AWARD NO. 31 CASE NO. 31

SPECIAL BOARD OF ADJUSTMENT NO. 1130

PARTIES ) BROTHERHOOD OF MAINTENANCE OF WAY EMPLOYES
TO )
DISPUTE ) UNION PACIFIC RAILROAD COMPANY (FORMER MISSOURI
PACIFIC RAILROAD COMPANY)

STATEMENT OF CLAM

Claim of the System Committee of the Brotherhood that:


1. The Agreement was violated when the Carrier assigned outside forces (Neosho Construction) to perform routine Maintenance of Way machine operator work (operate backhoe in connection with covering rail at crossings) between Mile Posts 158 and 166 on December 9, 10 and 11, 1998 (System File MW-99110/ 1178759 MPR).


2. The Agreement was further violated when the Carrier failed to furnish the General Chairman with proper advance notice of its intent to contract out said work or make a good-faith effort to reduce the amount of contracting, as provided in Article IV of the May 17, 1968 National Agreement and the December 1 1 , 1981 Letter of Understanding.



OPINION OF BOARD
The Organization focuses upon a notice sent by the Carrier dated November 2, 1998 listing 10 locations and mile post indicators which stated:

This letter is to advise that Missouri Pacific d/b/a Union Pacific Railroad, intends to contract work to an outside company for backhoe, dump truck, brush-hog, crane and chainsaw with operators and traffic control support services in connection with construction and repair of road crossings to assist company forces in the performance of their work. This work will be performed from December 1, 1998 through December 31. 1998, at the following locations.

SBA 1130, Award 31

S. C. Lewis

Page 2


Place: ...



According to the Organization, conference was held November 24, 1998. A contractor performed the work on the dates set forth in the claim.

For reasons discussed in Award 10 of this Board, because of the November 7, 1997 Implementing Agreement, the treatment of mixed practices for contracting out disputes on the Carrier as opposed to other predecessor properties shall govern.

Further, for reasons discussed in Award 10 of this Board, the Carrier's argument that the Organization must demonstrate that covered employees must perform the disputed work on an exclusive basis is rejected. The dis-


puted work - operation of a backhoe - is classic maintenance of way work and falls "within the scope of the applicable schedule agreement" as contemplated by Article IV.

For reasons discussed in Award 13 of this Board, we find the Carrier's notice met its obligations under Article IV. The notice specifies the location and identifies the type of work to be performed and further identifies the equipment to be used. The Organization was sufficiently put on notice of the Carrier's intentions in order to allow the Organization to adequately discuss the matter in a conference.

With respect to the particular work in dispute, the evidence shows that in the past the Carrier has contracted out this type of work. The evidence further shows that covered employees have also performed this type of work. Given that demonstrated mixed practice and as we discussed in Award 10, the well-developed body of decisions involving the Carrier requires a finding that the Carrier did not violate the

SBA 1130, Award 31

S. C. Lewis

Page 3


Agreement when it contracted out

the disputed work.



AWARD










Chicago, Illinois

Dated: 2' z9- 4z

i See e.g., Third Division Award 32867

where similar operation of a backhoe was contracted out ("... the kind of work involved in this dispute has been contracted out in the past ...."). See also, Award 13 of this Board (involving the contracting out of "operation of] backhoes to install crossings and switches").