File 890518


Parties Brotherhood of Maintenance of Way Employes
to and
Dispute Union Pacific Railroad Company
(Former Missouri Pacific Railroad

Statement
of Claim: BMWE - (1) Carrier violated the rules of the Agreement, when
Carrier engaged on the property a contractor performing
various work.

        ,(2) Claim in behalf of Messrs. Hoskins, et all for eight (8) hours per wdrk day including one day at the overtime rate between March 1, 1.989 and April 8, 1989.


        Carrier - The claim as described by the Union, reads as follows:


        "I am presenting a time claim by and in behalf of the below listed furloughed employees, who retain seniority on the Missouri division:


        D. R. Hoskin 354-44-7416 Trackman Driver

        W. J. Bathon 334-46-9862 Trackman Driver

        M. J. Cushman 327-46-2741 Machine Operator


        From Wednesday, March 1, 1989, through Saturday, April 8, 1989, the carrier had on the property at various locations on the Missouri division, a private contractor, Tweedy Brothers, from Pocahontas, Arkansas, engaged in performing various work which was that of the MofW employees. The contractor had on the property a back-hoe, two (2) dump trucks, with operators for each performing the below listed work:


            3-1 to 3-13 Location: Sparta, IL. MP 56.7

            Work: Repairing Derailment,

            Removing Track

            3-14 to 3-23 Location: Ziegler Coal Company

__ Work: Installing Road Crossings
3-24 to 4-8 Location: Coulterville, IL. MP 49
Work: Repairing Derailment
Installing Cross Ties
Remove, and Install
Switch,
Removing Siding
                        -2- Award No. 478


        The above listed work was performed by the contractors five (5) days per week, at eight (8) hours per day, for a total of 28 days, at the straight time rate, and one (1) day at the overtime rate, for Saturday, April 8, 1989."


        (The foregoing statement of claim is quoted from a letter

        dated April 27, 1989, from Assistant General Chairman Barker

        of the Brotherhood of Maintenance of Way Employes (Carrier's

        Exhibit "A") to Superintendent Barnes. It is used in this

        su mission solely for identification purposes, and its

        quotation does not constitute an adoption thereof by the

        Union Pacific Railroad Company.)


        Findings: The Board has jurisdiction of this case by reason of the parties Agreement establishing this Board therefor.


        This dispute appears to be not the usual dispute over contracting or "farming" out work. The facts involved as indicated by the above claim differ. The Employees assert the work was performed over 28 days. The Carrier asserts that it was performed over 8 days.


          The Employees assert that:


        "The rules of the current Agreement were violated when the Carrier assigned outside the scope of the Agreement contractor to perform work on the Missouri Pacific Railroad in the area of Sparta, Illinois, MP 56.7 and Coulterville, Illinois in performing maintenance of way work.


        The Carrier assigned outside contractor to perform work at various locations on the Missouri Division. The outside contractor, Tweedy Brothers from Pocahontas, Arkansas, had on the Missouri Pacific property 1 backhoe and 2 trucks with operators performing this work.


        The Carrier has the following employes that were furloughed from their positions:


          D. R. Hoskin - Trackman/Driver Furloughed W. J. Bathon - Trackman/Driver Furloughed M. J. Cushman - Machine Operator Furloughed


        The above employes hold seniority on the M. P. Missouri District. (Employes Exhibit A and B)


        The Carrier contends that this work does not fall within the guidelines of our Agreement. However the work of this character has customarily, traditionally and historically been performed by maintenance of way employes and is

                  -3- Award No. 478


contractually reserved to them under the provisions of the scope rule,..."


    Whereas the Carrier asserts that:


"A contractor, Tweedy Contractors, Inc., was used by the Company to perform service on 8 different days within the time frame covered by this case. Specifically, on March 24, 27, 29, 30, 31, 1989, and also April 3, 4 and 5, 1989, Tweedy worked for the company. On March 24 a backhoe, dozer, a 12 yard dump truck, and a 6 yard dump truck with operators were used at Sparta to repair derailment damage. The same equipment and operators were used at Sparta to continue the derailment repairs on March 27 and 29. On March 30, Tweedy employed the same equipment plus an air compressor and spiking hammer at Sparta. Once again four operators were involved and the crew spent the day removing and hauling ties. The following day, March 31, the same crew spent the day replacing and hauling ties. Then on April 3, 4 and 5 the same crew, working with a backhoe, dozer and two 12 yard dump trucks, removed and replaced ties at Sparta (Carrier's Exhibit "B"L.


The work performed at Ziegler Coal Company took only 2 days and not 10 days as alleged by the Organization in their April 27, 1989 letter (Carrier's Exhibit "Moreover, that work was done at the direction of the coal company, not by order of the railroad. The work was also paid for by the coal company and not the railroad. Therefore, the work at Ziegler Coal Company had no connection with the railroad and provides no basis for a grievance.


As a final comment, it should be noted that contracting in this instance was driven primarily by the fact that the company did not have the necessary equipment."


This issue of contracting out has been previously disputed on this property. NRAB Third Division Award No. 16459, involving these parties (BMWE and the TP portion of the former MOP) found:


"The question to be resolved is whether the scope rule confers upon the organization exclusive right to perform the work done by the contractor.


The scope rule is general in nature, and does not specifically reserve the work in question. It neither describes or defines the work covered by the agreement, but only governs 'the hours of service and working conditions' of the classes of employes listed therein, and there is no prohibition in the agreement against contracting out. See

                  -4- Award No. 478


Award 10585 (Russell) (same parties). It therefore follows that where the scope rule of the agreement does not delineate the work covered, the employes have the burden of proving such exclusive past practice. This the organization has failed to do to the exclusion of all others.


The record clearly establishes that some clearing of the right-of-way has been performed by the maintenance of way forces and independent contractors have performed some of the work in question. In our opinion, the parties have acquiesced in such partial performance and contracting out by the other. Therefore, as stated in Award 5120 (Carter):


'...The parties by their mutual interpretation of the applicable rules, have recognized the right of each to perform the work and, likewise, they have recognized that neither group has the exclusive right to. We adhere to the interpretation which the parties themselves have made. It has become the fixed contract of the parties which can be changed by negotiation, but not by this Board. No basis for an affirmative award exists.'


The burden of proving such exclusive, customary and traditional work by the maintenance of way forces has not been sustained."


Carrier Exhibit "F" indicates that its Exhibits "L," "M," "N," "0," "P" and "Q" involved the past practice on contracting out in instances covering "cleaning up debris," "crossing work," "picking up scrap," "track dismantling," "track work" and "equipment rental." Hence, as pointed out in Third Division Award No. 28574 involving "contracting out"!


"This Board has required a demonstration of work performance by custom, practice or tradition in order to sustain a contracting-out violation. Here, the Organization offered no evidence whatsoever that its employees performed this work in the past, while the Carrier vigorously asserted that there has been a longstanding practice of using outside contractors to perform the work in question. Given this state of the record, we must conclude that the Organization has not met its burden of proving the essential elements of its claim."


Here, as there, and for the same reasons, the claim will be denied.

                        -5- Award No. 478


Award: Claim denied.

                                D .~


. A. on s, Jr , ployee Member D.-A. Ring, Carr er tuber

                  rthur T. Van art, L airman

                  and Neutral Member


Issued August 27, 1991.