Special Board of Adjustment No. 1016
PARTIES TO DISPUTE:
Brotherhood of Maintenance of Way
Employees
and
Consolidated Rail Corporation
STATEMENT OF CLAIM:
"(1) The Agreement was violated when outside forces were
used to construct 'Trail Van' buildings at Buckeye
Yard from September 27, 1985 to November 27, 1985
(System Dockets CR-2267, CR-2269, CR-2271, CR-2273
and CR-2274).
(2) The Carrier also violated the Agreement when it
did not give the General chairman proper advance
written notice of its intention to contract out
said work.
(3) Because of the aforesaid violations, Messrs. J.K.
Lafferty, R.N. Williams, S.A. McDade, C.T. Julian
and M.G. Carmean shall each be allowed three
hundred fifty-two (352) hours of pay at their
respective straight time rates."
FINDINGS:
It is
Petitioner's position
that carrier used an outside
firm to perform work belonging by agreement to Carrier's
Maintenance of Way employees. Charges of that nature are
extremely serious since wrongful subcontracting may undermine
1
IDItp-22.
the collective bargaining agreement and in some instances,
render its benefits illusory.
The critical question in subcontracting cases is whether
the charges are supported by substantial competent evidence.
General assertions and suspicions are not, of course, to be
equated with competent proof. Particularly in subcontract
cases, involving as they often do heavy liability, it is
important that these elementary principles be heeded. We
emphasize this point because it is still not uncommon in the
cases that come before us to find that they are lost by one
party or the other because of a lack of evidence.
The work involved in the present case concerns the
construction of four new buildings and an intermodal
(Trailran) yard facility at Carrier's Buckeye Yard in
Columbus, Ohio. That construction work was required in
order to replace Carrier facilities at East Columbus that
were being displaced by a new interstate highway. The
overall cost of the project, which was paid for by the
State of Ohio, amounted to $13.5 million dollars.
Construction work is mentioned in the Scope Rule. That
provision covers Maintenance of Way employees
"engaged in work generally recognized as Maintenance
of Way work, such as, inspection, construction, repair
and maintenance of water facilities, bridges, culverts,
buildings and other structures, tracks, fences and
roadbed, and work which, as of the effective date of
this Agreement, was being performed by these employees."
2
inicP-2g .
With respect to subcontracting, the following procedure
is prescribed in subsequent provisions of the Scope Rule:
"In the event the Company plans to contract out
work within the scope of this Agreement, except in
emergencies, the Company shall notify the General
Chairman involved, in writing, as far in advance of
the date of the contracting transaction as is
practicable and in any event not less than fifteen
(15) days prior thereto. "Emergencies" applies to
fires, floods, heavy snow and like circumstances."
"If the General Chairman, or his representative,
requests a meeting to discuss matters relating to
the said contracting transaction, the designated
representative of the Company shall promptly meet
with him for that purpose. Said Company and
organization representatives shall make a good
faith attempt to reach an understanding concerning
said contracting, but, if no understanding is
reached, the Company may nevertheless proceed with
said contracting and the organization may file and
progress claims in connection therewith."
Carrier was placed on notice in 1984 that the State of
Ohio planned to construct the new interstate highway which
would intersect yard facilities at Buckeye Yard. It was
also informed at that time that it would have to relocate and
reconstruct buildings, structures and tracks and that 13.5
million dollars would be allocated by Ohio for that purpose.
By letter of October 5, 1984, Carrier notified General
Chairman Dodd that it was contracting out the work.. That
letter reads as follows in its entirety:
"The State of Ohio is planning a new highway IR 670
through the area of our Store Department and Intermodal
Facility at East Columbus, Ohio.
3
ID
~t~-2a'
The State is paying to contract new facilities at our
Buckeye Yard at a cost of $13.5 Million.
Track work will be done by Conrail forces.
Grading, building, paving and lighting will be done by
Contract.
All B&B forces on the Columbus Division will be
maintained while the contract covering B&B work
proceeds.
If you wish to confer please advise by October 20,
1984."
General Chairman Dodd replied as follows:
"This letter is in response to your letters of
October 5, 1984 regarding the contracting out of
MW work in the Southern Region. The work referred
to was a side track extension at Vandalia, IL and
construction of new facilities at Buckeye Yard,
E. Columbus, OH.
I wish to confer with you concerning both sites.
