PROCEEDINGS BEFORE SPECIAL BOARD OF ADJUSTMENT NO. 1016
AWARD NO. 43
Case No. 43
Referee Fred Blackwell
Labor Member: S. V. Powers Carrier Member: J. H. Burton
PARTIES TO DISPUTE:
BROTHERHOOD OF MAINTENANCE OF WAY EMPLOYEES
VS.
CONSOLIDATED RAIL CORPORATION
STATEMENT OF CLAIM:
Claim of the System Committee of the Brotherhood that:
(1) The Carrier violated the Agreement when it assigned outside forces to cut brush, clear
brush and pick up ties on the right-of-way on the Richmond Branch of the Philadelphia
Division beginning August 4, 1986 (System Docket CR-2944).
(2) The Carrier also violated the Agreement when it did not give the General Chairman
advance written notice of its intention to contract said work.
(3) As a consequence of the violations referred to in Parts (1) and/or (2) above, each
employe holding seniority rights on the Philadelphia Seniority District Vehicle Operator and
Trackman rosters shall be allowed pay at their respective rates for an equal proportionate
share of the total number of man-hours expended by the outside forces performing the work
referred to in Part (1) above.
FINDINGS:
Upon the whole record and all the evidence, and after hearing on August 17,1989, in the
Carrier's Office, Philadelphia, Pennsylvania, the Board finds that the parties herein are Carrier
and Employees within the meaning of the Railway LaborAct, as amended and that this Board
is duly constituted by agreement and has jurisdiction of the parties and of the subject matter.
FRED BLACKWELL
ATTORNEY AT LAW
19129 ROM WAY
GARHERSBU(G, 1
MARYLAND 2D979
 
P01) 983099
I
SBA No. 1016 / Award No. 43 - Case No. 43
DECISION:
Claims sustained as hereinafter provided.
OPINION
This case arises from claims filed on behalf of each Employee holding seniority
rights on the Philadelphia Seniority District Vehicle Operator and Trackman Rosters, on
the basis of allegations that the Carrier violated the BMWE Scope Rule by improperly
contracting with an outside contractor to cut brush, clear brush, and pick up ties on the
right-of-way on the Richmond Branch of the Philadelphia Division, beginning August 4,
1986, and by failing to comply with the requirement that the Carrier give the General
Chairman advance, written notice of its intention to contract the brush cutting work. The
Organization alleges that beginning on August 4, 1986, the outside concern (JMG
Excavating Co.), used three (3) high rail dump truck drivers and six (6) laborers to cut
brush and clear the right-of-way on the Richmond branch.
The Organization submits that the disputed work is encompassed within the
express, explicit text of the scope of the Agreement; that the disputed work of brush
cutting is also brought within the scope of the Agreement by the Agreement provisions
in paragraphs 1 and 5 concerning past practice; and that the Carrier failed to comply with
the Scope Rule requirements to give the General Chairman advance notice of is intention
to contract out the disputed work.
The Carrier submits that its action in contracting out the brush cutting work did not
ATTORNEY AT LAY
19128 ROMAN VWY
OARHERSBt1N<i,
MARYLAND 29979
p91) 977-5999
  
Class 3 and Class 2, operating Brush Cutter machines and Brush Cutter (on track)
  
machines, and rail-highway vehicles. In addition, paragraph 5 of the Scope Rule provides
  
that work which was being performed by Maintenance of Way Employees on the effective
  
date of the Agreement (February 1, 1982) is within the Scope of the Agreement.
  
Employees statements included in Employees' Exhibit A show that the Maintenance of
  
Way forces have performed brush cutting work on the Carrier's right of way for many
  
years before the execution of the current contract in February 1982.
   
There is thus no question that the subject work involved in this case is
  
encompassed within the text of the BMWE Scope Rule.
   
Accordingly, as noted previously, the Board finds that the Carrier action of
  
contracting the disputed work violated the work jurisdiction provisions of the BMWE
  
Scope Rule. Therefore, consistent with this finding, the precedential authority of Thir
  
Division Award No. 27333 
(08-30-88), Third Division Award No. 27185 (06-30-88), and the
  
doctrine of Stare Decisis, the Carrier will be held accountable for this violation as
  
hereinafter provided.
   
