Claim of the System Committee of the Brotherhood that:
1. The Agreement was violated when the Carrier assigned outside forces (W. T. Byler Construction Company) to perform Maintenance of Way machine operator work (operate backhoes and trackhoes) in connection with switch and crossing installation work between Mile Post 37 in the vicinity of Rosenberg, Texas and Mile Post 120 in the vicinity of Flatonia, Texas beginning on July 20, 1998 through September 15, 1998 (System File MW-98-217/ 1160497 MPR).
2. The Agreement was further violated when the Carrier failed to furnish the General Chairman with proper advance notice of its intent to contract out said work or make a good-faith effort to reduce the amount of contracting, as provided in Article IV of the May 17, 1968 National Agreement and the December
By notices dated June 12, 1998 from Directors of Track Maintenance D. E. Pecaut and B. J. Waguespack, the Carrier advised the Organization of its intent to contract out certain work at specified locations including
... tie renewal, crossing renewal, drainage work and vegetation control" further specifying that "[e]quipment that could be used is backhoe, dumptruck, dozer, bushhog, chain saws, various types
cranes, and operators." TheSBA 1130, Award 22
M. R. Jatzlau, et al.
Page 2
Organization asserts that it was not in receipt of the complete noticed information until June 28, 1998. By letter dated June 30, 1998, the Organization requested conference be held. By letter dated July 10, 1998, the Carrier declined to meet in
It is the position of the Carrier that you are out of time to conference Service Order notices by Pecaut and Waguespack as the notices were given June 12. 1998 and your letter was not dated until over 15 days later, June 30. According to Article IV - Contracting Out, the Carrier must notify the General Chairman of contracting out at least 15 days prior thereto. Thus, the Organization has fifteen (15) days to dissuade the Carrier from contracting out. On several of these notices, the fifteen (15) days has expired. Therefore, the Carrier will not conference the two notices dated June 12, 1998.
The Carrier contracted the work. This claim followed.
Article IV of the 1968 National Agreement states in relevant part:
nated representative of the carrier shall promptly meet with him for that purpose. Said carrier and organization representatives shall make a good faith attempt to reach an understanding concerning said contracting, but if no understanding is reached the carrier may nevertheless proceed with said contracting, and the organization may file and progress claims in connection therewith.
Nothing in this Article IV shall affect the existing rights of either party in connection with contracting out. Its purpose is to require the carrier to give advance notice and, if requested, to meet with the General Chairman or his representative to discuss and if possible reach an understanding in connection therewith.
For reasons discussed in Award 10 of this Board, the Carrier's argument that the Organization must demonstrate that covered employees must perform the disputed work on an exclusive basis is rejected. The disputed work - operation of backhoes and trackhoes - is classic maintenance of way work and falls "within the scope of the applicable schedule agreement" as contemplated by Article IV.
For reasons discussed in Award 13 of this Board, we find the Carrier met its notice obligations under Article IV. The notices specify the location and identifies the type of work to be performed and further identifies the equipment to be used.
SBA 1130, Award 22
M. R. Jatzlau, et al.
Page 3
The Organization was sufficiently put on notice of the Carrier's intentions in order to allow the Organization to adequately discuss the matter in a conference.
However, while we find that the Carrier met its Article IV notice obligations, we do not find that the Carrier met its conference obligations under Article IV. The notices were dated June 12, 1998. Asserting it did not receive complete notification until June 28, 1998 the Organization did not request a conference until June 30, 1998. On July 10, 1998, the Carrier declined to meet asserting that "... the fifteen (15) days [under Article IV) has expired. Therefore, the Carrier will not conference the two notices dated June 12, 1998." Simply put -and putting aside whether the Organization did not receive the Carrier's notices until June 28, 1998 or on some earlier date - Article IV does not contain the 15 day period for the Organization to request a conference as asserted by the Carrier. The 15 day period is the minimum time for the Carrier to give notice to the Organization ("... the carrier shall notify the General Chairman of the organization involved in writing as far in advance of the date of the contracting transac-
tion as is practicable and in any event not less than 15 days prior thereto."). The only obligation specified in Article IV on the Organization is for the Organization to ask for a conference. If the Organization does so, the Carrier must "promptly" meet ("If the General Chairman, or his representative, requests a meeting to discuss matters relating to the said contracting transaction, the designated representative of the carrier shall promptly meet with him for that purpose."). Again, there is no 15 day period in the negotiated language in Article IV for the Organization to request a conference. If the sophisticated negotiators who constructed Article IV desired such a result and their having placed that 15 day restriction on the Carrier, one would expect that they would have done the same for the Organization. Clearly, they did not do so. When the Carrier refused to meet after the Organization requested a conference, the Carrier therefore violated its obligation under Article IV to "promptly meet". A violation of Article IV has been shown. i
i Had the Carrier met its conference obligations as requested and had the
SBA 1130, Award 22
M. R. Jatzlau, et al.
Page 4
mandatory"). Through the persistent filing of claims, the Organization has put the Carrier on notice that it intends to enforce that language. This Board has repeatedly acknowledged that a point exists where the Carrier's reliance on the Organization's prior willingness to permit contracting of such work would no longer shelter the Carrier from liability in cases where the Carrier does not give the required notice. See Third Division Award 32338
The contracting of work in this case occurred after the 1991 admonitions from this Board that when the Carrier thereafter failed to give notice as required by Article IV, the Carrier could be liable for more than only compensation for furloughed employees. Award 32338 and the awards cited therein therefore require the imposition of remedial relief irrespective of whether the involved employees were furloughed. See also Third Division Award 28513 quoted in Award 32338 (imposing such relief "... where the Carrier failed to the degree demonstrated by this record to follow the previous admonitions of this Board over the requirement to give notice").
We recognize that the result in these cases where no notice is given may be anomalous. It may well be under Article N that had the Carrier given notice, (and because of lack of skills of the employees, need for specialized equipment, etc.), the Carrier may have been able to contract the work. However, in failure to give notice cases, even though the Carrier may have ultimately been able to contract the work, even employees who were working could be compensated only because notice was not given. We are very conscious of that result. But, our function is to enforce language negotiated by the parties. In Article IV and as a result of negotia-
SBA 1130, Award 22
M. R. Jatzlau, et al.
Page 5
tions, the parties set forth a process of notification and conference in contracting disputes. The Carrier's failure to follow that negotiated procedure renders that negotiated language meaningless. This Board's function is to protect that negotiated process . ...
The same conclusion is warranted where, as here, the Carrier fails to meet its conference obligations under Article IV for work contracted out in 1998. As in Third Division Award 32862, by refusing to meet with the Organization, the Carrier similarly frustrated the negotiated conference provisions under Article IV. Claimants are therefore entitled to make whole relief 2
The fact that the Carrier may have met with the Organization in October. 1998 with respect to other notices does not change the result. Under Article IV, the Carrier's obligation is to "promptly meet". After refusing to meet, agreeing to meet over three months later is not "prompt". In any
The claim shall be sustained. Claimants shall be compensated in accord with the Agreement provisions based upon the number of hours worked by the contractor's forces. The matter is remanded to the parties to determine the amount of relief Claimants shall receive.