AVARD NO. 121
Docket No. 121
SPECIAL BOARD OF ADJUSTMENT NO. 279
BROTHERHOOD OF MAINTENANCE OF WAY EMPLOYES
versus
MISSOURI PACIFIC RAILROAD COMPANY
STATEMENT
OF CLAIM:
Claim of the System Committee that:
1. Carrier violated the effective working Agreement
between the MoPacific RR Co. and the BMWE by
having the Miller-Stauch General Contractor Inc., build
a new freight house facility in East Bottoms, Kansas
City, Mo. This work commenced on or about
October 29, 1964.
2. Carrier shall now pay the following named furloughed
B&B employes at their respective pro rata rate for an
equally proportionate share of the total man hours consumed
by the Contractor's forces in the building of this facility:
E. P. Taylor
H. L. Jones
E. R. Glaze
W. A. Anderson
W. G. Lamar
E. J. Ballew
J. A. Anderson
G. F. Petre
W. J. Stehle
FINDINGS:
There is no provision in the agreement- respecting the
contracting of new construction projecs, the scope rule is
general in nature and has been held not to reserve such work, because it
does not describe or define any work coverage.
Thus it is necessary to examine the prior practice of the
parties under the agreement. It is apparent that in some cases buildings
have been constructed by Carrier's forces and in other cases they have
been constructed by contractors. This practice has not reserved the work
solely to Carrier's work force, but is consistent with the exercise by the
Carrier of a managerial right and responsibility to build or contract.
AWARD NO. 121
Docket No. 121
Historically the Carrier built a freight house facility at
St. Louis with its work force. Picketing by building trades unions delayed
the work and escalated the cost. When Carrier decided to build a distribution yard at Kansas City it obtained agreement by high level union officials on the distribution of work between its forces and the building trades,
but that agreement was without prejudice to anyone's future rights.
Many of the structures cited by the Employes as being built
by them were, part of that project and hence cannot establish a precedent.
Moreover the question of whether the Carrier had forces available to accomplish the job cannot be determined solely from the availability of a few
laid off B and B mechanics. One must also take into account the kinds of mechanics,
and the engineering, supervisory, and procurement forces needed to accomplish the work.
The Kansas City freight facility was a large, complex construction project involving an underfloor chain-conveyor system, air conditioning, plumbing, and lighting. Considering the size of this project and
the Carrier's unhappy experience at St. Louis in attempting to build a similar
project, it cannot be said that its decision to contract the Kansas City project
was unreasonable.
Hence no agreement-violation appears and the claim must be
denied.
AWARD
: Claim denied.
SPECIAL BOARD OF ADJUSTMENT NO. 279
Dudley E. W ' ing » Chairm
i.
A. J. ingham
0
ploye Member n .- Carrier Member
December 12, 1974
File: 247-4170