PARTIES TO DISPUTE:




STATEMENT OF CLAIM:















FINDINGS:
This companion case of Award No. 28, the lead case, and Awards 29 and 30, concerns the claim that Carrier used an outside firm to install culverts at Fisher Road in Columbus, Ohio. The work was a relatively small part of a $13.5 million project to replace Carrier facilities that were displaced by construction of an interstate highway. The 1


awards mentioned above dealt with other portions of the project. As in those other cases, all claimants were fully employed throughout the claim period.
What we had to say in Awards No. 28, 29, and 30 is equally applicable here. On that basis, this claim will be denied. In no measure is that decision based on Carrier's contention, unsupported as it is by evidence, that the work required special skills and equipment.

AWARD: Claim denied.

Adopted at Philadelp i,a, PA ~- a- , 1989

                Harold Weston, Chairman