I
PROCEEDINGS BEFORE SPECIAL BOARD OF ADJUSTMENT NO. 1016
AWARD NO. 40
I Case No. 40
Referee Fred Blackwell
Labor Member: S. V. Powers Carrier Member: J. H. Burton
PARTIES TO DISPUTE:
BROTHERHOOD OF MAINTENANCE OF WAY EMPLOYEES
VS.
CONSOLIDATED RAIL CORPORATION
STATEMENT OF CLAIM:
Claim of the System Committee of the Brotherhood that:
(1) The Carrier violated the Agreement when it assigned outside forces (Iberia
Construction Company) to haul stone, grade the right-of-way and install culverts between
Mile Post 83.7 and Mile Post 95.5 in the vicinity of Marion, Ohio beginning October 20,
1986 (System Docket CR-2895).
(2) The Agreement was further violated when the Carrier did not give General Chairman
Dodd prior written notification of its plan to assign said work to outside forces.
(3) As a consequence of the violations referred to in Parts (1) and/or (2) above, the two
(2) senior track foremen, four (4) senior trackmen, four (4) senior machine operators and
nine (9) senior vehicle operators on the Columbus Division Seniority Rosters, who were
furloughed during the claim period, shall each be allowed one hundred twenty (120) hours
of pay at their respective straight time rates.
FINDINGS:
Upon the whole record and all the evidence, and after hearing on August 17, 1989,
in the Carrier's Office, Philadelphia, Pennsylvania, the Board finds that the parties herein are
Carrier and Employees within the meaning of the Railway LaborAct, as amended, and that this
FM &ADUM Board is duly constituted by agreement and has jurisdiction of the parties and of the subject
An
a tlw matter.
19129 FD" MY
agnIEAAURG. , 1
w20879
PM)
m-sm
I I
i
I;
I
SBA No. 1016 / Award No. 40 - Case No. 40
I
DECISION:
Claims sustained.
OPINION
This case arises from claims filed on behalf of nineteen (19) furloughed
Maintenance of Way Employees on the basis of allegations that the Carrier violated the
BMWE Scope Rule by improperly contracting with an outside contractor to haul stone,
grade the right-of-way, and install culverts between MP 83.7 and MP 95.5 in the vicinity
of Marion, Ohio, Columbus Division. The work, it is alleged, occurred on fifteen (15) claim
dates in October and November 1986, with each of nineteen employees of the contractor
I performing eight (8) hours of work on each claim date for a total of 120 man-hours each.
i
The contractor's work force was comprised of two (2) foremen, four (4) laborers, four
machine operators, and nine (9) vehicle operators; the foremen supervised the work; the
I
laborers performed laborer's work; the machine operators operated a backhoe, a Gradall,
a bulldozer, and a roller; the vehicle operators operated eight dump trucks and one flat
bed truck.
The Claimants are nineteen senior unnamed Employees in the job classifications
that were allegedly used by the outside contractor to perform the work, namely: two
foremen, four laborers, four machine operators, and nine vehicle operators.
The Organization contends that the claims are valid because the Carrier violated
no BLACPAU the Employees' Scope Rule in two respects: 1) the Carrier contracted out work secured
arMer a uw
19129
aoww
MY
GUTHEFSBURG.
wRYLWD
vets'
PM)
qnsooo l ;
i:
n
FETED BLACKVJELL
ATTORNEY AT LIW
19129 FOW1 MY
C~A(THSSBURG.
MARYLAND
2fIE79
(301i 9T7-5000
SBA No. 1016 / Award No. 40 - Case No. 40
to the Employees by the text of their Scope Rule, and 2) the Carrier did not comply with
the Scope Rule notice provisions that obligated the Carrier to give General Chairman Jed
Dodd prior written notification of the project.
The Carrier submits that the protested contracting out did not violate the
Agreement, and that the claims should be denied on that basis. The specific grounds for
the Carrier's denial of the claims, reflected in the Carrier's submission, are as follows.
