SPECIAL BOARD OF ADJUSTMENT N0.
287
PARTIES: BROTHERHOOD OF MAINTENANCE OF WAY EMPLOYES
and
THE BALTIMORE AND OHIO RAILROAD COMPANY
AWARD IN DOCKET No. 1
STATEMENT
· "Claim of the System Committee of the Brotherhood that:
OF CLAIM:
(1) The Carrier violated the effective Agreement when, on Saturday,
December
20, 1952,
it allocated the work of repairing and/or replacing of the
crossing gate arms at Potee Street, Brooklyn, Baltimore Terminal to employes not
covered under the scope of the Carrier's Agreement with this Brotherhood;
(2)
Carpenters M. M. Crim and John Blair each be allowed four
(4)
hours' pay at their time and one-half rate account of the violation referred to in
part one (1) of this claim."
FINDINGS: Initially we have in this Docket the Third Party Notice issue raised
in Carrier's original submission to the Third Division. It also
appears in several other dockets pending before this Board.
Part Second of Memorandum Agreement, between the Baltimore and Ohio
Railroad Company and the Brotherhood of Maintenance of Way Employees, creating this
Special Board of Adjustment, provides that this Board "shall have jurisdiction to
hold hearings in respect to those claims (Attachment A) and to render awards thereon x x x.'
We are thus empowered to hold hearings in respect to these claims and
to render awards thereon, irrespective of any third-party issue which may appear in
the submission before us.
We shall proceed to the merits of this claim which is properly before
us.
We have here a question from the Carrier as to whether or not this case
has been timely filed by the Committee within the meaning of the time limit provision of Article V
(2)
of the August
21, 1954
Agreement.
Organization's letter of intent to file was dated December
29, 1955,
and does meet the requirement of the August
21, 1954
Agreement. The claim is properly before us. Award
7850.
The work involved in this claim is that of "repairing and/or replacing
of the crossing gate arms at Potee Street, Brooklyn, Baltimore Terminal." Organization claims that on December
20, 1952
"two Signal Department Mechanics were called
out to repair or renew the crossing gate arms" in question.
The grade crossing in question was constructed in
1947.
There is present in this record letter dated April
15, 1953,
from
Carrier's Manager labor Relations to Organization's General Chairman which admits
DOCKET N0. 1
that "the work of replacing or repairing these gates was initially handled by carpenters working under your agreement x x x."
It being abundantly clear that from the time of their construction in
1947
to December 20, 1952, the work of replacing or repairing the crossing gate arms
on this particular crossing was handled by Employees under the Maintenance of Way
Agreement, it is equally clear that Carrier's action of December 20, 1952, in
assigning this particular work to employees not covered under the scope of the
Carrier's Agreement with the Brotherhood here involved was a violation of that
Agreement.
What we are here deciding is "the work of repairing and/or replacing
of the crossing gate arms at Potee Street, Brooklyn, Baltimore Terminal," and nothing
more.
In sustaining this claim, however, we will follow those decisions of
the Third Division which hold that claims based on work not performed can be at pro
rata only.
AWARD
Part (1) of Claim sustained.
Part (2) of Claim sustained at pro rata only.
(s) Edward A. Lynch
Edward A. Lynch
Chairman
(s) A. J. Cunningham
A. J. Cunningham
Employee Member
Dated at Baltimore, Md.,
this 28th day of March, 1960.
(s) T. S. Woods
T. S. Woods
Carrier Member