As a consequence of the violations referred to in Parts (1) and/or (2) above, Claimants C,L, Daub, G.A. Golden, J.L. Royer and M.D. Tallarida shall each be allowed eight (8) hours' pay at the applicable straight time rate for each day the contractor forces performed fence construction work on December 21, 22, 23, 26, 28, 29, 30 and 31, 1992 and January 4, 5, 6, 7, 8, 9, 11 and 12, 1993. Claimant J.H. Love shall be allowed eight (8) hours' pay at the applicable straight time rate for each day the contractor forces performed fence construction work of January 4, 5, 6, 7, 8, 9, 11 and 12, 1993.
|
|