SPECIAL BOARD OF ADJUSTMENT NO. 1049
AWARD NO. 162
Parties to Dispute:
BROTHERHOOD OF MAINTENANCE OF WAY EMPLOYES
AND
NORFOLK SOUTHERN RAILWAY COMPANY
(Carrier File MW-CN-04-10-SG-153)
Statement of Claim:
Claim on behalf of the members of the TS-2 Timber and Surfacing Gang requesting that they each
shall be allowed six hours and thirty minutes overtime pay, in that they worked beyond their
regularly scheduled ten hours shift on certain days during the week of April 12, 2004, but were
released early at the end of the week as opposed to being compensated at the overtime rate.
Upon the whole record and all the evidence, after hearing, the Board finds that the parties herein are
Carrier and Employee within the meaning of the Railway Labor Act, as amended, and this Board is
duly constituted by agreement under Public Law 89-456 and has jurisdiction of the parties and
subject matter.
AWARD
After thoroughly reviewing and considering the transcript and the parties' presentation, the Board
finds that the claim should be disposed of as follows:
BACKGROUND
The record in this case shows that employees working on the TS-2 Timber and Surfacing gang
acknowledged, in writing, their desire to extend their normal working hours on Monday, Tuesday
and Wednesday under a make-up arrangement that would permit them to leave work early each
Thursday in order to travel home for a long weekend. The majority of employees expressed their
voluntary consent to this arrangement, and clearly understood that any additional time worked on
Monday, Tuesday or Wednesday would be used for make-up time for any regularly assigned hours
not worked each Thursday. The Gang worked a four ten-hour workday schedule pursuant to Article
I
X, Paragraph (b), Alternative Work Week and Rest Day Rule of the February 6, 1992 Imposed
Agreement covering production crews. It is undisputed that the total number of hours of make-up
time worked outside their regular 10-hour workdays between Monday and Wednesday was less than
the eight hour maximum permitted by the rule and were applied to the 10-hour workday each
Thursday during the claim period. Accordingly, it is clear that the gang completed their forty hours
of work for the workweek during the period April 12 through April 15, 2004, and was able to work
less than the 10-hour day on Thursday due to the fact that they had made up the time.
DISCUSSION
In this non disciplinary claim, it is the Organization's burden to demonstrate that there was a
genuine lack of consensus to the make-up time arrangement. Respectfully, given the undisputed
facts noted and detailed above, the Organization has failed in its burden. Accordingly, the claim
must be dismissed for lack of sufficient evidence.
CONCLUSION
The claim is dismissed.
r
ZD 7. am gna
ind Neutra ember
Dff,~olomay D.E. Kerby
Organization Member Carrier Member
Dated: July 31, 2007,
2