C AWARD No, 29
0 NRAB DOCKET N0. CL-$564
P CASE N0. 28
Y SSU FILE R-51-1031-7
BRC FILE Nft-27-32
SPECIAL BOARD OF ADJUSTMENT N0. 169
PARTIES) The Brotherhood of Railway and Steamship Clerks
TO )
DISPUTE) St. Louis Southwestern Railway Company
STATEMENT OF CLAIM: Claim of the System Committee of the Brotherhood:
(1) That Carrier violated the Clerks? current Agreement when it required
certain employees in the Recheck Bureau of the Freight Accounting Department, Tyler,
Texas, to suspend work on their regular assigned positions and perform work of
an entirely different character than covered by their assignment.
(2) That the following employees each be paid an additional three days at
the straight time rate of their regular position on April 129 13 and 16, 1951;
John J. Wallis, H. M. Griffies, Dan O?Connor, C. J. Stocker, Ralph Pool and
E. T. Edwards.
(3) That the following employees in the Interline Department each be reimbursed at penalty rate for three days: S. C. Boynton, Fd. Seydler, T. B. Sword,
H. D. Speaks, John L. Bailey and E. R. Williams.
FINDINGS: Claim is made that Recheck Clerks were taken off of their regular
assi;nments and used to assist the Interline Clerks in getting out
their monthly report, Allegation was made by the employees that there was a deadline that the reports had to be gotten out by the 16th of the month and that when
these Recheck Clerks were moved over to assist the Interline Clerks on the 12th,
13th and 16th in getting out the report that it was done for the purpose of absorbing overtime.
At first glance it looked as if the statement of the employees might be
correct. Evidence was submitted to the Board showing that getting the reports
out by the 16th of each month was not compulsory and that if they had not been
gotten out on the 16th no overtime would have been worked but the work carried
over until they could have completed it.
It appears from all the Board has been able to ascertain that the 16th
of the month was not an absolute deadline that the reports had to be mailed out on
that date; also that no overtime was ever employed in getting out these reports,
that if they were not gotten out by the 16th they were gotten out some days later
but it was the desire of the Carrier to get them out by the 16th and in most instances Interline Clerks get them out by that date.
There are numerous Awards which have been submitted to the National
Railroad Adjustment Board dealing with the language contained in current agreement
Rule No. 32-10, reading:
dEmployees will not be required to suspend work during regular
hours to absorb overtime.!?
Many Awards have held that taking an employee off of his regular assignment to
assist another is an indication that overtime would have been worked had that not
been done, but later awards have held that the absence of proof that overtime would
have been worked rebuts any presumption to that effect. Safe think the evidence in
this case indicates, regardless of whether or not the Recheck Clerks had been
used in this instance, that no overtime would have been worked by the Interline
Clerks had they not been assisted to get it out on the desired date; the Interline
Clerks would not have worked overtime but'would have done it on the following days.
To be consistent with that line of awards, we would be driven to the conclusion
that no overtime would have been worked and no overtime as such was absorbed. We
are driven to the conclusion from the facts in this case that no overtime wotkld
have been worked had this not been done, and under a long and consistent line of
holdings we cannot presume that overtime was absorbed as apparently none would
have been worked in this instance. Therefore, there is only one conclusion that
we can reach in this case and that is that there was no violation of the agreement in this instance.
Award No. 29
AUARD: Claim denied,
/s.! W, E. Straubin;er
W. E. Straubinger, Employee Member
DISSENT ATTACHED
/s/ Frank P. Dounlass
Frank P. Douglass, Chairman
Tyler, Texas
April 15, 1957.
/s/ L. C. Albert
L. C. Albert, Carrier Member
EMPLOYEE PSi2BERVS DISSENT TO A4dARD N0. 29
The Award states:
;?At first glance it looked as if the statement of the employees
might be correct. Evidence was submitted to the Board showing
that getting the reports out by the 16th of each month was not
compulsory and that if they had not been gotten out on the 16th
no overtime would have been worked but the work carried over
until they could have completed it.;?
It is assumed the evidence referred to is that shown in Carriers Submission on
pages 20 and 21, stating:
~4lithout prejudice to its position that Rule 32-10 applies only
when there is an actual suspension of work during assigned hours,
the fact remains that no overtime would have been i'm rked if the
assistance in question had not been rendered. Overtime was not
necessary to get out the work.·t
From page 2 of Carrier9s Oral Argument:
~iIn view of the foregoing, it is readily apparent that the 16th
of each month was by no means a ?deadline date? for the forwarding of interline accounts. Carrier was reasonably certain that
if they were mailed on this date, then wren the most distant carriers
would receive their interline settlements by the 20th, and there
would be no necessity of wiring the figures to any of them. Thus,
the 16th was not a ?deadline date? but was set as the date the interline settlements should be forwarded, not from necessity, but as the
most desirable ?due out? date for these interline accounts.-P
Emphasis supplied
From page
9
of Carriers Brief dated October 12, 1956:
ipThe conclusion that it was not necessary to use the recheck clerks
is correct. This was only one of several methods available as pointed out above.
UThe assistance given helped the interline clerks through a heavy
peak in the work, and was the common, practical method of keeping
the work current in event the interline clerks began falling behind
in such peak period.vt (Emphasis supplied)
During the course of the hearing before the Board on April 15, 1957, Mr. Sterling
Baker, General Auditor, gave testimony which corroborated Carrierts above quoted
statements.
