SPECIAL BOARD OF P-DJUSTMENT N0. 1063
Case No. 12
Award No. 12
PARTIES TO DISPUTE:
Brotherhood of Locomotive Engineers
and
Norfolk Southern Railway Company
Norfolk and Western Railway Company, et al.
STATEMENT OF CLAIM:
Claim of Pocahontas Division Engineer J. L. Chapman for
removal of 10 days deferred suspension and pay for all time lost.
OPINION OF BOARD:
On August 24 1991, Claima== was assigned as Engineer to Crew
U34 which was scheduled to wor_s at Amonate Mine. in the course of
doubling 38 loads to 19 loads or. the Front Track it was necessary to
make several attemvts to effect a coupling on a 1.5°e grade. Just
how many attempts, is one of the many questions left unanswered by
the transcript. In any event, on August 26. 1991, the Carrier first
became aware of burnt rails at the site of the Amonate Mine. Unon
investigation it was reported there were five separate burn marks on
both the north and south rails, each of which nearly matched the
burns on the opposite rail, which required 97' of new rail on the
south track and 84, of new rail on the north track. Following
discussion with the crew members of Crew U34, a formal investigation
was convened to determine Claimants responsibility, if any, for
damage to rail at Amonate Mine on August 24, 1991. Claimant was
found guilty as charged and assessed 10 days deferred suspension.
In the course of the investigation the Carrier witness testified
that Claimant admitted to him that he had damaged the rail at
Amonate. The Claimant denied this assertion at the trial. The
Claimant did admit to making two attempts to move the train but in
his words, "ran into a stone wall." The Conductor states that
possibly three attempts were made. The number is significant
because the inspection by the Assistant Supervisor of Tracks
disclosed five separate burn marks of various lengths and depths.
incriminating evidence points to Crew U34 as the responsible party
as there was no proof of another crew being in the vicinity of
Amonate Mine during the period in question. Thus, it becomes a
question of determining the truthfulness and credibility of the
various witnesses, which as we have stated marv times, is a function
of the Trial Officer. Unfort-inately the TrialyOfficer offered a
disclaimer
saying:
"I 'm not here to determine anvone'5 credibility.
71m
here t0 °_°t the =acz3."
SBA No. 1063 _
Case No. 12 -
Award No. 12
Thus, in this particular case and for the reasons alluded to, we are
constrained to make those determinations which normally reside with
the Conducting Officer.
It is auparent the Carrier's primary witness was relying upon a
statement which was allegedly made to him by Claimant several days
after the incident but presumably in the presence of other witnesses
including Engineer B. E. Burl^.ette. That testimony follows:
"At approximately 2:30 p.m. on that same date of
August 26th, 1991, I -as _n the process of leaving
the Yard Office with the u36, Mr. J. L. Chapman.
Mr. Wright and Mr. Ode:. =o relieve out U34, and as
we were in the process of l=eaving Yard Office, we
were met by the U35. ~~nd'_ctor D. A. Sanders,
Engineer 3~. L. Burn=tt°_, and Brakeman. I then
approached Mr. Burnett=_ a=d asked him how bad was
the track damaged at :1=mate Mine and he told me it
was damaged bad. At that time, Mr. Chapman said:
Mr. Stepp, sir, Saturday, at approximately 12:05,
while I was in the F=_nt T:ack at Amonate, I burnt
the rail a=proximately2 feet. and I said: Mr.
Chapman, a=a you tell-_-= me that you damaged the
rail at Amonate? He said: yes sir. I said: sir,
is this the first time t=at you have made this ...."
The Claimant categorically denies this testimony and in fact,
accused Carrier's witness cf lying. The Conductor appeared at the
trial and his testimony corroborates that of the Claimant more or
less. No attempt was made to call Engineer Burrette by either side
which appears rather strange since he was supposedly
in
the area
when Claimant offered his unsolicited confession of guilt. The plot
thickens further when it was revealed the Carrier's primary witness
was not aware Claimant and his crew were at the Amonate Mine the
following day, i.e., Auz.ist - doing shifting, apparently without
incident. This is prett-l r?mar_kable considering the testimony of
the Assistant Track Super-7'_so= who stated "I've been at this job for
20 months and this is the worst engine burns I've seen."
Sorting out the facts in t._is case has been a compelling
challenge. The Carrier has the burden to prove by substantial
evidence the truth of the c=argos. We are no= entirely satisfied
they have met this burden. CC=erSely, we are not certain Claimant
didn't contribute SCme
of
t_... :.',_ - ma=_CS -round on tae rn4l aI t
the evidence
15
more ~irC'f~S~t=a- than direct. Under the
circumstances we feel a
Rot=_~=C
-.laced on Claimant's record will
m_,d
hem
^c_ i i°_
'eceSS_t f -z -arer'11_--l mcn_toring tine engine
Deff_rmanC°Cf the Un_ts ll'-e-
___S
C:onz=Ol and we will expunge the
10 d=-.;-
deferred S
'_S-e.^.S '_^.^_.
SBA No. 1063
Case No. 12
Award No. 12
FINDINGS: The Agreement was violated.
AWARD: Claim Sustained.
ORDER: The Carrier will make the Award effective within thirty (30)
days of the effective date.
Dated at Norfolk, Virginia, this / Sdday of
/l , 1993
.
'~ F.
Euker, Neutral Member
S.'R. Budzind Carrier Member
-1 i
E. E. Watson, Organization Member
Carrier File: EE-RI-91-2
Or.7. File: D-448-91-2