PUBLIC LAW BOARD NO. 7101
CASE NO. 9
(Brotherhood of Maintenance of Way Employes
PARTIES TO THE DISPUTE:
(and
(
(Union Pacific Railroad Company
STATEMENT OF CLAIM: "Claim of the System Committee of the Brotherhood
that:
(1) The Agreement was violated when the Carrier utilized outside
forces to perform Maintenance of Way and Structures
Department work (construct track, unload ballast, surface track
and related work) near Mile Posts 204.0 and 204.3 at Ashton,
Iowa on the Worthington Subdivision on February 18, 21 and 26,
2004, instead of Seniority District T-7 employee R. Mefheim, P.
Slater, T. Witt and M. Miles (System File 7RM-9550TI1397777
CNW).
(2) The Agreement was further violated when the Carrier failed to
furnish the General Chairman with an advance written notice of
its intent to contract out the above-referenced work or make a
good-faith attempt to reach an understanding concerning such
contracting as required by Rule 1(b).
(3) As a consequence of the violations referred to in Parts (1) and/or
(2) above, the Claimants R. Melheim, P. Slater, T. Witt arid M.
Miles shall now' *** each be compensated for an equal and
proportionate share of 120 hours of straight time and 12 hours of
overtime that the contractor's forces spent performing their work,
at the applicable rates of pay.
The Carrier has declined this claim."
FINDINGS:
The Board, upon consideration of the entire record and all of the evidence,
finds that the parties are Carrier and Employee within the meaning of the Railway
Page 2 PLB 7101
Case No. 9
Labor Act, as amended; that this Board is duly constituted by Agreement; this
Board has jurisdiction over the dispute involved herein; and that the parties were
given due notice of the Hearing held.
All Claimants in the instant case have established and hold seniority in the
Maintenance of Way and Structures Department on Seniority District T-7 as
follows:
R. J. Melheim Foreman
P. M. Slater Assistant Foreman
T. R. Witt Welder
M. C. Miles Machine Operator (Common)
Sometime prior to the dates in question, the Carrier entered into an
agreement to provide rail service from its Worthington Subdivision rail line to the
Otter Creek Ethanol Plant at Ashton, Iowa.
On January 4, 2004, the Carrier assigned the Worthington, Minnesota
section crew (Gang 3394) to construct approximately 68 feet of track between the
new switch near Mile Post 204.3 and the new Industry track entering the Otter
Creek Ethanol Plant. On Wednesday, February 18, 2004, instead of assigning the
Worthington Section crew or any of its other Maintenance of Way employees to
continue to work on this section of track, outside forces (Railroad Salvage and
Restoration of Joplin, Missouri) unloaded and distributed ballast on this section of
new track. Six employees of the contractor expended 4 hours each in the
performance of the work. On Saturday, February 21, 2004, the Carrier utilized the
same contractor to build 72 feet of track connecting the track at the north end of the
Ethanol Plant to the Carrier's main line track near Mile Post 204.0. Six employees
of the contractor expended 10 hours each to complete the basic track maintenance
work. On Thursday, February 26, 2004, the contractor performed routine track
work. Six employees of the contractor unloaded ballast on the track at Mile Post
204.3 and surfaced and dressed the track on both ends of the way at Mile Posts
204.0 and 204.3
The Organization contends that the Agreement was violated when the
Carrier assigned Railroad Salvage and Restoration of Joplin, Missouri the work of
constructing track, unloading ballast, surfacing track and related work near Mile
Posts 204.0 and 204.3 at Ashton, Iowa on the Worthington Subdivision on February
18, 21 and 26, 2004. The Organization claims that it was improper for the Carrier
to contract out the above-mentioned work, which is work that is properly reserved
to the Organization.
According to the Organization, the Carrier had customarily assigned work of
this nature to the Carrier's Maintenance of Way Employees. The Organization
Page 3 PLB 7101
Case No. 9
further claims that the work in question is consistent with the Scope Rule.
According to the Organization, the Carrier's Maintenance of Way Employees were
fully qualified and capable of performing the designated work. The work done by
Railroad Salvage and Restoration of Joplin, Missouri is within the jurisdiction of
the Organization and therefore Claimants should have performed said work. The
Organization argues that because Claimants were denied the opportunity to
perform the relevant work, Claimants should be compensated for the lost work
opportunities.