Please contact my office to arrange a time and date
for our conference."
In line with the General Chairman's request, a
conference was held on October 31, 1984, in order to discuss
the matter. The meeting was attended by Mr. Dodd and Chief
Engineer Clark, the Carrier official who had signed the
letter of October 5.
Petitioner contends that it was not notified in timely
fashion that Carrier was contracting out the work. In that
regard, it relies on General Chairman Dodd's statement that
Mr. Clark informed him at the October 31, 1984 conference
that Carrier was already committed to contract out the
4
ID I (P-2-%
construction of the facilities in question and was unwilling
to alter those plans. In Petitioner's view, carrier was only
trying to give the impression of compliance with the
prescribed procedures while having violated the letter and
spirit of the Scope Rule by prematurely contracting the work
to outside forces.
Petitioner also contends that Carrier's letter of
October 5, the first notice Carrier had given to Petitioner ,
of its subcontract plans, was nothing more than "a blanket
notice," the equivalent of "no notice at all." Petitioner
points out that the October 5 letter did not identify the
specific work and dates and times it would be performed.
while the claim was under consideration on the property,
Carrier denied the claim for the following reasons:
1. It complied contractually by advising General
Chairman Dodd of the intent to contract the new
facilities at Buckeye Yard.
2. The Scope Rule was not violated.
3. The claims failed to give essential facts such as a
descriptive nature of the work involved, definite
dates and hours of work performed on each such day.
The vagueness and indefiniteness of the claim is
fatal.
5
I't7f Lo-2-?3
4. Claimants were on duty and under pay on the dates
claimed, and suffered no monetary loss. There is no
penalty provision in the Agreement. Claimants
therefore are not entitled to the compensation
claimed under any circumstances.
Carrier's fourth objection, just mentioned, is
unimpressive. In order to preserve the integrity of the
agreement and enforce its provisions, liability may well flow
from wrongful contracting out of work, even if claimants were
on duty and under pay when violations occurred. The point
will be discussed in depth if a violation is found in the
present case.
The third objection raised by Carrier is frivolous for
the claim letters apprise Carrier of the nature and basic
facts of the employees' complaint and Carrier has the best
access to all the details in this situation.
With respect to the first objection to the claim,
Carrier denies that the organization was ever told on October
31; 1984, that it had committed itself to contract out the
work. While General Chairman Dodd stated that he had been so
advised by Chief Engineer Clark, his statement stands alone
and is uncorroborated by evidence. On the other hand,
carrier's position is supported by evidence that the contract
was not executed until July 24, 1985 and actual work on the
6
D lip- Z,9
project did not start before September 1985. The facts
presented by Carrier in rebuttals were not untimely
submitted; Mr. Dodd's statement was first made to Carrier by
letter of March 4, 1987 and the Organization listed the case
with our Board just a few days later, on March 12. Carrier
was entitled to reply to a newly raised issue that had been
presented until near the close of discussions on the
property.
Accordingly, we find no sound basis for concluding that
Carrier had informed Petitioner that it was committed by
October 31, 1985, when the parties first met regarding the
matter to contract out the work. Nor does the record
establish that Carrier declined to explore in good faith with
Petitioner alternative possibilities or to furnish details
requested by Carrier. This is not a situation where the
first notice was given to the Organization just a short time
before work started or the project contract was signed.
Ample time was available for Petitioner to attempt to clarify
particulars and persuade Carrier to use its own forces to
perform the work.
In this setting, we are not persuaded that the notice
given to Petitioner was inadequate or that it was deprived of
an opportunity to explore the situation in a meaningful way
with Carrier. Nor are we persuaded that the Scope Rule has
7
fDi(o-29
been violated in any other respect. The record does not show
that claimants, all of whom were under pay and on duty during
the period in question, could have satisfactorily attended to
the work demands of this project which clearly was of major
dimensions. There is no indication that they had previously
been called upon to handle similar work under such
conditions. Awards that deal with much less complicated
projects and clear violations of the notice, meeting and
other requirements of the Scope Rule are to be distinguished
from the present case.
AWARD: Claim denied.
Adopted at Philadelphia, PA
a
~~ , 1989
I
$arol eston; Chairman
- 'v
Ca ier Member Employee Member
8