. ". PUBLIC LAW BOARD NO. 76
BROTHERHOOD OF MAINTENANCE OF WAY EMPLOYES
vs.
MISSOURI-KANSAS-TEXAS RAILROAD COMPANY
STATEMENT OF CLAIM:'
1. The Carrier violated the effective Agreement when on or about
August 15, 1961 it assigned the work of framing a building 8' x 12, to
and outside.contractorwhose employes hold no seniority rights under the
provisions of this Agreement.
2. The employes holding seniority in the Bridge and Building Department,
Seniority District No. 4, the old North Texas District; namely, R. C. Curry,
Foreman; J. W. Henderson, Mechanic; Anton Matz, Lead Mechanic; A. F. Davis,
Mechanic, and Larry Grossman, Mechanic, each be allowed pay at their respective
straight time rate for an equal proportionate share of the total man hours
consumed by the contractor forces in performing the work referred to in
Part 1 of this claim.
OPINION Or BOARD: At the outset Carrier challenges the jurisdiction of this Board
to consider the present claim. It contends that the claim is barred because proceedings were not instituted with the Third Division of the National Railroad
Adjustment Board (from which this Docket was withdrawn for presentation to Public
Law Board No. 76) within the time limit fixed by Article 5 Section 1 (c) of the
August 1954 National Agreement. That Section requires that proceedings be instituted with the National Railroad Adjustment Board within nine months after the
claim is declined by the highest officer of the Carrier. The present claim was
declined by Carrier's highest officer, authorized to handle such claims, on January
12, 1962. On October 4, 1962, H. C. Crotty, President of the Maintenance of Way
Employes, wrote a letter to the Executive Secretary*of the Third Division stating
p~r3-7Lo
-RWL3
that-the Organization intended to file an ex parte submission within 30 days. The
submission was filed after October 12, 1962 (more than nine months after denial of
the claim). Carrier contends that such notice of intent to file a submission is
not a petition and statement of facts with supporting data as required by Section
3
(i) of the Railway Labor Act and does not 'constitute an institution of proceedings
as required by that Section. This same procedural defense was raised by Carrier in
Docket No. 2 and in Award
No.
2 we held, as have many Third Division awards, that
the argument has no merit. We hold again, therefore, that the notice of intent to
file a submission did constitute an institution of proceedings before the Third
Division within the nine months time limit, giving the Third Division jurisdiction
over the matter. It necessarily follows that the claim is properly before Public
Law Board No. 76.'
We turn now to a consideration of the merits. On or about August 15, 1961
Carrier purchased from Cole Construction Company of Denison, Texas, a small frame
building, 8 feet wide, 12 feet long and 8 feet high for use at Dallas as an office
by the Missouri-Kansas-Texas Transportation Company (a wholly owned subsidiary of
Carrier). The building had been constructed by the Cole Company in its Denison
shop according to specifications supplied by Carrier. It was delivered complete
in all details (including hardware, paint, gas outlet and electrical wiring) to
Carrier.in Denison, placed on one of its cars and transported, to Dallas. Upon
arrival it was unloaded by employes who are claimants here and placed by them
upon the foundation which they had built.
The Organization contends that the work of constructing buildings of the
type involved is work belonging to Bridge and Building Department employes and that
by having the building constructed by employes of the Cole Company even though off
of the Carrier's property, Carrier violated the Scope and Seniority Rules of the
Agreement.
The Organization has argued that this.is not-a case involving the purchase
- 2 -
of
a
building, but rather one involving the contracting out of work to an outsider.
We do not agree. We think the record is clear that Carrier did purchase a completed building although it was not a stock item. We find nothing in the Agreement
which would restrict or limit Carrier's right to purchase such a building. Certainly
the Organization has pointed to no specific rule which grants to the employes an
exclusive right to,construct such buildings.
Various awards of the National Railroad Adjustment Board have upheld Carrier's
right to purchase items manufactured to its specifications. Award 2192 - Second
Division (Compressors;, the Referee said that the compressors were not the property
of Carrier at the time the work was performed and therefore the work claimed was not'
work of Carrier); Award 1990 - Second Division (prefabricated sides for hopper cars
manufactured to Carrier's specification; the Referee said that before the parts
were assembled the car sides did not become the property of Carrier and employes werenot deprived of any work to which they were entitled). In that case Carrier was
merely
purchasing the
completed car sides. In our case Carrier was purchasing a
completed building although it had specified the dimensions. One of the best state- -
ments of the principle is found in Award 5044 of the Third Division. Referee Carter
said: "The equipment was never purchased and delivered on the property of Carrier
for use until after the work claimed had been performed 'at the factory. The rights
of employes never attached until the carrier acquired possession of it . . .~ We -
fail to see, however, that a purchase of new equipment, in whatever form it may
exist, can constitute a farming out of work under the Agreement for the fundamental
reason that it never, had been under the Agreement. That which was never within the
Scope of an Agreement cannot be farmed out."
The Organization has sought to make a distinction between a building already
fabricated (in stock) and one which is made to specifications of Carrier, stating
that in the latter instance Carrier is contracting out specific work. We see no
merit in the distinction and it has been rejected by the Awards listed above. The
QL:(3
'1 6 - A&AJ ~ 3
,,important thing is whether the work was done before purchase by Carrier was completed. Here it was.
In our view, neither of the rules relied upon by the Organization have any
application to work performed by some manufacturer upon a structure before .the
structure becomes the property of the railroad. While the building in this case
was being constructed, the work performed was not work of Carrier and the present
Agreement cannot give the Maintenance of Way employes any right to it. We find no
violation of the Agreement. .
AWARD
The Claim is denied.
Public Law Board No. 76
I
Roy R. Ray
Neutral Member and Chairman
A. J.J/Cunningham U A. F: Winkel
Employe Member Carrier Member
Dallas, Texas
June 19, 1968.