Conversely, the Carrier takes the position that the Organization cannot meet
its burden of proof in this matter. The Carrier contends that the work performed
was done by and for the benefit of the third party industry (Otter Creek Ethanol
Plant) and without the knowledge of the Carrier. According to the Carrier, the
Industry's contractor took the initiative to perform the work without the consent or
knowledge of the Carrier. As the work was done without the Carrier's knowledge
or intent, there was no opportunity or reason to provide any Notice to the
Organization. Further, the Carrier claims that the work of February 26, 2004, was
acquiesced by the Carriers' employees. Finally, even if the Organization were to
prevail, the remedy requested is excessive as the Claimants were not on furlough
status and did not suffer any loss of wages.
We initially note that the Carrier has agreed that "The alleged work in
question, per the lease agreement, was to have been done by the Carrier's forces but
constructed at Otter Creek's expense. During the initial correspondence, the
Organization was made aware that alleged work was performed without the
Carrier's knowledge or authorization."
Thus, it is clear that the Organization should have performed the work in
question. However, it also appears that the Industry took it upon itself to complete
the work in question without notifying the Carrier. The Carrier contends that there
is nothing that it could have done in this case to prevent the situation. The
Organization contends that the work in question is their work and as such, should
have been assigned to Claimants.
A review of the materials in question yields that the work in question should
have been performed by the Organization. It is clear and in fact it has been
admitted by the Carrier that the work in question belonged to the Organization.
However, the work in question was done by the Industry without the Carrier's
permission. A review of the record in this case indicates that the work was
improperly performed by the Industry. The Industry Track Agreement required
that "Prior to entering Railroad's right-of-way ... the Industry ... are required to
notify the Railroad ... at least ten (10) working days in advance of such work ...".
In the instant case, there is no evidence of any advance notice.
Page 4 PLB 7101
Case No. 9
It does appear that the work should have been performed by the
Organization, which leads to the conclusions that Notice not provided and that
Claimants were improperly denied the right to perform the work. Therefore, this
Board rules that Claimants were denied the opportunity to engage in the relevant
work on February 18, 21 and 26, 2004.
Having made that determination, the next matter to be considered is the
appropriate remedy. The Carrier contends that because Claimants were fully
employed, there is no need for any additional remedy. Nonetheless, the
Organization contends that Claimants were unfairly denied the opportunity for the
relevant work; therefore, they should be compensated appropriately.
After a review of the all the relevant precedent cited by both parties, this
Board rules that Claimants shall be compensated for the work that was performed
by the Industry on February 18, 21 and26, 2004. As indicated by Referee Kohn in
PLB 7097 Award No. 4:
The remaining issue is the proper remedy for that violation. The
Carrier asserts that a monetary payment to Claimant would be
improper because he was "fully employed" and therefore suffered no
employment loss. That argument has been rejected in Third Division
Awards 35735, 37536 and 37022 ... The Organization asserts that
Claimant was available and willing to perform the work had he been
assigned. Once the Carrier assigned contractors' employees to
perform the work, Claimant lost the opportunity to perform that
work, whether on overtime or otherwise. While the Carrier may
contend that the work would have gone to an employee on furlough,
the Organization is entitled to select its Claimant. Given that the
Carrier was the party in possession of the work records and
contractor invoices to establish the work schedules of the outside
contractors' employees, and failed to provide any documentation to
refute the Organization's claim of lost work opportunity, the
appropriate remedy is that Claimant be compensated for that loss.
Id. at 4.
Thus, after a review of all the facts in this case, we have determined that
Claimants shall be made whole for the work in question on February 18, 21 and 26,
2004.
Claim sustained.
Page 5
PLB 7101
Case No. 9
AWARD
Claim sustained.
Steven
Digitally
signed by Steven Bietig
Bie
rig
Steven M. Bierig
Chairperson and Neutral Member
Dominic Ring
Carrier Membe
,0%6
5-- #7 Dq
Dated at Chicago, Illinois this 6`d day of May 2009.
Roy R~binson
Organization Member