Carriers evidence shows that the 16th of the month was the date it desired its
Interline Clerks to complete and mail out the Interline Accounts since it stated
the 16th was not a deadline date %?but was s'et as the date the interline settlements should be forwarded, not from necessity, but as the most desirable ?due
out? date for these interline accounts.vt
Employee Memberts Dissent to
Award No. 29
On page 2 of Employees' Brief dated October 1, 1956, we stated:
~ITf Carrier did not have to mail out the accounts and summaries on
the 16th; why were the six Recheck Clerks taken from their regular
assignments to perform Interline Department work? The obvious
answer is that the Interline Department
Clerks could not perform
the work by April 16th, without working overtime,which overtime
was absorbed by using the six Recheck Clerks.0
During the course of the hearing, the above quoted question was repeatedly asked
of Carrier Representatives, and at no time did they attempt to answer same. The
work involved could not be left to accumulate, but as stated by Carrier:
P'The assistance given helped the interline clerks through a heavy
peak in the work,
'.`%~f.~t
On April 15, 1957, 1-1x'. Joseph Griser, Head Clerk, Interline Bureau, testified
before the Board he had worked in that Bureau for thirty-eight years and had been
Head Clerk for about sixteen years. He stated the 16th of the month was the date
his men were expected to complete and mail the Interline Accounts, and that it
was very unusual when the work was not completed on the 16th.
The Employees presented information to the Board to the effect that during the
year 1955, Interline Bureau Summaries were mailed to foreign roads as follows:
I-loath Reporting Da a Mailed
January February 15th
February March 17th Thursday)
March April 18th Monday)
April May 13th
may
June 15th
June July 15th
July August 15th
August September 16th
September October 17th (Monday)
October November 16th
November December 14th
December January 17th (Tuesday)
The above indicates that in eight months the Summaries were mailed on or before
the 16th of the month; that in three months they were mailed on the 17th, and in
one month on the 18th. These figures indicate that Carrier had instructed its
employees to make every effort to have the Summaries completed and mailed on or
before the 16th.
On-the date involved in our claim the work could not have been completed by April
16, 1951, without the aid of the six Recheck Clerks.
- 2
Employee Memberps Dissent to
Award No. 29
The final paragraph of the Award contains this statement:
4Yde think the evidence in this case indicates, regardless of whether
or not the Recheck Clerks had been used in this instance, that no
overtime would have been ua rked by the Interline Clerks had they not
been assisted to get it out on the desired date; The Interline Clerks
would not have worked overtime but would have done it on the following days.0
The above is a presumption on the part of the Board. Carrier has admitted that
the 16th of the month was the
desired date for mailing the Interline Summaries.
Evidence by the Employees, which was not contradicted by Carrier, showed that the
Interline Department for many years has consistently completed and mailed Interline Summaries on or-before the 16th of the month. It should not be open to
debate that in April, 1957-, the month involved in our claim, Carrier desired the
work completed by April 16th, and used the six Recheck Clerks in order -'to get
it out on the desired date.0
Numerous Third Division Awards were cited by the Employees in support of our claim,
and the following are quoted as being particularly pertinent:
Award 5625, Referee Francis J. Robertson:
Mw*
In the absence of any evidence to the contrary, prior awards
of this Board appear to raise a presumption that overtime is absorbed by suspending an employe from his regular assignment to work
another over an extended period. However, the presumption disappears
in the light of evidence and in this instance Carrier shows by affirmative evidence that the work of Claimant's position, or of the
position he worked during the period involved in the claim, could
have been permitted to accumulate for a month or more
rd
thout~ore-
judice to Carrierfs business; and that it would not have been
necessary to have ordered overtime if Claimant had not been temporarily assigned to the lower rated position. It follows that in
this instance the effect of the temporary assignment was not to
absorb overtime and therefore, a denial award is required.'?
(Emphasis supplied)
Award 7094, Referee Edward F. Carter:
;This evidence clearly indicates that a condition existed which required that certain work be done as soon as possible and that the
Bureau did not desire it to be accumulated for processing at some
future time. This is clear evidence that overtime would have been
required to get this work done promptly. We think, therefore, that
the use of the Traveling Agents, when all the evidence is considered,
was to absorb the overtime work of the City Auditors. Awards 4499,
4500, 4646, 4690, 4692, 6153. The last cited award is particularly
in point with the present cased
-3-
Employee Memberps Dissent to
Award No. 29
Award 6153, Referee Mortimer Stone:
"Accordingly we think Carroll could not properly be assigned to
perform the work at the Tea Company warehouse. Before the Board
the Bureau no longer relies on Rule 43, the Preservation of Rate
rule, but insists that Carrollfs assistance at the Tea Company
warehouse was not for the purpose of avoiding overtime. It is
admitted that the work had fallen behind and that the help was
3iven so that it could be brought up to date. Ile can only say,
as this Board has repeatedly said before, that we must ascribe
to parties the intent to do that which normally and logically
results from their aets.0
This Award is clearly in error. For all of the reasons shown, I dissent from an
erroneous
conclusion.
/s/ Id. E. Straubinger
W. E. Straubinger, Employee Member