This is another of the contracting out of work cases that resulted from the project to replace carrier facilities in East Columbus, Ohio, that were displaced by the construction of an interstate highway. No new factor has been presented in the present case that was not before this Board when it handed down Awards No. 28 (the lead case), 29, 30, and 31, all concerning different types of work performed in the project. No valid basis is perceived for following a different course here.


                                          )Dlcv-3


AWARD: Claim denied.

Adopted at Philadelphia, PAS- 8" , 1989