SPECIAL BOARD OF ADJUSTMENT N0. 287
PARTIES: BROTHERHOOD OF MAINTENANCE OF WAY EMPLOYES
and
THE BALTIMORE AND OHIO RAILROAD COMPANY
AWARD IN DOCKET N0. 22
STATEMENT
OF CLAIM: "Claim of the System Committee of the Brotherhood that:
(1) The Carrier violated the effective Agreement when it assigned the
work of constructing an extension to Bridge 23235 to a General contractor whose
employes hold no seniority rights under the provisions of this Agreement.
(2) Each of the Bridge and Building employes on the seniority district
where the work was performed be allowed pay at his respective straight time rate for
an equal proportionate share of one thousand two hundred eighty (1,280) man-hours
consumed by the contractor's forces in performing the work referred to in Part (1)
of this claim.
FINDINGS: This case involves Bridge 23235 which was part of a major project
involving two other bridges in the Valley of the Little Wabash River
with which we are not here concerned. It involves extending Bridge 23235 from
125 feet in length to 272 feet. -
The aggregate estimate cost of this 3-bridge project was $554,000.
B&B forces handled the supporting work necessary on the project. Carrier elected to
have the permanent construction work done under contract.
On August
6,
1957, Carrier executed a contract with the Steel City
Contracting Company for the work on this bridge, and one other not here involved.
Carrier argues that this was "a job of considerable magnitude. In
addition, this project required equipment which the Railroad did not possess. The
work required the placing of steel sheet piling, and the work had to be arranged
carefully so as to assure completion before the spring flood season."
The claim, like those of several other contract cases before this
Board, arose because of Carrier action -- occasioned, Carrier argues, by the "1957
recession" -- in furloughing B&B forces in February of 1958. Organization states
the B&B forces on the St. Louis Division "were abolished except for one or two carpenters. x x x while the work referred to in this claim was being assigned to and
performed by an outside contractor."
However drastic was the furloughing, the fact remains it was done by
the Carrier long after the contract here involved was executed. Organization made
an eloquent plea here, as it did in the other contract cases before this Board, on
the basis of equity and justice.
The fact remains, however, that the parties negotiated an agreement
which exempts from the coverage of the agreement "work which is to be performed
sBAag9
DOCKET N0. 22
under contracts let by the Company" under "any one or more" of
6
circumstances which
we now hold, and have held, may exist at the time such contract is let.
We can only, then examine this negotiated right of the Carrier in the
light of the evidence in this record on which it relies.
It is unnecessary to analyze all six circumstances.
of them is sufficient.
At page
344
of the Transcript of the hearing held by this Hoard is what
we deem substantial evidence that employees covered by the Agreement on the seniority
district involved were fully engaged and could not, under the situation faced by the
Carrier at that time, be assigned to the work without impeding the progress of other
projects.
Thus Carrier action can now be held to be sufficiently justified under
paragraph
6,
among others, of (b)5(a). It will be so held.
"Any one or more"
Claim denied.
(s) Edward A. Lynch
Edward A. Lynch
Chairman
_(s) A. J. Cunningham
A. J.
Cunningham
Employee Member
(s) T. S. Woods
T. S. Woods
Carrier Member
Dated at Baltimore, Maryland,
this 28th day of March,
1960.