SPECIAL BOARD OF ADJUSTMENT 1110
Award No. 95
Case No. 95
PARTIES TO DISPUTE:
Brotherhood of Maintenance of Way Employees
and
CSX Transportation, Inc. (former Chesapeake
and Ohio Railway Company)
STATEMENT OF CLAIM:
Claim of the System Committee of the Brotherhood that:
1. The Agreement was violated when the
Carrier assigned outside forces (Progressive
Railroading) to perform Maintenance of Way
work (tear out track, stock pile materials
and distribute same) and [sic] Mile Post
11.7, Lundale Two Mine on the Buffalo
Subdivision beginning April 20, 1996 and
continuing (System File C-TC-6368)/12(96
1188) COS].
2. As a consequence of the violation
referred to in Part (1) above, furloughed
employes T. Rakes, R. Rakes, D. Green, D.
Shelton and D. Hatfield shall each be allowed
eight (8) hours' pay at the trackman's
straight time rate and two (2) hours' pay at
the trackman's time and one-half rate for
each day the outside forces performed the
work in question beginning April 20, 1996 and
continuing until the violation ceased.
FINDINGS:
This Board, upon the whole record and all of the evidence, finds
and holds as follows:
1. That the Carrier and the Employees involved in this
dispute are, respectively, carrier and Employees within the
meaning of the Railway Labor Act, as amended,; and
2. That the Board has jurisdiction over this dispute.
1
5 16A H
to
OPINION
OF THE BOARD:
The record indicates that the Carrier complied with the
requirement to provide advance written notice to the organization
about the intent to use outside forces. Specifically, the record
substantiates that the Carrier provided the appropriate notice to
the Organization before the performance of the disputed work
began. In addition, the record reflects that the parties
discussed the matter in a timely manner.
Rule 83 concerns contract work and provides, in pertinent part,
that:
(b) It is understood and agreed that
maintenance work coming under the provisions
of this agreement and which has heretofore
customarily been performed by employees of
the railway company, will not be let to
contract if the railway company has available
the necessary employees to do the work at the
time the project is started, or can secure
the necessary employees for doing the work by
recalling cut-off employees holding seniority
under this agreement.
The record indicates that outside forces performed the disputed
work. The Carrier relied on an alleged Construction Contract as
an affirmative defense to the Organization's assertion that the
claimants should have received the assignment.
The record includes the referenced Construction Contract, which
had a date of October 12, 1995. The Contract provided, in
relevant part, described the work to be performed by the
Contractor:
Removal of rail, ties, and OTM from various
locations in Gauley Yard and Number 2 Mine
Tracks, Lundale, West Virginia. Proposal
"A", is accepted, CSXT retain items 1-A, 1-C,
2-B, 2-C and 2-E. Contractor retain
remainder of material.
2. Lundale, West Virginia (#2 Mine tracks)
A. Remove est. 21664 L.F. 130,# rail.
B. Remove est. 8592 L.F. 131/132#
rail.
C. Remove 7 - 132# turnouts.
D. Remove remainder track material &
OTM.
E. Remove 6000 relay ties, including
2
S l3A 1110
Awd 9,5
all switch ties.
F. Remove remaining ties.
The Construction Contract by its very nature reflects that the
carrier retained control of the relevant location and the
material located at the relevant location. As a result, the work
to be performed at the location constituted scope covered work to
the extent that the carrier ultimately retained any of the
material. In contrast, the material that the outside contractor
purchased and removed from the Carrier's property did not
implicate scope covered work.
Under these circumstances the Carrier violated the Agreement with
respect to those portions of the Construction Contract in which
the Carrier retained the specific items (2-B, 2-C, and 2-E). The
carrier did not violate the Agreement with respect to those
portions of the Construction Contract in which the Contractor
used outside forces to remove the items that the Contractor had
purchased from the carrier, namely, items 2-A, 2-D, and 2-F.
Consistent with certain cited precedent, the parties shall meet
to determine the proportion of the work relating to items 2-B, 2C, and 2-E of the Construction Contract. The Claim shall be
modified to cover the hours of work needed to perform such work
and the Claimants shall be compensated at their straight-time
rate of pay for this portion of the work that the outside forces
performed pursuant to the Construction Contract.
AWARD:
The Claim is sustained in accordance with the Opinion of the
Board. The Carrier shall make the Award effective on or before
30 days following the date of this Award.
Robert L. DouEflas
Chairman and Neutral Member
D nald Bartho a Mark D. Selbert
Employee ember Carrier Member