SPECIAL BOARD OF ADJUSTMENT 1110
Award No. 113
Case No. 113
PARTIES TO DISPUTE:
Brotherhood of Maintenance of Way Employees
and
CSX Transportation, Inc. (formerly The Baltimore
and Ohio Railroad Company)
STATEMENT OF CLAIM:
Claim of the System Committee of the Brotherhood that:
1. The Agreement was violated when the carrier assigned
outside forces (Marta Construction) to perform Maintenance
of Way work (surface and adjust existing track) between Mile
Posts 127.0 and 128.5 at Garret, Indiana and assigned
outside forces (Midway Construction) to perform Maintenance
of Way work (ditching and dozing) between Mile Posts 115 and
124 on March 27, 28, 29, April 3, 4, and 5, 1998, instead of
assigning Messrs. G. A. Skelly, R. N. Tucker, T. L. Klink,
C. L. Murphy and R. A. Coppus [System File B-TC-2935/12(98
1033) BOR].
2. The Agreement was further violated when the Carrier
failed to provide the General Chairman with proper
advance written notice of its intent to contract out
said work as required by Addendum 13.
3. As a consequence of the violations referred to in Parts
(1) and/or (2) above Claimants G. A. Skelly, R. N. Tucker,
T. L. Klink, C. L. Murphy and R. A. Coppus shall now be
compensated "for sixty-six (66) overtime hours each
...."
FINDINGS:
This Board, upon the whole record and all of the evidence, finds
and holds as follows:
1. That the Carrier and the Employee involved in this
dispute are, respectively, Carrier and Employee within the
meaning of the Railway Labor Act, as amended,; and
2. That the Board has jurisdiction over this dispute.
1
SU IM)
pwd 113
OPINION
OF THE BOARD:
The Scope Provision provides, in pertinent part, that:
(a) These rules govern the hours of service and working
conditions of all employees in the Maintenance of Way and
Structures Department, and the following classes of employees in
the Transportation Department, subject, however, to the
exceptions provided in paragraph (b) of this rule:
Cleaning Gang Laborers (Baltimore Terminal).
Bridge Watchmen.
Crossing Watchmen.
Cut Watchmen.
Lampmen (Lamp Tenders).
Pumpers.
Water Treating Plant Attendants at other than engine
terminals.
Targetmen (except at Zanesville, Ohio).
(b) This Agreement does not apply to:
1. Bridge, Maintenance, Scale or Tunnel Inspectors.
Master Carpenters.
Track Supervisors and Assistant Track Supervisors.
General Foremen.
Other supervisory employees of equal or higher rank.
2. Clerical and Civil Engineering forces.
3. Signal Department forces.
4. Employees, as of the effective date of this agreement,
covered by agreements with other Labor Organizations.
5. (a) Work which is to be performed under contracts let by
the Company under any one or more of the following
circumstances:
1. By reason of the magnitude of the project.
2. Because of the requirement of special skills necessary
in connection with performance of the work.
3. Where equipment or facilities to be used in connection
with the work are not possessed by the Company and
available, consistent with requirements for a particular
project.
4. Where the work with Company forces would limit the
extent of the supplier's guarantee.
5. The time within which the work must be completed as
related to other projects.
6. Employees covered by the agreement on the seniority
district involved cannot be assigned to the work without
impeding the progress of other projects.
A careful review of the record indicates that the Carrier
provided advance notice to the Organization on April 14, 1997
concerning the plan to use outside forces to perform the disputed
work, which arose in connection with the construction of sections
of main line track in the corridor between Chicago, Illinois and
Cleveland, Ohio. At the request of the Organization, the Carrier
2
S6A 1110
At,d 113
provided additional information in a letter dated May 9, 1997.
The record demonstrates that the Carrier served the notice and
the supplemental information on the Organization. The record
therefore demonstrates that the Carrier provided the proper
advance notice to the Organization.
The record confirms that the advance written notice covered the
disputed work. In particular, the Division Engineer, P. M.
Tucker, provided additional information, in a letter dated June
13, 1998 during the handling of the Claim on the property, that
described the disputed work as "part of to the new construction"
initiated by the Carrier. Although the organization disputed
this description, the record developed on the property fails to
provide any basis to discredit, invalidate, or refute the
detailed information furnished by the Carrier. In this regard
the April 14, 1997 letter specifically referred to the Akron West
District and the Claimants hold seniority on the Akron West
Seniority District. As a result, insufficient credible evidence
exists to substantiate that a violation occurred under the
special circumstances reflected in the record.
AWARD:
The Claim is denied.
Robert L. Do as
Chairman and Neutral Member