PL13 No. 7100
Award 12
The statement signed by twenty (20) employees state the "right of way disking has
been done exclusively by B.M.W.E. forces since the inception of the Power River
Subdivision. Twenty feet as required by law in Wyoming MP 271-179 each side of the
railroad right of way. Also one pass ten feet has been done in Nebraska MP 179-160, not
required, just prudent practice."
In addition, the Organization argues Carrier violated Rule 52(a) of the Agreement and
the December 11, 1981, Letter of Understanding, when it subcontracted the work in dispute
without providing proper advance written notice to the General Chairman and when failed to
make a good faith effort to assign its Maintenance of Way forces the fire guard work in
dispute. It claims the Notice sent by the Carrier was vague because it failed to state when
and where the "vegetation control" work would be perform. Further, is insists none of the
exceptions detailed in Rule 52 of the Agreement (to justify subcontracting of work) was
present in this case. In this regard, it argues the equipment used was a tractor-type machine
with a disc attachment was "common to virtually every farm." The Organization refutes
Carrier's assertion Claimant has no exclusive right to the work in dispute to the exclusion of
others. The Organization argues the exclusivity argument has been rejected by the Board in
contracting dispute. Finally, the Organization refutes the Carrier's argument Claimant is not
entitled to the remedy requested because he was employed on the dates involved in the
dispute. The Organization contends the Third Division has awarded monetary compensation
and made whole fully employed employees for lost work opportunity in subcontracting
cases.
Carrier, on the other hand, argues it has a historical practice of subcontracting the
9
PLB No. 7100
Award 12
work of fully operated tractors, mowers and other equipment needed to control vegetation on
a system wide basis. It contends the work in dispute falls within the "existing rights and
practices" exception contained in Rule
52
(b) of the Agreement. It further maintains the
work of controlling vegetation is not exclusive to the BMWE employees covered by the
Agreement. Furthermore, it argues, the fact the work in dispute has never been
subcontracted on the Powder River Subdivision is of no relevance. It contends "the existing
rights and practices" under the Agreement are based on a system wide basis. It also contends
the Third Division in countless awards has held pursuant to Rule
52
(b), where a "mixed
practice" exists of contracting the work out
and
using employees covered the Agreement,
Carrier has the right to use its discretion to have either contractors or BMWE employees to
do the work.' In this respect, Carrier argues the Organization never disputed its past practice
on a system wide basis. It notes during the on property handling of the Claim it provided the
Organization with various lists documenting its past practice of contracting out plowing fire
guards. Specifically, it cited to documentation provided in
1996
by Carrier to the General
Chairman to establish a mixed practice of contracting out the work of "plowing fire guards
and destroying weeds" in various locations in Wyoming and Colorado. `
Therefore, Carrier insists it did not violate the Agreement since it provided the
General Chairman with the required advance written notice; the notice conformed with the
requirements of Rule
52
inasmuch as it was timely and provided the Organization with a
description of the work; and a conference was held between the parties to discuss the
contracting of the work in dispute. In these circumstances, it contends, Carrier showed the
' Third Division Award No.
30287,
PLB
5546,
Case No.
15
10
PL13 No. 7100
Award 12
good faith required by Rule 52 of the Agreement.
With regard to the remedy requested, Carrier asserts Claimant is not entitled to any
monetary relief. It argues even if the Board finds Carrier violated the Agreement when it
subcontracted the work in dispute, the remedy in subcontracting cases is confined to
furloughed employees. Here, Carrier maintains, it is uncontested Claimant was fully
employed during the period in question.
After reviewing the record facts, the Board finds the grievance must be denied. It is
well established pursuant to Rule 52 of the Agreement and the December 11, 1981, letter
Carrier is required to provide advance written notice and confer, if requested, with the
Organization in all instances where Maintenance of Way work is to be contracted; and to
engaged in good faith efforts "to reduce the incidents of subcontracting and increase the use
of their maintenance of way forces."6 The Board finds the Carrier complied with the Notice
and conference requirements contained in Rule 52 of the Agreement. The Notice was timely
and contained a description of the work and there reasons thereon. Further, it is uncontested
the parties held a conference to discuss the work in dispute.
A review of the record shows the contracting in this case falls within the "existing
practice" exception provided in Rule 52(b) of the Agreement, which states, "nothing
contained in this rule will affect prior and existing rights and practices of either party in
connection with contracting out." Here, the record evidence supports Carrier's contention
about its system wide practice for using contractors in certain subdivisions to perform the
work in dispute. The fact Carrier has not used contractors in the Powder River Subdivision
6
Third Division Award Nos. 28590, 31025, 31038, 31041 and 35736
11
PLB No. 7100
Award 12
is not determinative. The Carrier presented extensive documentation submitted to the
General Chairman R.B. Wehrli in 1996 regarding its past contracting practices on all phases
of track, roadbed and bridge & building work. This documentation included work which
involved plowing fire guards, ditch right of way cleaning, mowing, ditching and grading and
weed control. The Third Division has held in numerous cases Rule 52(b) permits the
subcontracting of work when Carrier has a "mixed practice" of using outside contractor and
employees to perform the work in dispute.' The Board finds the Carrier has successfully
established a "mixed practice" of using contractors and employees covered by the
Agreement to perform the work in dispute.
The Board agrees with the Organization's argument the use of a tractor to pull a disc
for fire guard does not fall under any of the exceptions provided in Rule 52(a) of the
Agreement. The Board believes Claimant was qualified and available to do the work; and
Carrier could have used the equipment in its possession or leased the equipment to perform
the disputed work. Nonetheless, Carrier did not rely on Rule 52(a) of the Agreement when it
subcontracted the work in dispute. Rather, Carrier asserted the "existing practice" exception
contained in Rule 52(b) of the Agreemerit. Therefore, the Organization's argument is
misplaced. Accordingly, the Claim is denied.
' Third Division Award Nos. 37490, 37365, 29539 and 302$7
12
PLB No. 7100
Award 12
AWARD
Claim denied.
411,~Lz
Martin F. S emman, Esq. Chairman
eutral Member
A
Carrier Member Organ'z ion Member
Dated:
A04A q
?-,Of)
9roiberb-d Cute 12-d
13