The Carrier also violated the paragraph 2 provisions in the Scope Rule that required
 
KTORNFY AT WV 
the Carrier to give the General Chairman notice of the Carrier's intent to contract the
 
18129 ROMAN VAY
 
GmRtieSBm~   4
 
MARYLAND 20979
 
pml 9n-s9oo
SBA No. 1016 / Award No. 43 - Case No. 43
brush cutting work.
The Carrier's contention that exclusivity applies to this dispute, and hence notice
to the General Chairman was not required, has been considered and rejected in prior
Third Division Award No. 27012 (04-25-88) on 
a dispute between these parties. The
following extract from that Award is apropos to this dispute:
    
"The Board 
finds 
that the Carrier's 
insistence on 
an exclusivity test is not
   
well founded. Such 
may 
be 
the critical point in other disputes, 
such 
as
   
determining which class 
or craft of the Carrier's employees may be entitled
   
to perform certain work. Here, however, a different test is applied. The
   
Carrier is 
obliged to 
make notification where work to be contracted out is
   
`within the 
scope' of the Organization's Agreement. There is no serious
   
contention that 
brush cutting work is not properly performed 
by Maintenance
   
of Way employes, even if not at all locations or to the exclusion of other
   
employees. As 
emphasized by 
the Organization, the Carrier failed to make
   
any 
notification to 
pny Organization." (Emphasis added in original)
   
For a ruling that treated Award 
No. 27012 
as controlling precedent, see Thir
  
Division Award 
No. 27014 (04-25-88).
   
Inasmuch as the facts and issues in 
Third Division Award 
No. 27012 
are analogous
  
to the facts and issues in the confronting dispute, the Carrier contention in this dispute
  
concerning exclusivity is rejected on the basis of the precedential authority of Third
  
Division Award 
No. 27012.
   
In view of the Carrier's violations of the work jurisdiction and the notice provisions
 
FRED KXKWELL 
of the Scope Rule, a remedy is in order. As to the form of the remedy, the Board
 
ATTORNEY AT LAW
 
19129 ROMAN WAY
 
GAMBUNG~    5
 
MARYLAND 20979
 
13071977-soon
SBA No. 1016 / Award No. 43 - Case No. 43
recognizes that no Maintenance of Way Employee was on furlough on the Philadelphia
Division during the period of the brush cutting contract; the Board is also aware that
Boards generally exercise restraint in awarding compensation to Employees who are on
duty and under pay during the time of the performance of Agreement work by an outside
contractor, even where, as here, the award is not only for lost work opportunities, but also
has the purpose of enforcing and preserving the integrity of the Agreement. The Board
also notes that, so far as the record shows, the claims are open-ended without a closing
date on the alleged liability of the Carrier to compensate the Claimants.
In balancing these factors with one another, the Board concludes that a
compensatory award is an appropriate remedy in this case but that the compensation
should be subject to a ceiling. Therefore, based on the record as a whole, the Claimants
will be awarded compensation at their respective rates for an equal proportionate share
of the total number of man-hours expended by the contractor's work force in the
performance of the protested brush cutting work covered by the BMWE Scope. The said
compensation will be based on the number of actual days worked by the contractor's
work force subject to a ceiling of a maximum of twenty (20) work days. This finding
concerning the quantum of the compensation to be awarded shall not be a precedent in
any future dispute except where the facts and issues are analogous to the facts and
issues of this dispute.
ACCORDINGLY, based on the whole record, the claims will be sustained as
RED BWKWU
hereinafter provided.
19128 ROMAN MY
6
MARYLAND 20879
PM) Ta-W
SBA No. 1016 / Award No. 43 - Case No. 43
Fred Blackwell
Chairman/ Neutral Member
Special Board of Adjustment No. 1016
April 12, 1994.
FRED BWKWELIL
ATTORNEY AT 
LAN
19129 ROMAN WAY
GARN6iSBURG, 'j
MARYLAND 20979
 
(307) W-5000
SBA No. 1016 / Award No. 43 - Case No. 43
AWARD
The Carrier violated the work jurisdiction provisions and the notice provisions of the
confronting Scope Rule. Accordingly, the claims are hereby sustained and the Carrier is
directed to pay the Claimants compensation at their respective rates for an equal
proportionate share of the total number of man-hours expended by the contractor's work
force in the performance of the protested brush cutting work covered by the BMWE Scope.
The said compensation will be based on the number of actual days worked by the
contractor's work force subject to a ceiling of a maximum of twenty (20) work days.
Jurisdiction is retained for the Board to consider questions concerning the
implementation of this Award, which are submitted in writing and received in the office of
the undersigned within sixty (60) days from the date hereof.
BY ORD R OF SPECIAL BOARD OF ADJUSTMENT NO. 1016
 
Fred Blackwell, Neutral Member
S. V. Powers, Labor Member 
.-$. 
Bon, Carrier Member
Executed on 
s 
- , 1994
Conrail\1016\43-43.412
 
FRED BLACKWELL
 
ATTORNEY AT LAW
 
18129 ROM MY
 
GADHEMRG~ 8
 
MNRYLAND 20879
 
po119n.sw