1. The claims are procedurally defective, because the claims lack data that
would enable the Carrier to identify the unnamed Claimants.
2. On August 14, 1986, the Carrier notified General Chairman J. B. Cassese,
I who heads the Consolidated Rail System Federation, of its plan to contract out grading
and drainage work preparatory to the track construction phase of the Galion to Ridgeway,
Ohio, TCS project. Mr. Cassese took no exception to the contracting of the subject work,
and no claims for the work were submitted on behalf of Employees represented by his
I~
General Committee. This notice complied with the notice requirements of the Scope Rule
I
and the Carrier was not required to give notice also to General Chairman Jed Dodd, who
i
heads the Pennsylvania Federation.
3. The work in question was unusual and the required skills and equipment,
and Employees who were qualified to perform the work, were not available to the Carrier.
Also, the work project involved a considerable number of man hours.
4. The work of grading and hauling stone does not accrue to the Claimants by
,Agreement or past practice.
SBA No. 1016 / Award No. 40 - Case No. 40
5. Approving the claims for compensation would constitute the Board's
(assessment of a penalty against the Carrier, which the Board has no authority to do in
the absence of an Agreement provision so providing.
From full review and assessment of the foregoing, in the context of the whole
record, the Board finds and concludes that the confronting claims have merit and that the
i Carrier's position is not supported by the record.
More particularly, the subject work is within the purview of the text of the BMW
Scope Rule that makes specific reference to
"work
generally recognized as Maintenance
I
of Way work, such
as,...construction, repair and maintenance of ..culverts...tracks...and
The Board finds that in view of this express coverage of the subject work by the
confronting Scope Rule, the Carrier's action in contracting the subject work violated the
(,Scope Rule. The Board further notes that the Organization stated at the hearing on this
i
case that the request for compensation is limited to Claimants represented by the
Pennsylvania Federation; therefore, subject to this limitation, the claims are deemed
meritorious and compensation will be awarded as hereinafter provided on the basis of the
Carrier's violation of the Scope Rule. It is also noted that the Hopkins-Berge Letter of
Agreement dated December 11, 1981, has been omitted from the considerations of this
dispute. Said letter was held not applicable on Conrail in this Board's
Award No. 66-A
FRED BLACKWELL
executed on January 18, 1993.
ATTORNEY AT LAW
P.O. BOX 60% 4
WEST COLUMBA
SC.29171
(8031791-8096
i, I
ai
i
SBA No. 1016 / Award No. 40 - Case No. 40
ACCORDINGLY, based on the whole record, the claims will be sustained. This
Finding disposes of the claim; therefore, the Board finds it unnecessary to discuss or rule
on the Organization's allegations that the Carrier violated the notice provisions of the
Scope Rule.
I,
,I
Fred Blackwell
Chairman/Neutral Member
Special Board of Adjustment No. 1016
i
w
jiJanuary 9, 1995
ii
il
IFRED BLACKWELL
ATTORNEY AT
LAW
P.O. BOX 6095
5
WEST COLUMBIk
S.C. 79171
1803) 791.eoes
SBA No. 1016 / Award No. 40 - Case No. 40
The Carrier violated the Scope Rule.
The claims are hereby sustained on the basis that the Carrier is directed to
compensate the herein Claimants represented by the Pennsylvania Federation in accord with
i the compensation requested in said claims.
BY ORDER OF SPECIAL BOARD OF ADJUSTMENT NO. 1016
ii;
Fred Blackwell, Neutral Member
l
S. V. Powers, Labor Member . . Burton, Carrier Memb
ii
I dissent because this Award is
i' erroneous in light of Award 29
~~Executed on ,1995
of SBA
1016
involving the same
kind of work and Third Division
Award 29187 involvinsz notice to
i the involved General Chairman.
' Conrail\ 1016\40-40.109 -
FRED BLACKWELL
ATTORNEY AT LAW
P.O. Box sons
WEST COLUMBIA,
S.C.29171
(9031791-X86